© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2003] VSC 275
Supreme Court of Victoria
2003-07-28
DODDS-STREETON J.
Original judgment source is linked above.
ARBITRATION - Commercial Arbitration - Award - Application for leave to appeal against award of Arbitral Tribunal - Manifest error of law in relation to Arbitral Tribunal's rejection of claimed remedy for breach of contract to construct mining facility - Court's restricted jurisdiction to review arbitral awards - Error must be obvious without need for prolonged adversarial argument - Judge entitled to consider documents incorporated by reference in award - Relevance of technical, complex and ambiguous nature of award - Arbitral Tribunal failed to approach remedy for breach of warranty in accordance with established legal principles - Imposed on victim of breach the onus of establishing its claimed remedy the only one - Manifest error of law more than merely arguable and obvious on face of award - Determination of question of law could substantially affect the rights of one or more parties to the arbitration - Leave to appeal granted - Judge determined appeal instanter - Award and Reasons for Judgment remitted to Arbitral Tribunal - Allegation of technical misconduct on ground that remedy denied on basis of an issue not live or put to the parties not determined, as appropriate relief of remission granted on alternative ground - Allegation that awards of interest involved technical misconduct by reason of denial of natural justice not founded - Allegation that parties denied opportunity to adduce evidence or make submissions in relation to interest not founded - Natural justice or procedural fairness did not require publication of principal findings with opportunity for further submissions on interest.
"`Award' means final or interim award. `Misconduct' includes corruption, fraud, partiality bias and a breach of the rules of natural justice."
"`Interim awards' Unless a contrary intention is expressed in the arbitration agreement, the arbitrator or umpire may make an interim award."
"Judicial review of awards (1) Without prejudice to the right of appeal conferred by sub-section (2), the Court shall not have jurisdiction to set aside or remit an award on the ground of error of fact or law on the face of the award. (2) Subject to sub-section (4), an appeal shall lie to the Supreme Court on any question of law arising out of an award. (3) On the determination of an appeal under sub-section (2) the Supreme Court may by order-- (a) confirm, vary or set aside the award; or (b) remit the award, together with the Supreme Court's opinion on the question of law which was the subject of the appeal, to the arbitrator or umpire for reconsideration or, where a new arbitrator or umpire has been appointed, to that arbitrator or umpire for consideration-- and where the award is remitted under paragraph (b) the arbitrator or umpire shall, unless the order otherwise directs, make the award within three months after the date of the order. S. 38(4) amended by No. 15/1993 s. 16(1). (4) An appeal under sub-section (2) may be brought by any of the parties to an arbitration agreement-- (a) with the consent of all the other parties to the arbitration agreement; or (b) subject to section 40, with the leave of the Supreme Court. S. 38(5) substituted by No. 15/1993 s. 16(2). (5) The Supreme Court shall not grant leave under sub-section (4)(b) unless it considers that-- (a) having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of one or more parties to the arbitration agreement; and (b) there is-- (i) a manifest error of law on the face of the award; or (ii) strong evidence that the arbitrator or umpire made an error of law and that the determination of the question may add, or may be likely to add, substantially to the certainty of commercial law. S. 38(6) substituted by No. 15/1993 s. 16(2). (6) The Supreme Court may make any leave which it grants under sub-section (4)(b) subject to the applicant complying with any conditions it considers appropriate. S. 38(7) repealed by No. 15/1993 s. 16(2). * * * * * S. 38(8) re-numbered as s. 38(7) by No. 15/1993 s. 16(3). (7) Where the award of an arbitrator or umpire is varied on an appeal under sub-section (2), the award as varied shall have effect (except for the purposes of this section) as if it were the award of the arbitrator or umpire."
"Power to set aside award (1) Where-- (a) there has been misconduct on the part of an arbitrator or umpire or an arbitrator or umpire has misconducted the proceedings; or (b) the arbitration or award has been improperly procured-- the Court may, on the application of a party to the arbitration agreement, set the award aside either wholly or in part. (2) Where the arbitrator or umpire has misconducted the proceedings by making an award partly in respect of a matter not referred to arbitration pursuant to the arbitration agreement, the Court may set aside that part of the award if it can do so without materially affecting the remaining part of the award. (3) Where an application is made under this section to set aside an award, the Court may order that any money made payable by the award shall be paid into court or otherwise secured pending the determination of the application."
"Interest up to making of award S. 31(1) amended by No. 15/1993 s. 14(1)(c)(i)(ii). (1) Unless a contrary intention is expressed in the arbitration agreement, but subject to sub-section (4), where the arbitrator or umpire determines to make an award for the payment of money (whether on a claim for a liquidated or an unliquidated amount), the arbitrator or umpire shall have power to include in the sum for which the award is made interest at such rate as the arbitrator or umpire may direct (being a rate not exceeding the rate at which interest is payable on a judgment debt of the Supreme Court) on the whole or any part of the money for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. S. 31(2) inserted by No. 15/1993 s. 14(2). (2) Unless a contrary intention is expressed in the arbitration agreement, but subject to sub-section (4), where-- (a) arbitration proceedings have been commenced for the recovery of a debt or liquidated damages; and (b) payment of the whole or a part of the debt or damages is made during the currency of the proceedings and prior to or without an award being made in respect of the debt or damages-- the arbitrator or umpire may order that interest be paid at such rate as the arbitrator or umpire may direct (being a rate not exceeding the rate at which interest is payable on a judgment debt of the Supreme Court on the whole or any part of the money paid for the whole of any part of the period between the date when the cause of action arose and the date of the payment). S. 31(3) inserted by No. 15/1993 s. 14(2). (3) Without limiting sub-section (2), arbitration proceedings shall, for the purposes of that sub-section, be deemed to have commenced if-- (a) a dispute to which the relevant arbitration agreement applies has arisen; and (b) a party to the agreement-- (i) has served on another party to the agreement a notice requiring that other party to appoint an arbitrator or to join or concur in or approve of the appointment of an arbitrator in relation to the dispute; (ii) has served on another party to the agreement a notice requiring the other party to refer, or to concur in the reference of, the dispute to arbitration; or (iii) has taken any other step contemplated by the agreement or the law in force at the time the dispute arose, with a view to referring the dispute to arbitration or appointing, or securing the appointment of, an arbitrator in relation to the dispute. S. 31(2) re-numbered as s. 31(4) by No. 15/1993 s. 14(3). (4) Sub-section (1) does not-- (a) authorize the awarding of interest upon interest; (b) apply in relation to any amount upon which interest is payable as of right whether by virtue of an agreement or otherwise; or (c) affect the damages recoverable for the dishonour of a bill of exchange." S. 32 amended by No. 15/1993 s. 14(4)(a)(b).
"Interest on debt under award (1) Unless a contrary intention is expressed in the arbitration agreement, where the arbitrator or umpire makes an award for the payment of money, the arbitrator or umpire shall have power to direct that interest at the same rate as that at which interest is payable on a judgment debt of the Supreme Court shall be payable from the date of making of the award or such later date as the arbitrator or umpire may specify on so much of the money as is from time to time unpaid and any interest that so accrues shall be deemed to form part of the award. S. 32(2) inserted by No. 15/1993 s. 14(5). (2) If judgment is entered by the Court in terms of an award, interest shall cease to accrue in pursuance of a direction under this section on the date of the entry of the judgment."
"(1) there is no appeal from an arbitrator on a question of fact;
(2) while s.38 provides that an appeal shall be from the award of an arbitrator on a question of law, leave must nevertheless be obtained unless both parties consent to the appeal;
(3) leave will only be granted in circumstances prescribed in s.38(5);
(4) the applicant for leave must satisfy both para(a) and para(b) of 38(5);
(5) the epithet `manifest' in the expression `manifest error of law' is used to indicate an error which is evident or obvious rather than one which is arguable;
(6) if the court determines that there is no manifest error of law, an application based on this ground fails;
(7) if the court is satisfied that a manifest error of law exists, a question arises whether the court should, in the exercise of its discretion, grant leave; and
(8) assuming that there is not a manifest error of law on the face of the award, it may be argued that there is strong evidence that the arbitrator made an error of law and the determination of the question may add, or may be likely to add, substantially to the certainty of commercial law. This requirement indicates that the question should be one of wider and greater importance than, for example, the construction of a one-off clause in the context of the particular agreement between the parties."[2]
"The added requirements of manifest error of law on the face of the award or strong evidence that the arbitrator made an error of law and that the determination of the question may add substantially to the certainty of commercial law suggest that the draftsman was seeking to constrain the exercise of control over arbitral awards in the manner described by the House of Lords in The Nema. A manifest error on the face of the award may be an error which would be apparent to the judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument."[13]
"In applying s.38, as amended, a construction that would promote the purpose or object underlying the Act must be preferred to a construction that would not promote that purpose or object ... The expression `error of law on the face of the award' is one of a type well-known to courts. The award having been examined, the question is whether there is apparent (and such is the denotation of the word `manifest') an error of law. `Manifest error' is an expression sometimes used in reference to reasons given by judges or the approach taken by juries ... It is used to indicate something evident or obvious rather than arguable .... The matters referred to by Lord Diplock in The Nema remain important factors in determining whether leave should be given. However, I have difficulty in defining the significance of an error of law by reference to whether it is apparent to a judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument. I understand the views expressed that decisions on questions of law should be left to the arbitrator with minimal interference by the courts unless the arbitrator may be establishing an erroneous precedent on a matter of law which may affect other cases between other parties, as, for example, where the question concerns the construction of a contract in standard terms. But the paragraph requires a determination as to whether or not there is a manifest error on the face of the award and I do not see why a judge should be required to do that without adversarial argument. If the judge concludes after argument that there is not such an error of law an application based on this ground fails ... There is nothing, in my opinion, in the language of the sub-section or in any other material, to which consideration can appropriately be given pursuant to the terms of the Interpretation Act which would allow the judge to proceed to determine the application without hearing argument. However, as McHugh JA pointed out "manifest" in the context of the sub-section, which contemplates the grant of leave before an appeal can be pursued, connotes an error of law which is more than arguable. There should, in my opinion, before leave is granted be powerful reasons for considering on a preliminary basis, without any prolonged adversarial argument, that there is on the face of the award an error of law".[15]
"An error on the face of the award is not to be discovered by looking behind its back. It is not permissible to treat the limited jurisdiction by which a court ensures that an arbitration is conducted in accordance with law as if it were the equivalent of an appeal from an arbitrator's decision."[17]
"Obviously, there is difficulty in the word `manifest'. What may be `manifest' to one judicial officer may fail to persuade another. The criterion cannot be the swiftness of mind of the sharpest intellect. Nor can it be the perception of one whose whole career has been devoted to examining and reflecting upon building contracts. An objective, not a subjective, test for what is `manifest' is contemplated. But the word will not go away. Against the background of its history in this context it requires swift and easy persuasion and rapid recognition of the suggested error."[20]
"If however, the decision or direction given is expressed in terms which are to such a degree referential that, without reading a document referred to, it is not possible to understand what has been decided or directed, or not possible to give effect to the decision or direction, then the document should be treated as incorporated in the award. Again, if the decision or direction is expressed to be based upon the wording of a specified clause of a contract, the clause is incorporated ... How matters stand where the decision or direction is expressed to be based not upon the wording or effect of any specified clause, but upon the wording or effect of the contract as a whole, or of the provisions of the contract relating to a particular subject matter, is debatable; but the weight of authority supports the view that in such circumstances the contract, or the relevant part of it, is incorporated."[22]
"To my mind, however the court is in any event entitled to look at those documents when seeking to interpret the interim award on a broader ground. As regards an interim award, ... it seems that in a case such as the present the court must normally be entitled to look at those documents in order to see exactly what was submitted to the arbitrators as being the preliminary issues to be decided, so as to ensure that the court's interpretation of the award is correct. The documents in question are to my mind in the circumstances analogous to that submission to arbitration which a court can always look at in relation to any application to set aside a final award."[27]
"Misconduct is not necessarily personal misconduct. If an arbitrator for some reason which he thinks good declines to adjudicate on the real issue before him, or rejects evidence which, if he had rightly appreciated it, would have been seen by him to be vital, that is within the meaning of the expression `misconduct' in the hearing of the matter which he has to decide and misconduct which entitles the person against whom the award is made to have it set aside."[33]
"..misconduct in this context was used only its technical and often misleading sense. No one suggests, or could suggest, the smallest deviation from the strict path of honour. But the word `misconduct' as employed in this connection includes even a mistake in procedure which has or may have unjustly prejudiced a party."[36]
"We are concerned with a case where the arbitrators appear mistakenly to have thought that the issue of the width of the turning place was one which had been raised before them and upon which they were entitled to decide the case, without drawing the point to the attention of the charterers. With great respect to the very experienced arbitrators who presided at the hearing, on this they were mistaken. I wish to stress that we in this Court have had the advantage of looking at the matter very clearly on a full transcript with the assistance of leading Counsel and having the benefit of full argument directed towards this very point, which has, no doubt, made it easier for us to assess the position; but the fact remains that the award was made on the basis of a point which was never raised as an issue or argued before the arbitrators. There is plain authority that for arbitrators so to decide a case, without giving a party any warning that the point is one which they have in mind and so giving the party no opportunity of dealing with it, amounts to technical misconduct and renders the award liable to be set aside or remitted... It truth, we are simply talking about fairness. It is not fair to decide a case against a party on an issue which has never been raised in the case without drawing the point to his attention so that he may have an opportunity of dealing with it, either by calling further evidence or by addressing argument on the facts or the law to the tribunal. In my judgment, the arbitrators in the present case failed to give that opportunity to the charterers in respect of an issue not raised in the arbitration that the turning space at the entrance to the dock was insufficiently wide. It follows that they committed technical misconduct of the kind I have described. I say this in no spirit of criticism of these three very experienced arbitrators. Expressions such as `misconduct' and `breach of the rules of natural justice' carry overtones whicih are frequently unjustified. Here, it appears that there may well have been some misunderstanding on the part of the artibtrators; but the fact remains that, in the result, there was unfairness to the charterers." [41]
"That rights of appeal were intended to be restricted was emphasised by the Minister for Industry, Commerce and Technology (Mr. Cathie) in his Second Reading Speech when the Commercial Arbitration Bill was debated in Parliament in September 1984 (Hansard, vol. 375, Legislative Assembly, 13 September 1984, p.434). The Minister then said: `The new commercial arbitration system is intended to supplant the jurisdiction of the Court where an agreement permits arbitration as a means of dispute resolution. It will encourage the development of a speedy and economical means for resolution of disputes by experts in their field'. This theme was echoed in the Attorney-General's second Reading Speech in the debate on the Commercial Arbitration (Amendment) Bill in March 1993 (Hansard, Vol. 410, Legislative Asembly, 11 March 1993, pp.171-172). Mrs Wade noted that clause 16 of the Bill inserted a new s.38(5) into the Commercial Arbirtration Act. This was intended to restrict judicial review of awards by the Supreme Court. The Attorney continued: `The reasons for restricting judicial review of awards by the Supreme Court are: (a) to provide for uniformity across Australia; and (b) if arbitration is not to be viewed as a dry run before litigation it was thought that more restictive criteria are desirable. The underlying policy is that in most cases the parties should have to accept as final the decision of the arbitrator they have chosen to decide the matter in the first place'."[46]
THE PARTIES' CONTENTIONS ON THE FIFTH AUTOCLAVE DECISION
(1) The Arbitral Tribunal did not find a contractual warranty of an extraction rate of 95% in the autoclaves. Rather, it found two discrete contractual warranties. First, a warranty that 3.75 million tonnes of ore could be processed per annum. Secondly, a warranty that 45,000 tonnes of nickel could be produced per annum. There was no finding of a single warranty that 45,000 tonnes of nickel could be produced from 3.75 million tonnes of ore and no more.
(2) The extraction rate of 95% referred to in the Interim Award was not found to be a contractual warranty. Rather, it was found to be a design criterion, a variable, which, like the ore quality (1.35% of nickel content) and the density (39%) and the 3.75 million tonnes of ore (as a minimum) and the retention times, could be varied or adjusted.
(3) The Arbitral Tribunal did not find that the discrete contractual warranties it recognised were breached. Rather, its reasoning in relation to throughput and production under separate heads indicated that Anaconda had not proved that:
(a) an annual throughput of 3.75 (and more) million tonnes of ore could not be achieved by various adjustments. The most significant requirement for achieving the minimum throughput was running the autoclaves in "catch up" mode for lengthy periods;
(b) 45,000 tonnes of nickel for sale per annum could not be produced.
(4) On the basis of that reasoning, the Arbitral Tribunal concluded that Anaconda had not discharged the onus of establishing that either the throughput warranty or the production warranty had been breached.
(5) Thus characterised, the Arbitral Tribunal's reasoning in relation to throughput and production was not speculation as to why Anaconda should not receive its claimed remedy for breach of the warranty asserted by Anaconda. Rather, it was justification for the finding that there was no breach of either of the warranties identified by Fluor.
(6) The "simple calculation" in paragraph 13.69 of the Interim Award referred to by the Arbitral Tribunal in relation to production is not incorrect, but treats the 3.75 million tonnes as a variable (upwards), the 39% density as a variable, and the extraction rate as a variable, which could be mutually adjusted in order to produce the 45,000 tonnes of nickel.
RELEVANCE OF COMPLEXITY OF THE INTERIM AWARD
"The present proceedings concern an award which was made after 145 days of hearing and in respect of which the Arbitrator's Reasons are some 350 pages in length. It cannot be that the complexity of the matter precludes the court from arriving at the conclusion that there is a manifest error of law on the face of the award."[48]
"The tension between the application of the principle of swift recognition of the error, and the necessity, in what are frequently complex cases, to argue and demonstrate the error is not always simple to resolve. Some penetration of the intellectual process and legal analysis is bound to be necessary."[50]
(1) On 21 August 1997 Anaconda entered the EPC Contract and the CARUA Contract with Fluor. [para 1.03]
(2) Anaconda considers that Fluor has breached both the EPC Contract and the CARUA Contract. [para 1.05]
(3) The claims dealt with in the Interim Award include Anaconda's pleaded contention 3.5.5.8. [para 3.02(1)(c)]
(4) The claims are summarised to include "rectification costs for defective works alleged to constitute breaches of the EPC Contract. Rectification claims within the scope of the January hearings will be dealt with in Section 7 - 13 of this Award". [para 3.06(A)]
"Subject to Clause 6.5, the Contractor must construct the Facility in accordance with the requirements of the Contract and:
(a) the Revised Scope Book and the documents issued by the Owner under Clause 8.7;
(b) any Design Documents which comply with the requirements of the Contract and which the Contractor is entitled to use for construction purposes under Clause 6.4; and
(c) any Direction of the Project Manager given or purported to be given under a provision of the Contract, including any Variation directed by the Project Manager by a Variation Order ... "
"4.29 Exhibit 1 to the EPC Contract comprises the Revised Scope Book together with its attachments including The Project Scope Book of 31 January 1997 (referred to in these Contentions as the `original Scope Book'), indexes of drawings, data sheets and PDS Arrangements, Specifications Lists and an index of Design Criteria and Equipment List.
4.30 These documents contain design criteria and specifications that define the detailed requirements of the contract referred to in the EPC Contract. The index of design criteria specified in Attachment C to the Revised Scope Book cross-refers to the detailed design criteria included at Volume 2 Part 8 of the original Scope Book, which in turn is derived from the metallurgical mass balance prepared by Fluor. Anaconda relies on these detailed design criteria as the performance standards by which Fluor's design and construction of the Facility is to be judged.
4.31 When the individual sections of the Facility are considered in detail these performance criteria will be addressed in more detail but as an indication of the performance of the Facility as a whole it is worth recording that the requirement was for the Extraction Plant to operate for the equivalent of 340 days of the year at design capacity, thus enabling the Facility to process 3.75 million tonnes of ore and produce a nominal output of 45,000 tonnes of nickel and 3,000 tonnes of cobalt."
"The Arbitral Tribunal accepts that the Mass Balance cannot be read as a literal requirement for the operation of the Facility. The same goes for the moisture content of feed, given that no means of control is included in the design. However, given Fluor's acceptance that the Facility was to be capable of processing 3.75 mtpa (dry) of blended ore, there must be an implicit minimum or average rate at which the ore is to be processed, bearing in mind the needs of maintenance. Those needs are set out in precise detail within Section 4.3 (Acid Leach Availability) in volume 1 of the original Scope Book. The availability of the Facility (and necessary maintenance time) must be regarded as subject to some degree of variability. This cannot, however, be of much comfort to Fluor since any reduction in the achievable rate of production would lead to fewer days being available for maintenance operations, and would require enhanced reliability. The details of the PDC and Scope Book, and the interrelationship among availability, reliability and productivity, are examined further in Section 13."
"13(A) Introduction 13.01 Anaconda asserts that as a result of inadequacies in the design of the plant, Area 3200 will never be capable of achieving the contractual output of nickel and cobalt. It claims the cost for one or possibly two additional autoclaves which it says are necessary to achieve an output of 45,000 tonnes of nickel and 3,000 tonnes of cobalt in a year from a throughput of 3,750,000 dry tonnes of ore. 13.02 According to Mr Burvill, Anaconda appointed GRD Minproc in early 2000 to design a 5th train. The concept was to acquire a larger autoclave than autoclaves 1 to 4 with a capacity greater than necessary to make up for the alleged shortfall. Mr Burvill (and Anaconda in its Statement of Contentions) claimed only a percentage of the cost. Mr Burvill explains that limitations in other areas led to the abandonment of this approach. It was not pursued in the hearing. Anaconda now claims the whole cost of whatever size of autoclave it is entitled to. 13.03 In its Closing Submission, Anaconda quantified its claim, which arises from Contention D.3.5.5.8, as being in an amount between A$53,731,000 and A$206,851,000, depending on the size of the fifth autoclave to be constructed."
(a) that the area be capable of operating for 93.15% of the year;
(b) that the area be capable of processing 3,750,000 dry tonnes of ore per year;
.....
(f) that certain operating conditions of the autoclaves be achieved;
(g) that the following extraction rates be achieved
(i) Ni (nickel) 95%
Co 92%
"The rates of recovery are the rates that Anaconda could expect to achieve if a blended ore generally in the proportions set out in the PDC for Area 3100, containing minerals within the range of proportions listed in a slurry containing 39% solids and at a throughput of 115 dry tonnes per hour of ore, were fed through the Facility at the temperatures and pressures and other conditions specified. No test data has been adduced to demonstrate that a T15 blend would produce 95% nickel - but that was Fluor's problem."
"The introduction to Volume 1 of the Scope Book contains the following statement: "The project design is based upon a capacity of 3.75 Mt/a (dry) feed to the acid leach circuit and a nominal production rate of 45,000 t/a nickel and 3000 t/a cobalt."
"In its opening submissions, Fluor accepts the contractual obligation to design and engineer and construct a plant with a capacity of 3,750,000 tpy (in specified conditions, but claims that the meaning of `nominal' is that found in the Oxford English Dictionary `existing in name only, in distinction to real or actual; merely stated or expressed without reference to reality or fact'. It is, says Fluor (Opening 181) `calculated' as opposed to `specified'."
"As a matter of calculation, if the annual throughput is 3,750,000 tonnes, and if it is possible to deliver ore to the design percentage of nickel of 1.35% (Area 3200 PDC), and the design recovery is 95%, then total recovery per year in Area 3200 will be 48,094 tonnes Ni per year. This is the model assumed in the Mass Balance (stream 435 - see Sefton para. 25). If, however, the proportion of nickel in ore was the design minimum of 1% (Area 3200 PDC section 8), the tonnage produced will be 35,981 tonnes. These figures require adjustment to take account of downstream losses. Thus, 48,094 tonnes would be reduced to about 45,000 and there would be proportional reductions in the lower figure."
"The Arbitral Tribunal accepts that `nominal' does not mean `specified'. The only sensible interpretation of the obligations created by the EPC Contract, and thus by the Scope Book, is to state the output expected in given conditions. Thus, when Fluor warranted that its design would satisfy the requirements of the EPC Contract it warranted that if the Facility was fed ore meeting design specification (including nickel content) at the density and blend (T15 not OC3) specified at the rates of throughput necessary to process 3,750,000 tonnes per year to an Area 3200 operating under design conditions, then the tonnage of nickel available for sale would be in the order of 45,000 tonnes."
"There is limited disagreement as to the effect of reducing retention time from 90 to 80 minutes. Dr Dreisinger claims that it would result in a drop of 1%. Dr Sefton says it would be between 1% and 2%. If, therefore, the Facility is being run at 110% catch up for nearly all the time when all 4 autoclaves are running, and at 120% or 130% when 3 or less are running, then a reduction of at least 1% must be expected in addition to the 92% recognised by Fluor as the best that might be achieved. If, as a result of the addition of another screen in Area 3100, the slurry concentration is increased to 41%, the Arbitral Tribunal assumes that a reduction of 1.5% will occur, allowing for the current retention time being some 95 minutes (see above). With these factors in mind, a simple calculation can be undertaken as follows, taking the design throughput, the design concentration of nickel, an increase in slurry density from 39 to 41% and a level of recovery of 90.5%.
3,750,000 x 1.35% x 41/39X90.5% = 48,165 tonnes
48,165 tonnes of nickel will reduce to about 45,000 tonnes after losses downstream of Area 3200."
"But neither fact is of itself sufficient to satisfy the heavy burden which lies upon Anaconda to show that after remedial work has been completed the only means to achieve capacity is to expend a minimum of some A$50 million."
"in accordance with the contract and the plans and specifications which formed part of it, and her damage is the loss which she has sustained by the failure of the [builder] to perform his obligation to her. The loss cannot be measured by comparing the value of the building which has been erected with the value it would have borne if erected in accordance with the contract; her loss can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give her the equivalent of a building on her land which is substantially in accordance with the contract. ... The qualification, however, to which the rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. ... As to what remedial work is both `necessary' and `reasonable' in any particular case is a question of fact."
"closely approximated its actual costs, it was for [the respondent] to show why some further adjustment of the figure was necessary ... Only if the respondent introduced into the debate some new or additional occasion for adjustment were it for [the appellant] to go beyond the proof it adduced of the excessive profit which [the respondent] had received. Especially was that so where the appellant demonstrated not only that there was a very wide discrepancy between profit in fact earned and 5% of actual costs incurred but also that any productivity gains during the period when [the respondent] asserted that they were made were not `significant'. It was not enough for [the respondent] to answer this evidence by saying that there might have been some other unidentified reason for its profit being as large as it was, or by pointing to the possibility of adopting some other method of assessing [the appellant's] damages. Yet in essence it was these two propositions that underpinned the Full Court's conclusion that the appellant had not proved the amount that it had lost as a result of [the respondent's] breach."[59]
"Another way of viewing the respondent's submissions in the Full Court and this Court is as a plea in the nature of a plea in mitigation of damages. The onus in this regard lies upon the party seeking the reduction."[62]
"17 INTEREST 17.01 Both Parties claim interest on sums to be awarded in respect of wasted past expenditures. Anaconda claims simple interest on past rectification costs at a uniform rate of 10%, which it contends is reasonable in light of the interest rate provided by the EPC Contract for overdue payments. Anaconda's approach is consistent with the variable but generally higher rates claimed by Fluor, which alternatively claims comparable rates of simple interest in accordance with the Commercial Arbitration Act 1984 (Vic) s.31 and the Penalty Interest Rates Act 1983 (Vic). 17.02 The Arbitral Tribunal has determined in Section 16 that a single award should be issued covering claims by each Party. Anaconda, as the net creditor, is entitled to set-off. The adoption of Anaconda's simpler uniform interest rate on the net sums due to Anaconda operates, over-all, to Fluor's advantage. The Arbitral Tribunal therefore accepts and adopts Anaconda's claim for interest at 10%, which will be applied to sums awarded to both Anaconda and Fluor. The effect of set-off is that interest is applied to the net sum standing to Anaconda's credit up to 1 September 2002. 17.03 Anaconda has provided a Schedule (Closing Schedule 1) of rectification expenditure, with interest calculated from the end of the month following the date on which it was incurred. The Arbitral Tribunal accepts it as accurate. To the extent that Fluor's liability for those expenditures is established, the Arbitral Tribunal accepts Anaconda's contentions as to the dates from which interest should run on sums found to be due. 17.04 The Parties subsequently agreed quantum of some items (see Paragraph 11.14). No agreement was made on interest, but the Arbitral Tribunal considers that interest on the sums agreed can be properly assessed pro rata. 17.05 The Arbitral Tribunal appreciates that the interest component of amounts awarded could in theory be refined by reviewing all the excluded elements of the relevant claim and establishing separate dies a quo in each case. But even this exercise would be inexact (for example, invoice dates are not payment dates) and no greater accuracy would be obtained. Accordingly interest has been calculated by maintaining the proportion of interest computed on the principal amounts claimed as against that computed on the principal amounts awarded. ... 17.07 In consequence, interest on past costs recovered by Anaconda is awarded in a total amount of A$13,729,663 broken down as follows: Anaconda Contention D.2.5.6 A$4,126 Anaconda Contentions D.3.5.6 and D.3.5.6.1 A$10,980,504 ... Anaconda Contention D.3.5.1.3 A$90,296 Anaconda Contention D.3.5.1.4 A$49,591 Anaconda Contention D.3.5.2.1 A$243,502 Anaconda Contention D.3.5.2.3 A$79,736 Anaconda Contention D.3.5.5.6 A$156,713 Anaconda Contention D.3.5.2.4 A$852,508 Anaconda Contention D.3.5.5.7 A$44,212 Anaconda Contention D.3.5.5.4 A$373,261. 17.08 Interest on sums due to Anaconda as liquidated damages, as determined in Section 14, is awarded in the amount of A$6,475,949, assessed by the Arbitral Tribunal as follows: (1) On A$5,000,000 from 1 March 1999 amounting to A$1,750,000; (2) On A$5,760,000 from 1 May 1999 amounting to A$1,920,000; (3) On A$19,806,700 from 1 April 2001 amounting to A$2,805,949. 17.09 Interest with respect to Anaconda's partially successful TPA claim (see Paragraph 15.83) is awarded in the amount of A$2,083,000. (Lacking a sensible basis for making further refinements, the Arbitral Tribunal has proceeded on the footing, favourable to Fluor, that the entirety of the loss occurred in June 1998). 17.10 Interest on Fluor's claims is computed by adopting the starting date proposed by Fluor (13 January 2000), leading in the Arbitral Tribunal's determination to an amount of A$22,412,858."
(1) Unless a contrary intention is expressed in the arbitration agreement, but subject to sub-section (4), where the arbitrator or umpire determines to make an award for the payment of money (whether on a claim for a liquidated or an unliquidated amount), the arbitrator or umpire shall have power to include in the sum for which the award is made interest at such rate as the arbitrator or umpire may direct (being a rate not exceeding the rate at which interest is payable on a judgment debt of the Supreme Court) on the whole or any part of the money for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.
(2) Unless a contrary intention is expressed in the arbitration agreement, but subject to sub-section (4), where--
(a) arbitration proceedings have been commenced for the recovery of a debt or liquidated damages; and
(b) payment of the whole or a part of the debt or damages is made during the currency of the proceedings and prior to or without an award being made in respect of the debt or damages--
the arbitrator or umpire may order that interest be paid at such rate as the arbitrator or umpire may direct (being a rate not exceeding the rate at which interest is payable on a judgment debt of the Supreme Court on the whole or any part of the money paid for the whole of any part of the period between the date when the cause of action arose and the date of the payment).
(3) Without limiting sub-section (2), arbitration proceedings shall, for the purposes of that sub-section, be deemed to have commenced if--
(a) a dispute to which the relevant arbitration agreement applies has arisen; and
(i) has served on another party to the agreement a notice requiring that other party to appoint an arbitrator or to join or concur in or approve of the appointment of an arbitrator in relation to the dispute;
(ii) has served on another party to the agreement a notice requiring the other party to refer, or to concur in the reference of, the dispute to arbitration; or
(iii) has taken any other step contemplated by the agreement or the law in force at the time the dispute arose, with a view to referring the dispute to arbitration or appointing, or securing the appointment of, an arbitrator in relation to the dispute.
(a) authorize the awarding of interest upon interest;
(b) apply in relation to any amount upon which interest is payable as of right whether by virtue of an agreement or otherwise; or
(c) affect the damages recoverable for the dishonour of a bill of exchange.
(1) Unless a contrary intention is expressed in the arbitration agreement, where the arbitrator or umpire makes an award for the payment of money, the arbitrator or umpire shall have power to direct that interest at the same rate as that at which interest is payable on a judgment debt of the Supreme Court shall be payable from the date of making of the award or such later date as the arbitrator or umpire may specify on so much of the money as is from time to time unpaid and any interest that so accrues shall be deemed to form part of the award.
(2) If judgment is entered by the Court in terms of an award, interest shall cease to accrue in pursuance of a direction under this section on the date of the entry of the judgment."
"The power to award interest which is invested in the courts ... and arbitrators is an adjectival one which enables the tribunal, be it court or arbitrator, to do more complete justice between the parties than would otherwise have been possible. It is not designed to compensate the party for loss arising out of a cause of action but to provide compensation for the circumstance that money has been outstanding to a party for a period of time. It is, of course, trite that the power should be exercised in a manner that achieves substantial justice between the parties. Save for observing that under s.31 of the Act there is no power to award interest upon interest, there would not seem to me to be any specific procedure which should be followed by an arbitrator when a claimant succeeds in its claim and its opponent succeeds in a counterclaim. In cases in which that occurs (and where there is no contractual entitlement to interest) it would be open to an arbitrator, as it seems to me, to award each party interest on the amount it successfully claimed and then balance one figure against the other. Alternatively, the arbitrator may deduct the amount allowed to one party from the amount allowed to the other and award interest on the balance. The adoption of one approach rather than the other would not, in my view, involve error of law. Is it different where one party is entitled to interest upon part of the amount awarded pursuant to the contract between the parties? I think not. It would, in my view, have been open to the arbitrator to allow the respondent interest under s.31 of the Commercial Arbitration Act 1984 in respect of part of the amount the respondent was held entitled to and interest under the contract in respect of the progress payment. Likewise interest could have been awarded to the appellants under the Act on the amounts to which they were found to be entitled,. In those circumstances the ultimate amount awarded would reflect the balance between the two claims. Such an approach would not, in my opinion, have involved error of law."[76]
Interest on Fluor's claims is computed by adopting the starting date proposed by Fluor (13 January 2000) leading in the Arbitral Tribunal's determination to an amount of A$22,412,858.
(a) The Owner is not obliged to pay the Contractor interest on the Approved Security.
(b) ...
(c) ...
(d) If the Owner makes a call upon the Approved Security and obtains cash as a consequence, the Owner shall be obliged to pay interest on the amount of any cash payments in excess of the sum to which the Owner is entitled at the time of such call. The sum attracting interest will be further reduced by any unsatisfied amounts which subsequently become payable by the Contractor to the Owner, at the time such amounts become payable.
For the above reasons, and rejecting all claims and contentions to the contrary, the Arbitral Tribunal hereby:
(A) DECLARES that Fluor owes Anaconda the total sum of A$147,606,926 (one hundred forty-seven million six hundred six thousand nine hundred twenty-six Australian Dollars), being the total of the following amounts:
to which have been added (and included in the aforementioned total amount) interest in the following amounts.
(B) DECLARES that Anaconda owes Fluor the total sum of A$107,795,176 (one hundred seven million seven hundred ninety-five thousand one hundred seventy-six Australian Dollars), being the total of the following amount:
85,382,318 (per Paragraph 16.39) to which has been added interest in the following amount
(C) DECLARES that Anaconda's debt to Fluor is offset by its larger entitlement against Fluor. (D) ORDERS Fluor therefore forthwith to pay to Anaconda the amount of A$39,811,750 (thirty-nine million eight hundred eleven thousand seven hundred fifty Australian Dollars), and that interest thereon is payable, from the date of this Interim Award, at the same rate as that at which interest is payable on a judgment debt of the Supreme Court; any interest that so accrues shall be deemed to form part of this Interim Award.'
[1] BC9400868, unreported, Supreme Court South Australia, 11 November 1994.
[3] BC 200204450 [2002] VSCA 113.
[10] [1992] 26 NSWLR 203 at 217.
[11] [1982] AC 724 at 742G-743A.
[13] [1992] 26 NSWLR 203 at 222.
[19] BC9402554, unreported, New South Wales Court of Appeal, 26 May 1994.
[42] [1998] VSC 40 (21 August 1998).
[44] BC9102985, unreported, Supreme Court of New South Wales, 16 August 1991.
[46] [1998] VSC 40 (21 August 1998) at 26.
[47] [2003] VSC 85 (24 April 2003).
[49] BC 990 7849, unreported, Supreme Court of Victoria, 29 November 1999.
[55] [2003] HCA 10 (March 11, 2003).
[72] Arbitral Tribunal Communication No.63
[73] BC9201605, Supreme Court of New South Wales, Court of Appeal, 11 September 1992
Anaconda Operations Pty Ltd
Fluor Australia Pty Ltd [2003] VSC 275
(1991) 105 FLR 304
(1968) 41 ALJR 307
(1954) 90 CLR 613
(1996) 67 SASR 28