(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates."
37 The provisions of the relevant construction contract (s 22(2)(b)) will be relevant for a number of reasons. They may specify the reference dates on and from which a claimant has an entitlement to a progress payment (s 8). They may specify how the amount of the progress payment is to be calculated (s 9). They may specify how the construction work is to be valued (s 10). They may specify the due date for payment (s 11).
38 Although all those matters (and many others that may be taken into consideration under s 22(2)) go to the determination of the amount of the progress payment that is payable, they do not all deal with the valuation of the construction work that is the subject of the payment claim for that progress payment. The adjudicator's task may (and usually will) comprehend more than merely the valuation of the relevant construction work. Attention to the requirements of the contract may indicate that there are to be deducted from, or offset against, that value some particular amounts (for example, retention payments or conceded back charges for defective or incomplete work). Thus, construction work may be valued at a particular sum, but the adjudicated amount of the progress payment may be less than that sum because of some such deduction or offset.
39 Further, there may be a question as to whether the claimant is entitled to be paid at all for construction work: for example, for an unauthorised variation where the contract specifies that the written authority of the respondent is required as a precondition of entitlement. (I leave aside, for present purposes, the possible impact of s 34 on such a provision.)
40 The precise issue that s 22(4) posed for Mr Davenport was not the amount determined by Mr Dutton as the progress payment payable in respect of the March payment claim. It was whether, in determining the amount of that progress payment, Mr Dutton had valued construction work that was required to be valued in the second adjudication pursuant to the May payment claim. Sections 9 and 10 make it clear that there is a distinction between the calculation of the amount of a progress payment (which is, ultimately, what the adjudicator is required to do) and the valuation of construction work. That is the distinction that I sought to point out (on reflection, in a way that was perhaps unduly brief and somewhat delphic) in para [43] of my decision in Rothnere.
41 It was, therefore, fundamental to the task to be undertaken by Mr Davenport that he apply himself to the parties' submissions based on what I had said in Rothnere. (Those submissions were made both in the payment claim and payment response and in support of the adjudication application and adjudication response. It is not suggested that either party sought impermissibly to extend the ambit of its submissions.)
42 In my view, the concept of materiality is inextricably linked to the measure of natural justice that the Act requires parties to be given in a particular case. Whatever the principles of natural justice may require in a particular case, they could not, in my opinion, require an adjudicator to give the parties an opportunity to put submissions on matters that were not germane to his or her decision. For the reasons that I have given, I think that the relevant aspect of my decision in Rothnere was germane to Mr Davenport's decision.
43 Mr Davenport was correct in stating that the relevant part of my decision in Rothnere was obiter. I did not decide the case on the basis of the distinction between entitlement and valuation. If his reasoning had gone no further (ie, if he had reasoned that the relevant part of my decision was obiter, and therefore not strictly speaking binding upon him, but had decided nonetheless to act in accordance with what I had said), then no question of denial of natural justice could arise. That is because, in the hypothetical circumstances, the point would not be material. But Mr Davenport went further. He decided not only (and correctly) that what I had said was obiter, but also that it was wrong, and that he would not follow it. The question, therefore, is whether this was material; and, if so, whether he was obliged to give the parties an opportunity to address it.
44 If Mr Davenport had notified the parties of the issue, John Goss could have put submissions directed to at least two points. Firstly, it could have sought to develop or explain my reasoning in Rothnere. Secondly, it could have submitted that, regardless of the precise status of that reasoning (as obiter or as part of the reasons for decision) and regardless of whether it might be incorrect, Mr Davenport should nonetheless follow it. The latter submission would invoke considerations of certainty, and analogous to those considered (although in a different context) by the High Court of Australia in Australian Securities Commission v Marlborough Gold Mines Limited (1993) 177 CLR 485, 492.
45 Such submissions might have had one of three results. They might have persuaded Mr Davenport that the distinction between entitlement and valuation was one required by the Act to have been made. Or they might have persuaded him that, regardless of his own views, he should defer to a reasoned expression of opinion in this Court reached after full argument on the point. Or they may have failed to dissuade him from his view that what I had said on this point in Rothnere was wrong, and should not be followed. Because Mr Davenport did not tell the parties that he was proposing to decide the application on a basis for which neither had contended, he deprived John Goss of the opportunity to put submissions that could well have persuaded him to take either the first or the second of those courses.
46 Clearly, the issue of the correctness of my reasoning, on s 22(4) in Rothnere, was material to the issue for Mr Davenport's decision. Each party had approached the matter on the basis that what I had said was correct. The question was whether, being correct, it governed the outcome. It might be thought to follow (subject to the fifth of Leighton's submissions to which I refer in the next paragraph) that Mr Davenport, in denying John Goss an opportunity to address his thinking, denied it in a real and material sense an opportunity to be heard.
47 Leighton however submitted that it did not follow that there was a denial of natural justice. Firstly, it submitted, the question of the meaning and application of s 22(4) was clearly within the defined area of dispute. Secondly, it submitted, the real question was whether Mr Davenport was constrained by the relevant part of my decision in Rothnere to decide the issue in favour of John Goss. Thirdly, it submitted, the parties had had an opportunity to put submissions on Rothnere. Fourthly, it submitted, Mr Davenport's views on the correctness of what I had said in Rothnere did not form part of his reasoning. Fifthly, it submitted, I could conclude that even if John Goss had had an opportunity to address the issue, Mr Davenport would have come to the same conclusion.
48 As to the first submission: it is correct to say that the issue that Mr Davenport was required to decide included a question as to the meaning of s 22(4) (in particular the words "determined … the value of any construction work") and its application to the facts before him. But the debate was conducted on the basis that the meaning of the subsection had been addressed in the relevant part of my reasons in Rothnere. The debate was not conducted on the basis that the relevant part of those reasons was wrong (or, for that matter, that it was obiter). As I have indicated, the submission for Leighton was that the facts in Rothnere were clearly distinguishable from the facts before Mr Davenport, so that he was not required to apply, by analogy or otherwise, my reasoning on this point. To put it another way: the debate before Mr Davenport concerned not the validity of the distinction that I drew in Rothnere at para [43], but the relevance (or applicability) of that distinction to the facts before him.
49 As to the second submission: essentially the same reasoning applies. If one accepts that the relevant questions were as formulated by Leighton, it does not follow that a determination of that question, on a basis not propounded by either party and not communicated to them before the determination was made, involves no denial of natural justice. There is a significant conceptual difference between saying that a decision (whether or not obiter) is correct but distinguishable, and saying that it is incorrect. A debate conducted along the former lines will not involve considerations relevant to the latter.
50 As to the third submission: it is correct to say that the parties had had the opportunity to put submissions on Rothnere. But as I have said, and as Mr Davenport recognised in the last paragraph of his determination, those submissions did not challenge the conclusions that I expressed in the relevant part of my decision.
51 As to the fourth submission: Leighton submitted that Mr Davenport determined the application not on the view that he took of my reasoning in Rothnere, but because he concluded that s 22(4) required him to adopt what Leighton called "Mr Dutton's valuation" (written submissions dated 19 July 2006, para 16). There are a number of difficulties with this submission. Firstly, it begs the question, whether there was any "valuation" performed by Mr Dutton. Secondly, it begs the question of the proper construction to be given to s 22(4). Both of those were matters with which the relevant aspects of my reasoning in Rothnere dealt.
52 Thus, I think that the distinction that Leighton sought to draw between what I had said in Rothnere and what Mr Davenport considered, and decided, was illusory. As I have said, a consideration of the applicability of s 22(4) necessarily requires a consideration, among other things, of the meaning of the words "determined … the value of any construction work". The question is whether that is, or is a part or component of, the determination of the amount of the progress payment referred to in s 22(1)(a). That is the precise point discussed, although obiter, in the relevant part of my reasons in Rothnere. Had Mr Davenport accepted (either because he thought it was correct or because he thought, notwithstanding his doubts, he should not depart from it) and applied my reasoning in para [43] of Rothnere, he should have come to the conclusion that, in determining the amount of the progress payment payable in respect of the March payment claim, Mr Dutton had not determined the value of the construction work (or alleged construction work) comprised in the second, third and fourth components of that progress claim.
53 The fifth submission was based on the forthright way in which Mr Davenport expressed his views. But it does not follow that he would not have paid due attention to submissions put to him before those views became, as it were, finalised in his determination. In particular, it is apparent that he either was unaware of, or if aware of did not consider, the second alternative referred to in para [45] above.
54 I therefore conclude that Mr Davenport, in deciding the way he did, denied John Goss natural justice.
55 The result, according to Brodyn, is that John Goss is entitled to appropriate declaratory relief. I should record that John Goss made a formal submission that it was entitled not merely to a declaration but to an order in the nature of certiorari, quashing Mr Davenport's determination, and that in this respect Brodyn was wrongly decided. For obvious reasons, I cannot accept that submission.
Want of good faith
56 The conclusion to which I have come renders it unnecessary for me to consider this aspect of the submissions for John Goss. In circumstances where the expression "good faith" (or its Latin ancestor, "bona fides", or some cognate form) is used not only as a circumstance of invalidation on the Brodyn test, but also as a qualification to the statutory right of immunity given to adjudicators by s 30(1) of the Act, I do not think that it is appropriate for me to consider the point. What I have said should not be read as implying that, were it necessary to do so, I might have accepted the submissions for John Goss on this point.
57 The content of the concept of good faith (in the Brodyn sense, if I may call it that) is unsettled - see the judgment of Brereton J in Holmwood Holdings Pty Ltd v Halkat Electrical Contractors Pty Ltd [2005] NSWSC 1129 at paras [63] and following. There is possibility for that concept to overlap with the reference to "good faith" in s 30(1). In those circumstances, I think that courts should be slow to decide applications on the basis of a lack of "Brodyn" good faith unless it is necessary to do so. In many cases, it will be possible to decide an application on the basis of denial of natural justice; and if this is so, then that should be sufficient.
58 The legislature has emphasised, both in debate and in the wording of the Act, the significance that it attaches to the purposes for which the Act was enacted. The work that adjudicators do is fundamental to the successful operation of the Act. It is essential that qualified and experienced people, capable of working under the very tight deadlines imposed by the Act, are available to accept appointment as adjudicators. It is not unreasonable to think that many of them are comforted, in seeking to do their best, by the immunity given to them by s 30(1) should they make a mistake. I think that there would be legitimate concern if decisions of this Court were seen to have the possibility to encroach on that immunity, by pronouncing on questions which, although they raise issues perhaps quite different to those that might be raised under s 30(1), nonetheless use, in common with it, the language of "good faith". In this context, it is necessary to remember that adjudicators customarily, and very properly, file submitting appearances when their determinations are challenged by proceedings in this Court. Thus, they are bound by the findings (including, if made, as to want of good faith) in circumstances where they have not taken an active part in the hearing.
59 These concerns are not diminished if the tentative view of Basten JA, expressed in Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385, at 404 [72], [75], questioning the applicability of the concept of "good faith" to the determinations of adjudicators under the Act, is borne in mind.
Abuse of process
60 Leighton asserted that the conduct of John Goss in making the May payment claim and instituting the second adjudication was an abuse of process. It relied upon this, in a way that I must confess I find difficult to follow, as a defence to the whole of the claim by John Goss in this Court.
61 The abuse of process was said to arise from the circumstance that all three elements of the May payment claim and the second adjudication had been included in the March payment claim and had been determined by Mr Dutton in the first adjudication. It was an essential element of Leighton's argument on this issue that Mr Dutton had determined the value of the delay and disruption claims, and that John Goss did not in the second payment claim assert that those items had any value other than that which it said had been determined by Mr Dutton.
62 There seem to me to be three answers to this submission. The first is that the Act by s 13(6) permits (or, more accurately, "does not prevent") the inclusion in a payment claim of an amount that has been the subject of a previous payment claim. Any question of "abuse of process", or "adjudicator shopping", is dealt with by s 22(4).
63 The second answer is that Mr Dutton did not determine the value of the relevant construction work. In my view, it is quite plain on reading his determination that his conclusion was based not on any valuation of the work but on his view that, by the operation of cl 45 in the events that had occurred, Leighton was not liable to John Goss for the relevant claims. It was accordingly unnecessary for him to seek to value, and he did not value, the work that was the subject of those claims.
64 The third answer is related to the second. The argument based on abuse of process only arises for consideration if s 22(4) is to be construed as apparently Mr Davenport construed it. If that were so then it is difficult to see how John Goss could obtain relief in this Court, given that (by hypothesis) Mr Davenport's reasoning would have been seen to be correct. In that hypothetical circumstance, abuse of process leads nowhere. Alternatively, if s 22(4) is to be construed as I have said it should be, abuse of process does not arise.
65 Finally, I note that although Leighton addressed the concept of abuse of process at some length in its supplementary written submissions (dated 25 July 2006) and relied upon those written submissions in its oral submissions, it did not indicate how the alleged abuse of process might be relevant to the issues arising on the claim by John Goss.
Clause 45
66 Clause 45 is lengthy. It is only necessary to set out cl 45.1:
"45.1 Notwithstanding any other provision of the Works Contract to the contrary, Leighton will not be liable upon any claim by the Contractor in respect of any matter arising out of the Works Contract or otherwise including but not limited to variations to the work under the Works Contract and claims for damages unless:
(a) the claim together with full particulars thereof is lodged in writing with Leighton not later than ten (10) Business Days after the date the Contractor became aware or should have reasonably become aware of the occurrence of the events or circumstances on which the claim is based; or
(b) written notice of intention to make the claim specifying the nature of the claim is lodged with Leighton within that time and the claim, together with all particulars thereof, is lodged in writing with Leighton before the Date of Substantial Completion."
67 The form of "prescribed notice" must be so titled, and must set out particulars of the breach etc on which the claim is or will be based, the relevant provisions of the contract or other contractual basis, and the amount or likely amount of the claim.
68 Section 34 of the Act provides as follows:
"34 No contracting out