© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[1998] VSC 40
Supreme Court of Victoria
1998-08-21
HARPER, J.
Original judgment source is linked above.
"All of the call statistics used in my calculations are from Telecom Australia and were supplied under Freedom of Information. They are all exchange based equipment results recorded on TBAX, TIMS and ELMI Smart testing equipment. Whilst extrapolation may contain some variants, Telecom had monitoring and testing equipment on the telephone service for almost 50% of the total 51 month period, and this is sufficient to provide a firm base for assumption and an accurate guide to results."
(i) The arbitrator failed to require Telstra to provide all proper documents.
(ii) The arbitrator failed to allow new evidence to be submitted by the claimants.
(iii) The arbitrator failed to accept late submissions made by the claimants.
(iv) The arbitrator failed to require compliance with rulings and procedure.
(v) The arbitrator failed to provide reasons in the award.
(vi) The arbitrator was unreasonable.
According to the plaintiffs, these failures (whether singly or in combination) amounted to misconduct the effect of which was to vitiate the arbitration.
"1. The liability of Telecom Australia to the claimant[s] in respect of alleged service difficulties, problems and faults in the provision to the claimant[s] of telecommunication services. 2. The adequacy of the amounts paid by Telecom to the claimant[s] under earlier settlements in relation to alleged service difficulties, problems and faults in the provision to the claimant[s] of telecommunication services. 3. The liability of Telecom Australia to the claimant[s] in respect of alleged service difficulties, problems and faults in the provision to the claimant[s] of telecommunication services since the date of the settlement payment for the ... claimant[s'] earlier claims, up to the date of the arbitrator's decision. 4. If Telecom Australia is found liable in accordance with (1) or (3) above, the quantum of compensation payable by Telecom Australia to the claimant[s] for the claimant[s'] proven loss."
"28. Unless a contrary intention is expressed in the arbitration agreement, the award made by the arbitrator or umpire shall, subject to this Act, be final and binding on the parties to the agreement."
"7.5 Without limiting any rights the parties may have to obtain documents or evidence under the Act, either may, upon reasonable notice in writing to the other party, apply to the arbitrator for directions upon any matter in relation to the proceedings including an amendment to the statement of claim, defence or reply, the production of further documents, further particulars of [the] statement of claim, ... defence or reply. Each party is entitled to be heard on any such application. In giving directions, the arbitrator, where appropriate, shall impose time limits for compliance with such directions. On any such application, the arbitrator may not require the production of documents protected by legal professional privilege.
7.6 The arbitrator may by notice in writing require either party to provide any further documentary information and/or particulars which he reasonably considers would assist him."
"Whatever may be the position under the Freedom of Information Act, clause 7.5 of the arbitration procedure provides for you as arbitrator to be able to give directions inter alia relating to the discovery of relevant documents. [We] apply to you for a direction requiring Telecom to make available to [us] unobliterated and exempted copies of all the documents in respect of which it has claimed an exemption other than under the ... legal professional privilege or ... relevance categories. The other grounds of exemption available under the Freedom of Information Act are not available in the course of the arbitration process."
"You have requested that I direct Telecom to make available 'unobliterated and exempted copies' of all documents which you are seeking under the Freedom of Information Act ... In its response, Telecom has indicated that it believes the balance of outstanding documentation sought under FOI will be forwarded to you within a week ... I believe it would be inappropriate for me to intervene in your FOI claim. It may in due course be appropriate for me to issue directions relating to discovery in the context of the arbitration but I believe such an order would at present be premature, particularly in view of the fact that Telecom is currently processing your FOI application and expects that process to be completed shortly. In the circumstance, I am not prepared to issue the directions which you are seeking."
"To assist in this process, the Chairman of AUSTEL lodged Mrs. Garms' FOI application with Telstra on 3 December 1993 and requested that Telstra give priority to the request so that she could use the information in her submission under the Fast Track Settlement Proposal. When the Fast Track Settlement Proposal was developed two of the specified elements were 'speed is of the essence' and 'the review will be primarily based on documents and written submissions'. It is apparent that speed also was an essential element of the Fast Track Arbitration Process, (sic) which replaced the Fast Track Settlement Proposal, as it was signed on 21 April 1994 and the timetable provided that Mrs. Garms would lodge her claim documents by 25 May 1994.
Although my investigation relates to Telstra's actions under the FOI Act, the foregoing is relevant in establishing the reliance Mrs. Garms placed on the FOI process, and the apparent acceptance by the arbitrator appointed under the Fast Track Arbitration Process that the FOI process was an appropriate method for Mrs. Garms to obtain information from Telstra, and is relevant in assessing the impact of Telstra's failure to provide documentation requested under the FOI Act."
"The more recent work of Telstra has shown a heightened awareness of the FOI processing requirement and improved decision making procedures. But in my opinion, had Telstra processed the application correctly at the outset, Mrs. Garms would have received the documents many months earlier and the hours spent by Telstra (and Mrs. Garms) would have been substantially less.
Despite the actions taken to implement my earlier recommendations the processes adopted in the COTs Cases are still characterised by degrees of defective administration. Significantly, further and important documents have recently been discovered and released to Mrs. Garms up to the date of this report (May 1996). These documents were important to ensure an effective and fair Fast Track Arbitration Process."
"I accept that not all documentation relating to all exchanges, including the Fortitude Valley Exchange, is covered by Mrs. Garms' FOI applications; but it is my view that the specific exchange documents which relate to investigation of Mrs. Garms' complaints are covered by the applications, even if she is not named in the documents. It is my understanding that the activities of the Fortitude Valley Exchange, and indeed other exchanges, are critical to the telephone services provided to the Tivoli and to Mr. and Mrs. Garms."
Of course not all documentation relating to all exchanges was necessarily relevant to the issues to be resolved in the arbitration. Equally clearly, documents were not necessarily irrelevant simply because neither the Tivoli Restaurant nor the claimants were named in them. The relevant documents were those which would assist the arbitrator to calculate the rate of call loss to and from the claimants' business: a simple enough proposition, it seems to me, but one which, apparently, nobody involved with the arbitration or with the claimants' FOI applications managed to articulate.
"On 29 May 1996 the claimant (sic) asserted that it would be a grave miscarriage of justice to proceed in the circumstances. Subsequently, between 10 June and 6 August 1996, I received a variety of submissions from the claimant foreshadowing the introduction of new evidence based on material obtained through the intervention of the Commonwealth Ombudsman and expressing general concern about the conduct of the arbitration and participants in it. As part of this award, I propose making a direction in relation to this material. Throughout these proceedings, I have endeavoured to provide the claimants (sic) with as much leeway as possible in submitting late evidence and generally in ensuring that I am able to reach a conclusion based on all the relevant facts. Telstra is, however, entitled to a degree of certainty in the knowledge that submissions by both parties have concluded. By accepting late submissions of evidence, there is a real danger that this arbitration, already greatly protracted, would become almost interminable. This is not in the spirit of the arbitration agreement, nor is it conducive to the finalisation of the arbitration in a just and equitable fashion. Were I convinced that any of the material submitted subsequent to 20 May 1996 was likely to substantially affect my existing view of the evidence or my initial views regarding quantum, I would have had no hesitation in re-opening the proceedings. I have not been convinced, however, that the material submitted or foreshadowed since 20 May 1996 is of this nature. I accordingly direct that no material submitted or foreshadowed by the claimants subsequent to 20 May 1996 is admissible and I note for the record that no such material has been taken into account in the formulation of this award."
"I have throughout the proceedings been concerned to ensure that my function did not become confused with any parallel FOI applications. I have at all times, however, remained willing to order production of appropriate documentation where necessary. I was concerned on the one hand to ensure that all relevant documentation was placed before me, and on the other hand to ensure that I was not overwhelmed by irrelevant or unanalysed material. Whilst I had occasion to order the production of documents by Telstra, for the most part I was able to rely upon its co-operation with requests made by me through the Resource Unit in the course of the Resource Unit's deliberations and also upon assurances by Telstra from time to time that relevant material was in the process of being made available to the claimant (sic) under FOI. I am aware the claimants, (sic) have been concerned at my refusal to order the production of documentation relating to certain exchanges but my rulings in this regard were based upon my opinion that those exchanges were either not relevant to the claim or that the production of the immense volume of documentation being sought was unlikely to materially affect the issues in dispute or the quantification of the claimants' entitlement".
"The claimants' problems were allegedly exacerbated by a virtual disconnection for four days in 1990 due to problems in the exchange and a failure by Telstra, following a change of telephone number in November 1992, to place a voice recorded announcement of the change on the old number until February 1993.
Evidence that the telecommunications service was deficient throughout the period of the claim is said to be found in the fact that a major upgrade of the Fortitude Valley Exchange in September 1993 resulted in an improvement to the Tivoli's telephone service, albeit too late.
The claimants estimate business losses arising out of their telephone difficulties at $8,110,080 less $360,000 paid under a previous settlement, leaving a net total of $7,750,080. The claimants further seek compensation totalling $334,500 for pain and suffering, making the net value of the claim $8,084,580."
"Telstra disputes that the difficulties experienced by the Tivoli were attributable to faults with its telephone service. Telstra dismisses the claimants' technical evidence as unconvincing and as being of little or no probative value. Telstra denies 'a major upgrade' of the Fortitude Valley Exchange occurred in September 1993 and therefore the claim is fundamentally flawed to the extent it seeks to derive support from this event. Telstra submits that the claimants' complaints were extensively tested and investigated in a diligent manner by experienced and appropriately qualified personnel, and most of the complaints were not proven or verified in any way. To the extent that faults were detected, rectification was achieved at a very high level, far in excess of the usual level of service appropriate for similar configurations."
George Close & Associates made much in their analysis of the effect which, according to them, the "major upgrade" had on the Tivoli's telephone service. Equally, Telstra made much of what it claimed was the real reason for a large increase in the number of calls received by the restaurant in the months following September 1993. According to Telstra, this increase did not demonstrate that the system was sub-standard before the upgrade and improved thereafter; there simply was no upgrade. The increase in calls received was, Telstra argued, entirely explicable on the basis of seasonal factors: spring and the pre-Christmas period is the time when the citizens of Brisbane resort to theatre restaurants.
"The report accepted that the COT Cases had each experienced like service difficulties and faults but these faults were 'intermittent and their causes difficult to trace'. Specific reference was made to Telstra's older analogue equipment. The report emphasised, however, that these observations were not necessarily relevant to the determination to be made by me as to whether Telstra had failed to meet acceptable service standards or whether these deficiencies had caused the losses claimed by the COT Cases ...
Specifically in relation to the claimants (or, more precisely, Mrs. Garms), the report makes the following observations:
* the claimants had complained of numerous faults including 'no ring received', 'call drop out', 'incorrect recorded voice announcements', 'false busies' and 'rotary problems';
* the claimants had been pressured into accepting an inadequate settlement (in June 1993) and in any event, had continued to receive an inadequate telephone service subsequent to that settlement;
* Telstra had endeavoured to minimise the seriousness of their complaints, exemplified by an attempt in 1990 to attribute the claimants' problems to their Commander system when at the same time Telstra was aware of problems with the Fortitude Valley Exchange which could also have been responsible for the reported service difficulties."
"Telstra had been requested to give [this] application priority so that the information so gained could be used in the claimants' submissions to this arbitration. The report noted that Telstra had progressively provided documents to the claimants over a period of more than two years, the latest release being in April 1996."
(c) "that some records, considered important by the claimants and other COT members, had either been lost or destroyed" and (d) "this reflected an inadequate record keeping practice by Telstra". The arbitrator continues:
"The report speculates as to certain factors which may have influenced assumptions by me in relation to the process of production of documents by Telstra under FOI. In relation to this arbitration, the Ombudsman expressed concern that the claimants had been disadvantaged financially and personally because of defective administration by Telstra in its handling of applications under the FOI Act."
"In relation to the Ombudsman's report, it is not necessary for me to comment upon her observations concerning these proceedings, save that I am satisfied that, regardless of any difficulties the claimants may have faced in collating material relevant to their submission and irrespective of where the fault (if any) for delayed production of documentation lies, the claimants were ultimately provided with a reasonable opportunity to adequately present their case."
(a) particular (xii): "failing to order production of Telstra files which were ultimately and at a late stage produced by [Telstra] to the Ombudsman under the Freedom of Information Act";
(b) particular (xiii): "in March 1996 accepting the statement of [Telstra] that all documentation had been provided when such was not the case";
(c) particular (xvi): "failing to order appropriate discovery by [Telstra]";
(d) particular (xvii): "on 23 October 1995 ordering only limited discovery by [Telstra] when there were many more documents relevant to the plaintiffs' claim";
(e) particular (xviii): "failing to order [Telstra] to produce all relevant documents to the Resource Unit";
(f) particular (xix): "failing to provide to the Resource Unit all relevant documents";
(g) particular (xxii): "failing to allow evidence to be produced concerning the Central West EMG";
(h) particular (xxiii): "failing to direct that documents held at the Central West EMG in respect to the Fortitude Valley Exchange be produced by [Telstra]";
(i) particular (xxviii): "making a ruling ... in relation to the documents sought to be tendered by the plaintiffs without giving the plaintiffs an opportunity to challenge that ruling prior to a final award being made".
* "[F]or extended periods, calls in the order of two out of three were lost and in some periods almost all calls were lost;
* more than 3,800 faults were reported by the claimants to Telstra during the claim period;
* only 60 job numbers were issued by Telstra in response to these 3,800 fault reports;
* there were more than 3,000 unanswered calls on the old telephone number following the change of telephone number on 18 November 1992 when the telephone service was transferred from the older ARE equipment to the newer AXE equipment at the Fortitude Valley Exchange, due to the fact that Telstra had failed to connect the RVA;
* for three years the Tivoli was omitted from the Yellow Pages listing under "Restaurants";
* for four continuous days (21 May to 24 May 1990), there was no service;
* Telstra records establish that more than 11,800 calls did not result in a ring tone;
* the claimants' Commander system was changed three times until Telstra declared it "fault free" and not the cause of the problems;
* in September 1993, Telstra undertook major upgrading of the Tivoli lines, amounting to an effective complete refurbishment of the 'customer specific' exchange equipment and lines, resulting in call averages rising from 69 per day to 215 per day;
* known call losses occurred between the Fortitude Valley Exchange and the Tivoli - call losses within the host exchange (Fortitude Valley), or occurring exchange-to-exchange would be additional, as would drop outs and fading calls;
* overall, Telstra had inadequately documented faults and tests throughout the claim period."
"The Resource Unit could ... find no basis to support the very high estimates of incoming call losses which underpinned the claimants' quantification of losses. Whilst the claimants had estimated a call loss of 50-65%, the Resource Unit considered a reasonable upper limit of confirmed faults on the basis of material then available would have been in the vicinity of 4%."
"(a) I have reviewed all the material submitted by both parties, together with the results of the independent analysis of that material by the Resource Unit's technical personnel. I accept in essence the conclusions reached by the Resource Unit.
(d) Accepting as I do the essence of the Resource Unit's analysis of the evidence, it follows that I also accept the Resource Unit's estimate that the loss of incoming calls was in the vicinity of 2.7%, significantly lower than the claimants' estimate of up to two thirds of incoming calls lost for extended periods. Obviously this estimate is highly speculative. I note the Resource Unit's concession that the call loss could have been as high as 4% and theoretically higher.
(e) In summary, I accept that the Tivoli had persistent and not insignificant problems with its telephone lines. I accept that the claimants' complaints were not well handled by Telstra, either at a technical or at a PR level. The final question to address is, therefore, the financial impacts of these difficulties upon the claimants' business, and to a lesser extent, the health of Mr. and Mrs. Garms."
"In Telstra' financial response ... dated 16 December 1994, it is asserted that the claimants have no entitlement to compensation. This conclusion is based on a number of factors but essentially reflects a dispute as to the claimants' methodology in calculating their loss, differing views as to viability of the business and differing views as to the existence or the level of compensable call loss. At my request, the Resource Unit made a series of calculations based on a variety of scenarios, taking into account the realistic range of options open to me in the event that I were to accept that the claimants had experienced compensable call loss. As indicated above, I have accepted the essence of the technical findings of the Resource Unit and, in broad terms, its estimate of the likely general call loss over the claim period. Overall, I consider the most realistic estimate of loss in my view was the Resource Unit's 'High Range'. This calculation assumed a general call loss of 4% over the claim period and it further assumed that faults and incidents classified as indeterminate in the Resource Unit's technical evaluation reports were in fact the responsibility of Telstra and that those incidents and faults resulted in loss of profits to the Tivoli. I am mindful, nevertheless, that the general call loss could, according to the Resource Unit, theoretically have been higher than 4% and I acknowledge that the claimants have submitted a considerable amount of material, supported by an expert witness, in support of their contention that the call loss was significantly higher. Accordingly, I have proceeded on the basis of a 6% general call loss throughout the claim period."
"So far as the letter of the Act is concerned, it gives the parties the greatest possible freedom in the conduct of arbitration. Even the requirements of s.22 may be relaxed. The laws of evidence need not be followed ... The sole requirement in the 'letter and spirit' of the Act is the call of natural justice which, whilst requiring that each party may have a proper opportunity of putting its own case, and meeting the case for the other party, does not regard adherence to court procedures as necessary."
"It should be very clear from the commencement that the power under s.42 [of the Commercial Arbitration Act] to set aside [an] award is not to be used as an endeavour or means to overcome the restrictive rights of appeal."
"The new commercial arbitration system is intended to supplant the jurisdiction of the Court where an agreement permits arbitration as a means of dispute resolution. It will encourage the development of a speedy and economical means for resolution of disputes by experts in their field."
"The reasons for restricting judicial review of awards by the Supreme Court are: (a) to provide for uniformity across Australia; and (b) if arbitration is not to be viewed as a dry run before litigation it was thought that more restrictive criteria are desirable. The underlying policy is that in most cases the parties should have to accept as final the decision of the arbitrator they have chosen to decide the matter in the first place."
"Subsequent to my correspondence to you of 24 April 1995 and 1 May 1995 I have consulted Mr. Peter Bartlett ... regarding the progress of our arbitration including the time frame applicable to the finalisation of our claim. I have also sought from my professional advisers legal opinion as to Telecom's conduct in the provision of documents. Contrary to my request for the production of documents and after very careful consideration of all the circumstances, I wish to advise that I will leave the discovery of documents entirely at your discretion in conjunction with the requirements of the Resource Unit."
"On an assessment of the progress of the arbitration and an analysis of the documentation provided by Telstra we can but disagree with the basis upon which Mr. John Rundell [of the Resource Unit] has made the statement in his correspondence to you of 5 September 1995: 'We also had in mind the context in which our statement of 5 June 1995 was made, namely the claimants' concern to find documentation to substantiate a very high proportion of lost calls over the period of the case (whether it be 50% or 57% or 67%). Based on our reviews to that date, we believed that such documentation did not exist.' In the face of conclusive evidence that Telstra has provided incorrect misleading statements throughout the history of the dispute it is a denial of natural justice for the Resource Unit to speculate 'Based on our reviews to date, we believed that such documentation did not exist.' As the Resource Unit had in their requests to Telstra not requested Telstra to provide historic documentation it cannot be conclusively established that the information provided by Telstra is factual when it is not supported by historic documentary evidence."
One must, finally, ask the hard question: what, and where, was the documentation about which George Close & Associates spoke if it was not produced with their report in April 1994?
"In reaching this position, we had the view that any further information that might be sourced from Telecom pertaining to this case ... would be unlikely to contradict the material already provided, to the extent that it would affect the arbitrator's ruling. We also had the view that any documentation the claimant could bring to bear to support her case would already have been presented."
The arbitrator was entitled to rely upon these statements.
"I acknowledge receipt of your facsimile dated 18 April 1996 ... I direct as follows: (1) The claimants' submission in relation to the documentation produced by Telstra during March 1996 is to be made by 1 May 1996; (2) Telstra shall, within a week of receiving the claimants' submission, submit its response to the claimants' submission. My intention is to conclude this arbitration as expeditiously as possible. In doing so, I shall ensure the rights of either party are not materially compromised. I am not satisfied that the outstanding FOI requests to which you refer are of sufficient relevance to warrant a further extension. My current intention is to be in a position to hand down an award on or about 31 May 1996."
"You must appreciate that, in the interests of both parties, I am endeavouring to conclude this arbitration in the spirit of speed and efficiency with which was (sic) the common goal of both parties at the commencement. I do not believe that it is in the interests of either party to pursue documentation which in all probability will be of minimal, if any, relevance to the final outcome and the production of which can only have the effect of delaying the conclusion of these proceedings."
"I have had reservations on the basis that whilst Mr. Garms has clearly experienced an immense amount of anxiety due to the failure of the Tivoli business, clearly there have been factors (as emphasised in this award) other than Telstra's poor service which had contributed to that business failure. To the extent that Mr. Garms has experienced anxiety as a direct consequence of Telstra's poor service, there is a limit to the extent to which Telstra should be held accountable for what appears to me to be something of a pre-occupation by one or two individuals ... Notwithstanding these reservations, I am aware the claimants, particularly Mr. Garms, have suffered considerable distress, and understandably so, as a consequence of Telstra's inability to provide a suitable level of service over a period of many years."
Garms
Telstra Corp. Ltd [1998] VSC 40