14 The first draft of the TPA was sent to Mr Amara of the applicant on 9 March 2001 which was a standard document making no reference to the need to reduce the project costs by means of deferring payment for work done by the builder and subcontractors who were agreeable to purchasing apartments to an agreed value. A provision relating to deferral arrangements was inserted in a later draft by the Bank's solicitors on 2 April 2001 as a new cl 8. At a meeting of all the parties held on 4 April Mr Gavranich representing the applicant protested at the insertion of that provision as a result of which a full meeting took place on 4 April in order to negotiate a solution. The draft wording of the new clause would have the applicant responsible to defer some $5,100,000 in payments pending settlement of all contractor (including subcontractors) related apartments. Of this, a sum of $3,100,000 related to subcontractor deferral arrangements (set out in cl 8(b) of the draft) and the sum of $2,000,000 to builder deferrals (set out in cl 8(a) thereof). During the TPA negotiations the $2,000,000 builder sum was corrected by the pre-agreed 10 per cent discount. The builder had no difficulty with the concept of having to defer payment for work done by itself up to a value of $1,800,000 in exchange for its purchase of apartments and accordingly agreed to retain subclause (a) of cl 8 in the TPA to that effect. However, the applicant succeeded in having the subcontractor deferral arrangement provision in cl 8(b) of the draft TPA deleted.