CITATION: Modscape Pty Ltd v Francis [2017] TASSC 55
Contracts - Building, engineering and related contracts - Remuneration - Statutory regulation of entitlement to and recovery of progress payments - Adjudication of payment claims - Natural justice - Whether duty to invite further submissions for a second time.
Building and Construction Industry Security of Payment Act 2009 (Tas), s 24(2).
Musico v Davenport [2003] NSWSC 977, referred to.
Judgment Number: [2017] TASSC 55
"[23] Notwithstanding that Modscape conceded the applicability of the Dualcorp principles to the Tasmanian Act, and that my request under section 24(2) of the Act specifically sought submissions on whether the NSW Court of Appeal decision in Dualcorp prevented it from reagitating issues determined by Adjudicator Martin in the Previous Determination, Modscape eschewed doing that. Instead, its submissions focussed on issue estoppel as such and what it described as the 'classic formulation of issue estoppel' of Dixon J in Blair v Curran [1939] HCA 23; (1939) 62 CLR 464 (at pages 531 - 3). In support of that approach it relied on State Water Corporation v Civil Team Engineering Pty Ltd [2013] NSWSC 1879 at para [77] and Caltex Refineries (Qld) Pty Ltd v Allstate Access (Australia) Pty Ltd & Ors [2014] QSC 223 at para [45].
[24] Given the specific terms of my request under section 24(2) of the Act I did not find that approach to be of assistance. There are two reasons for that. The main reason for that is that what Macfarlane JA had in mind in Dualcorp was something less than the operation of the common-law [sic] doctrine of issue estoppel as it is usually understood. [Footnote: as recognised by the decision of Philip McMurdo J in Caltex Refineries (Qld) Pty Ltd & Anor v Allstate Access (Australia) Pty Ltd & Ors [2014] QSC 223 at [54].] Secondly, the requirements for issue estoppel preferred by the Court of Appeal in Dualcorp were not those articulated in Blair v Curran, but those set out in of [sic] the High Court decision in Kuligowski v Metrobus [2004] HCA 34; (2004-2005) 220 CLR 363 at [21] in the following terms:
'21 In his speech in Carl Zeiss Stiftung v Rayner & Keeler Ltd (No 2), Lord Guest, after noting that the doctrine of issue estoppel had been accepted by Australian courts for a number of years, indicated that, for the doctrine to apply in the second set of proceedings, the requirements were:
"(1) that the same question has been decided; (2) that the judicial decision which is said to create the estoppel was final; and, (3) that the parties to the judicial decision or their privies were the same persons as the parties to the proceedings in which the estoppel is raised or their privies".'"
[25] To the extent that State Water and Caltex v Allstate adopt the Blair v Curran approach they do not assist either, and, being decisions of single judges are not to be preferred over the decision of the Court of Appeal in Dualcorp and its reasoning.
[26] Similarly, Stowe's agreement in its section 24(2) comments on Modscape's submissions as to the principles of issue estoppel applying in the adjudication context are similarly affected by Modscape's error.
[27] The enquiry as to what the previous adjudicator indispensably decided, as postulated by Modscape after Blair v Curran, is not one I am required to make."
"I am not persuaded that in order to determine whether the same question has been decided that [sic] it is necessary for me to go beyond the text of the Previous Determination. Indeed, in my view, to go into the parties' submissions in Previous Adjudication seems likely to me to engage in the very mischief which the Dualcorp principal [sic] seeks to eliminate, namely, reagitating issues which were determined in the previous adjudication."
"Long standing authorities, in my opinion, warrant the statement that, as a mechanism I the process of accumulating material for the determination of issues in a proceeding between parties, an estoppel is available to prevent the assertion in those proceedings of a matter of fact or law in a sense contrary to that in which that precise matter has already been necessarily and directly decided by a competent tribunal in resolving rights or obligations between the same parties in the same respective interests or capacities, or between a privy of each, or between one of them and a privy of the other in each instance in the same interest or capacity. The issue thus determined, as distinct from the cause of action in relation to which it arose, must have been identical in each case." [My emphasis.]
"107 ... It may readily be accepted that the Act provides for a somewhat rough and ready way of assessing a builder's entitlement to progress claims. It may also be accepted that the procedure is intended not only to be swift, but also to be carried out with the minimum amount of formality and expense. Nonetheless, what an adjudicator is required to do is to decide the dispute between the parties. Under the scheme of the Act, that dispute is advanced by the parties through their adjudication application and adjudication response (which, no doubt, will usually incorporate the antecedent payment claim and payment schedule). If an adjudicator is minded to come to a particular determination on a particular ground for which neither party has contended then, in my opinion, the requirements of natural justice require the adjudicator to give the parties notice of that intention so that they may put submissions on it. In my opinion, this is a purpose intended to be served by s 21(4) of the Act (although the functions of s 21(4) may not be limited to this).
108 It follows, in my opinion, that where an adjudicator determines an adjudication application upon a basis that neither party has notified to the other or contended for, and that the adjudicator has not notified to the parties, there is a breach of the fundamental requirement of natural justice that a party to a dispute have 'a reasonable opportunity of learning what is alleged against him and of putting forward his own case in answer to it'. (See Lord Diplock in O'Reilly [O'Reilly v Mackman [1983] UKHL 1; [1983] 2 AC 237] at 279.)"
"Musico v Davenport ... is authority for the proposition that an adjudicator breaches the requirements of natural justice where an application is determined upon a basis not advanced by either party."
"... the rules of natural justice do not require the decision maker to disclose what he is minded to decide so that the parties may have a further opportunity of criticising his mental processes before he reaches a final decision. If this were a rule of natural justice only the most talkative of judges would satisfy it and trial by jury would have to be abolished."
"... in approaching the question of procedural fairness in the decision-making of an adjudicator under the Act, not too fine a point should be taken in relation to what is done. The shortcomings of the statutory procedure provided for in the Act point to the need for a large measure of practicality, flexibility and common sense being observed to make it work. The procedures will call for adaptation in each case in the light of the clear legislative intention of the Act, namely that an adjudicator's determinations are to be carried out informally ... and speedily ... and 'on the papers' ... and bearing in mind that there is always the facility for erroneous determinations to be corrected upon a final hearing of the issues in dispute between the parties ...".