THE CONTEST
28 The plaintiff directed a number of discrete attacks on the Adjudication as well as an attack based on apprehended bias. The last mentioned attack was properly abandoned during submissions. However, one aspect of it is deserving of comment and it will be further referred to below. Both parties provided written submissions which were refined during oral submissions.
29 For the reasons which follow I have reached the conclusion that two of the plaintiff's attacks on the Adjudication are well founded and that the Adjudication should be set aside or quashed.
30 Having regard to the delay which has already been occasioned to these proceedings, to the approaching of the end of the law term in this busy list and to facilitate the giving of an ex tempore judgment, I do not propose to deal with the plaintiff's unsuccessful attacks. Also, these reasons are also somewhat more abbreviated than they otherwise would be.
31 Having regard to the first defendant's failure, it will in the substantive case no doubt being a cross-claim for the monies it asserts it is owed.
32 I consider it appropriate that this matter be fixed for hearing of the parties' substantive claims and cross-claims at the earliest time consistent with the availability of judicial resources and the parties having sufficient opportunity to prepare.
The liquidated damages claim
33 The plaintiff put that the Adjudicator had failed to deal properly or at all with the prevention principle issue and was wrong to say that the plaintiff had not provided any authority for the proposition for which it contended. Although there is some substance in this complaint, it seems to me that the way in which the Adjudicator dealt with it arose from the manner in which the parties put their submissions. It may be that some authority was, in an indirect fashion, referred to by the plaintiff in support of the proposition that there is no room for the application of the prevention principle where there is a power to extend time. However, the Adjudicator had regard to the plaintiff's submission and resolved the issue against the plaintiff by making a finding of law which may or may not be right, but which was clearly made. In my view, the Adjudicator's approach in this respect did not reflect jurisdictional error.
34 However, in my view the manner in which she resolved the question of whether the first defendant was delayed by variations does reveal jurisdictional error.
35 In par 9 in his Statutory Declaration Mr Burford stated that the first defendant failed to meet its obligations under the contract and failed to meet its contract program.
36 The plaintiff put to the Adjudicator that the first defendant had not demonstrated that it was delayed, that the first defendant had not provided a contract program or demonstrated any impact on the critical path. Rather than approaching the matter by way of determining whether any delay had been established, the Adjudicator found delay because, as she put it, the plaintiff had offered no alternative explanation.
37 This approach discloses no logical or rational reasoning process for the conclusion that the delay was at least in part attributable to variations and in my view reflects a failure by the Adjudicator to make a bona fide attempt to carry out the function with which she was charged. An obvious possible reason for delay was, as the plaintiff submitted, that the first defendant was not working with sufficient diligence. In my view, in approaching the matter as she did, the Adjudicator did not carry out the task given to her by the Act and fell into jurisdictional error: see Bauen Constructions v Westwood Interiors [2010] NSWSC 1359, particularly at [20] - [27] and [36] - [43] and the authorities cited there.
Date for payment
38 Under s 22(1)(b) of the Act the Adjudicator is to determine the date upon which the adjudicated amount became payable. This is an essential requirement.
39 As the Adjudicator recorded, neither party submitted that cl 15 was void for uncertainty because the term "month" is not defined in it. Yet without hearing from the parties on the subject or giving them an opportunity to be heard, the Adjudicator determined that the provision was void.
40 Leaving aside the eccentricity of this finding and the absence of any reasoning as to why even without a definition the word would or could not be given a meaning, the parties were undoubtedly denied natural justice by not having had an opportunity to make submissions on the question.
41 It was put by the first defendant that this error was not material because the effect of it, in financial terms, represents something of the order of $4,000 in an adjudication award of over $1.3 million. Reference was made to what McDougall J said in Laing O'Rourke Australia Construction v H&M Engineering & Construction [2010] NSWSC 818 at [25] and Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399 at [42] and following, to the effect that a denial of natural justice must be material, meaning that the requirement for natural justice to be afforded does not require an adjudicator to give parties opportunity to put submissions on a matter not germane to his or her decision.
42 The meaning of the term month was not merely germane to the Adjudicator's determination of an essential matter under the Act but was the very subject of it. It was thus clearly material and in proceeding as she did the Adjudicator fell into jurisdictional error. It is not for the Court to substitute its own determination for that of the Adjudicator and absent a valid determination of the date for payment the Adjudication lacks an essential element.
43 I consider that this error too warrants quashing the Adjudication.
CONCLUSION
44 It follows that an order in the nature of certiorari quashing the Adjudication is appropriate.
45 I order that the Adjudicator's Adjudication Determination dated 22 February 2010 be quashed and set aside. The money standing in Court is forthwith to be paid out to the plaintiff.
46 The first defendant is to pay the plaintiff's costs of the proceedings.