Lawrence v Ciantar
[2020] NSWCA 89
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2019-11-28
Before
Bathurst CJ, Meagher JA, Gleeson JA, Henry J
Catchwords
- CONTRACTS - Construction - Interpretation - Principles of construction of commercial contracts.
Source
Original judgment source is linked above.
Catchwords
Judgment (20 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the judgment] The respondents, the registered proprietors of a property in Forestville, received council approval to subdivide their property into three lots. Various conditions needed to be satisfied prior to the issue of a construction certificate, including engineering plans for the design and construction of certain matters. Around early March 2014, the respondents advertised the property for sale. The appellant entered into negotiations with the respondents under which he proposed to carry out the works to complete the subdivision. The appellant was a licensed builder, but the conditions on his licence did not permit him to carry out the whole of the construction work necessary to complete the subdivision. On 24 October 2014, the respondents' lawyer wrote to the appellant's lawyer to summarise what had been agreed upon in prior correspondence and outstanding points. A letter dated 29 October 2014 from the respondents to their lawyer stated that the parties had agreed to proceed "in similarity to what you have set out in your letter" of 24 October 2014. On 12 November 2014, the parties met and executed the "November Agreement", incorporating what was said to have been agreed upon on 29 October 2014. The agreement set out that a share transfer for a one-third share of the property would be executed, and that an unregistered second mortgage "as to the works of $435,000 which is applicable to the existing D/A approval" would also be executed. A caveat was to be provided "in favour of the Mortgage … in support of this agreement to secure any monies by [the appellant] or his nominees". It also set out that on completion of the works the transfer would be provided to the appellant and registered. Another clause set out various preliminary works "that [the appellant] shall proceed to carry out" prior to any major works. On 26 March 2015, the parties re-executed the November Agreement. There was a delay in the completion of the subdivision works to be carried out by the appellant. The appellant's lawyer asserted that the delay was due to the respondents wishing to pursue a four lot subdivision. He stated that the appellant had undertaken to perform works necessary to obtain the subdivision approval of 3 blocks, and that the cost of the works were the appellant's liability. There was further correspondence. The respondents purported to rescind the contract under the Home Building Act 1989 (NSW). The appellant sought declarations that he held a one-third interest in the property, that he held an unregistered mortgage or charge over the property, and that the agreements had not been validly terminated. He also sought specific performance or damages in the alternative. The appellant's claims were dismissed by the primary judge of the Equity Division of the Court. Various grounds of appeal were raised by the appellant, involving the terms of and construction of the contract, that there was no variation of the contract, that preparatory work did not fall within the provisions of the Home Building Act, that there was no valid termination of the contract and specific performance. The Court dismissed the appeal. Was the agreement between the parties that the appellant would carry out the whole of the Development Application works by himself or under his supervision, as distinct from providing funds for the project? (i) Having regard to the well-established principles of construction of commercial contracts, the agreement was that the appellant would carry out the whole of the works by himself or under his supervision. The surrounding circumstances made it clear that it was the parties' intention that the appellant perform the construction work. Sections 7D and 10 of the Home Building Act therefore had the effect of denying the appellant any interest in the property and rendering the contract void: [80], [97]-[118] (Bathurst CJ); [142] (Meagher JA); [143] (Gleeson JA). Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37; Codelfa Constructions Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337; [1982] HCA 24, considered. Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85; [2016] HCA 47; Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544; [2017] HCA 12; Victoria v Tatts Group Ltd (2016) 90 ALJR 392; [2016] HCA 5; Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633; [2014] NSWCA 184; Cherry v Steele-Park (2017) 96 NSWLR 548; [2017] NSWCA 295; Adamastos Shipping Co Ltd v Anglo-Saxon Petroleum Co Ltd (The Saxon Star) [1959] AC 133; [1958] 1 All ER 725; Agricultural and Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57; County Securities Pty Ltd v Challenger Group Holdings Pty Ltd [2008] NSWCA 193; Franklins Pty Ltd v Metcash Trading Ltd (2009) 76 NSWLR 603; [2009] NSWCA 407; Butt v Long (1953) 88 CLR 476; [1953] HCA 76, referred to. Was there variation of the contract? (i) While it may have been theoretically possible for the contract to be varied by conduct such that the appellant's obligation to act as funder was replaced by an obligation to act as builder, there was nothing to suggest that this occurred, as the appellant always had the obligation to act as the builder: [122] (Bathurst CJ); [142] (Meagher JA); [143] (Gleeson JA). Brambles Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153; [2001] NSWCA 61; Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523, referred to. Did the preliminary work fall within the provisions of the Home Building Act? (i) The preliminary work required by the November Agreement did not fall within the definition of "residential building work" under the Home Building Act. This ground of appeal was made out, although as the appeal had failed on grounds 1-5 this conclusion did not affect the result: [123]-[131] (Bathurst CJ); [142] (Meagher JA); [143] (Gleeson JA). Grygiel v Baine [2005] NSWCA 218, considered. Was there a valid termination of the contract? (i) There was a clear intention by the appellant not to be bound by the contract or to perform it in a manner substantially inconsistent with his obligations. Since the appellant was bound to complete the works, the appellant repudiated the agreement and the respondents were entitled to terminate the contract on that ground. [136]-[139] (Bathurst CJ); [142] (Meagher JA); [143] (Gleeson JA). Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623; [1989] HCA 23; Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; [2007] HCA 61, referred to. (ii) The appellant was not entitled to an order for specific performance: [140] (Bathurst CJ); [142] (Meagher JA); [143] (Gleeson JA).