To calculate the Time Factor from the Contract Date for Practical Completion to the completion of rectification works directed in the Interim Award
Part 1 - Delay from Contract Date Completion to Termination ... 29th April 2003 to 16th September 2003 ... 20 weeks
Date of Contract.... 25th July 2002
Schedule of particulars states ... 28 working days to commence
Contractual start date is 25 July 2002 plus 28 working days is ... 27th August 2002
It is recorded that the concrete slab was poured in early September 2002.
The [owners] claim the Contractual Completion Date is ... 1st April 2003
However, from the Contract my calculation for Contractual completion date is 25 July 2002 plus 150 working days to ... 29th April 2003. This date allows for Public Holidays, RDOs and the Christmas Building Industry recess.
Pursuant to Clause 7 of the Building Contract, the Builder is obligated to advise the Owner of any delays and to have approval to extend the Contract Period. This did not occur.
To allow for all the various problems and other claims and counter claims, for the purpose of this item only in the time factor I shall take the completion as the date the [owners] terminated the Contract, took possession and lived in the house, ie ... 16th September 2003
Based on the above details the [owners are] entitled to damages for late completion for the period of 29th April 2003 to 16th September 2003 and is 140 days or 20 weeks, but as there is no allowance for delay defined in the Contract, the Contract does not automatically cover delay or the costs of non-approved delay. (original emphasis)