…
51 At least in relation to findings of primary fact, the weight to be given to any particular matter is for the decision-maker and is not reviewable by the Court. As Spigelman CJ noted in Bruce v Cole (1998) 45 NSWLR 163 at 186D-E, the scope for assessing whether the decision-maker has given proper, genuine and realistic consideration to a mandatory matter must be approached with caution, so as to avoid the Court impermissibly reconsidering the merits of the decision. Indeed, the language adopted by Gummow J in Khan was not expressly directed to mandatory considerations, but to the merits of a case, and would extend to all material matters raised by an applicant, failure to consider which in the manner described is now treated as a question of procedural unfairness: see Dranichnikov v Minister for Immigration and Multicultural Affairs (2003) 77 ALJR 1088 at [24] (Gummow and Callinan JJ) and [87] and [88] (Kirby J)."
25 I do not think that the Adjudicator failed to consider, in the sense that I have explained, the relevant parts of the payment schedule. On the contrary, I think, it is apparent from her determination that she did so. Whether or not her reasoning and conclusions were correct is irrelevant.
26 In short, I do not think that the Adjudicator denied Veolia natural justice in this respect.
27 In any event, as the second half of paragraph 38 of the determination makes plain, the Adjudicator was not satisfied as a matter of fact that there was any incomplete or defective work. On the basis that, as I have said, the adjudication response and Mr Fenton's statutory declaration were to be treated at most as submissions (or were not required or able to be "considered" as evidence), that reasoning cannot give rise to reviewable error.
28 In this context, and as to the s 20(2B) point raised by Kruger before the Adjudicator (see paragraph 37 of the determination), it is plain that much of the material asserted by Mr Fenton was known, or available, as at 9 August 2006 when the payment schedule was provided.
29 However, for the reasons that I have given above, I do not think that the Adjudicator erred in failing to "consider" this as something capable of supplementing the deficiencies of proof to which she adverted to in paragraph 38.
30 It follows that even if, contrary to my view, the Adjudicator did fail in the relevant sense to consider the relevant aspect of the payment schedule (ie, Veolia's case and submissions based on the proposition that there was defective and incomplete work), that error would not have been dispositive, given her conclusion on the associated question of proof (or lack thereof).
Second issue: clause P47
Basis of the claim; relevant contractual provisions
31 This issue too concerns the claim for delay costs. Unfortunately, to understand the issue, it is necessary to look at that claim, and the relevant contractual provisions, in a little detail.
32 It was common ground, and in any event is plain, that Kruger put this claim on two bases. The first basis relied on Veolia's alleged failure to provide to Kruger timely access to the site. The second relied on Veolia's alleged suspension of the works.
33 Access to the site is dealt with by clause P27.1 of the contract, which provides relevantly:
"P27.1.1 The Contractor shall on or before the expiration of the time stated in the Annexure Part A give the Subcontractor access to sufficient of the Site to enable the Subcontractor to commence work. The Contractor shall from time to time give the Subcontractor access to such further parts of the Site as may be necessary to enable the Subcontractor to execute the work under the Subcontract in accordance with the requirements of the Subcontract. The Contractor shall advise the Subcontractor in writing of the date upon which the Site or any part will be available.
P27.1.2 Notwithstanding the provisions of this Clause, if the Subcontractor is in breach of Clause 21.1, the Contractor may refuse to give the Subcontractor possession of the Site or any part of the Site until the Subcontractor has complied with the requirements of Clause 21.1.
P27.1.3 The Subcontractor shall only be entitled to such use and control as is necessary to enable the Subcontractor to execute the work under the Subcontract."
34 Suspension of the works is dealt with by clause P34 of the contract, which provides relevantly:
" P34.1 Suspension by Contractor's Representative
If the Contractor's Representative considers that the suspension of the whole or part of the work under the Subcontract is necessary:
(a) because of an act or omission of:
(i) the Contractor, the Contractor's Representative or an employee, consultant or agent of the Contractor; or
(ii) the Subcontractor, a Secondary Subcontractor or an employee or agent of either;
(b) for the protection or safety of any person or property or the environment; or
(c) to comply with an order of a court,
the Contractor's Representative shall direct the Subcontractor to suspend the progress of the whole or part of the work under the Subcontract for such time as the Contractor's Representative thinks fit.
…
P34.3 Cost of Suspension
Any cost incurred by the Subcontractor by reason of a suspension under Clause 34.1 shall be borne by the Subcontractor but if the suspension is due to an act or omission of the Contractor, the Contractor's Representative or an employee, consultant or agent of the Contractor and the suspension causes the Subcontractor to incur more or less costs than otherwise would have been incurred, the difference shall be valued under Clause 40.2.
… ".
35 Clause P40.2 provides, relevantly:
" P40.2 Valuation
Where the Subcontract provides that a valuation shall be made under Clause 40.2, the Contractor shall pay or allow the Subcontractor or the Subcontractor shall pay or allow the Contractor as the case may require, an amount ascertained as follows:
…
(c) to the extent that neither Clause 40.2(a) or 40.2(b) apply, reasonable rates shall be used;
…
(f) if the variation has caused a delay in respect of which the Contractor's Representative has extended the Date for Practical Completion, the valuation may include additional time based costs incurred by the Subcontractor in respect of the delay or disruption and the valuation shall include a reasonable amount for overheads but shall not include profit or loss of profit; and
… ".
36 Veolia submitted in this Court that its case, as advanced in the payment schedule and before the Adjudicator, was that the claim, however based, was defeated by clause P47. That clause provides:
" P47. NOTIFICATION OF CLAIMS
The Contractor shall not be liable upon any claim by the Subcontractor in respect of any matter under or arising out of or in connection with the Subcontract or any alleged breach thereof unless:
(a) the Subcontractor gives written notice to the Contractor's Representative not later than 7 days after it becomes aware of or should reasonably have been aware that it had a claim;
(b) the Subcontractor lodges the claim with the Contractor's Representative within a further 14 days or any other period agreed to by the Contractor's Representative from the date of written notice of the claim; and
(c) the claim sets out:
(i) the legal base for each aspect of the claim;
(ii) the facts relied upon in support of each aspect of the claim; and
(iii) details of the quantification of the sums claimed showing the manner of their calculation,
(iv) sufficient to enable a proper assessment of the claim; and
(d) any other requirement for notification of the claim elsewhere under the Subcontract has been met."
How Veolia put its case in the payment schedule
37 As I have noted, and as the Adjudicator commented, the payment schedule is not easy to follow. In their submissions, however, the parties drew attention to the various places in which clause P47 was mentioned in the payment schedule.
38 I start by setting out the relevant parts of paragraph 4:
"4. The Payment Claim refers to Subcontract Number 400-896. It is incumbent upon Kruger Engineering to substantiate in its Payment Claim, its entitlement, if any, to a progress payment. Based upon the terms of that Subcontract and in spite of the position adopted by VWSA in its previous payment schedules related to payment claims referred to in Schedule 2 of the Payment Claim, Kruger Engineering, in its Payment Claim:
…
(h) has again failed to recognise, or incorrectly interpreted, the effects of Clause P36, "NOT USED" and its resultant effect on the meaning of the entry in Annexure Part A of the Subcontract "Limit of Delay Costs (Clause 36.2), Subcontract Sum". P36, had it been used, would have addressed Delay costs entitlements. That Clause P36 was however not used in the Subcontract and cannot and did not operate in the Subcontract. There can be no entitlement under Clause P36 to adjust the Subcontract Sum under Clause P36. As such the Subcontract Sum, as defined in Clause P2.1, is unaffected by Clause P36. In any event VWSA submits:
…
(iv) To the extent Kruger Engineering is relying upon the provisions of Clause P34.3 then VWSA denies that this Clause gives rise to any entitlement to extra payment to Kruger Engineering on the basis that there was no suspension under Clause P34.1 (or 34.1) (or Clause 44.9.1). In any event the amount claimed of $369,943.10 (excluding GST) has not been valued consistent with the provisions of Clauses P34.3 (or P44.9.1).
(v) To the extent that Kruger Engineering is relying upon breach by VWSA then Clause P47 of the Subcontract is relevant to consideration of the position with liability.
(i) has again failed to recognise the effects of Clause P47 of the Subcontract in that Kruger Engineering has not taken action consistent with parts (a) to (d) of that Clause, and as a result VWSA "shall not be liable upon any claim by the Subcontract". Kruger Engineering has failed to discharge its onus of proof of entitlement to the claimed "Time Based Cost" and/or "Interest".
(j) has again failed to establish that Kruger Engineering has given notices and claims conformably or consistent with taking action under Clauses P35.5 and/or P47. In any event VWSA denies that Kruger Engineering has submitted notices and claims as it is obliged to do under Clauses P35.5.1 and/or P35.52.1 and/or P47 in relation to its Claims for $369,943.10 and $27,534.05 plus associated GST. To that extent that Kruger Engineering's Payment Claim is based upon alleged substantial breach by VWSA related to delay in giving access and/or alleged suspension then VWSA submits that as a result of Kruger Engineering's failure to comply with the provisions of Clauses P35.5 and/or P47 the Clause P47 provides that VWSA "shall not be liable upon any claim", by Kruger Engineering. Such provision is applicable to Kruger Engineering's claims for $369,943.10 and $27,534.05 plus associated GST. In any event VWSA denies any liability upon those claims.
…
(s) failed to demonstrate that any of the amounts which Kruger Engineering has referred to in its Schedule 2 can be properly characterised as " moneys due". In any event VWSA denies that any of such amounts are "moneys due" for the purposes of Clause P42.11.
…
(v) Kruger Engineering failed to give any notices under Clause P47 relative to any claim of the nature in Schedule 2 after receipt of the relevant VWSA payment schedule, or otherwise. VWSA relies upon such failure and its consequences under Clause P47 whereby VWSA "shall not be liable upon any claim by the Subcontractor".
In any event VWSA denies that Kruger Engineering has any entitlement under Clause P42.12 for part or all of the claimed amount of $27,534.05 plus associated GST.
… ".
39 These were apparently prefatory or introductory comments. It was not until paragraph 7(f), some nine pages further into the document, that Veolia commenced to "respond" to the detail of the payment claim:
"(f) VWSA responds to Kruger Engineering's Payment Claim, pages 002/011 (page 2 of 11) to page 7 of 11 as follows:
(i) The Kruger Engineering material comprises unsubstantiated assertions. The material contains a number of errors, inaccuracies and inconsistencies as demonstrated by the responses below. The most significant individual components of the Payment Claim relate to claimed time-based costs, Interest and associated GST. Such matters have been the subject of previous payment claims referred to in Schedule 2 and such claims have been responded to by VWSA in payment schedules. The method by which Kruger Engineering has now, in its 26 July 2006 Payment Claim, calculated and presented its claim differs from the methodology adopted in those previous payment claims. Such differences are consistent with Kruger Engineering recognising the flawed nature of its previous claims. As demonstrated in this Payment Schedule there remains significant flaws in the claimed position."
40 In paragraph 7(f)(iii), Veolia dealt with the claim insofar as it was based on breach of clause P27.1:
"(iii) In response to paragraph 2 "Veolia failed … to the site" then VWSA submits that even if there was failure of the nature asserted then the Subcontract had terms which were potentially relevant. VWSA submits:
…
(d) Kruger Engineering did not attempt to comply with items (a) to (d) of Clause P47 notwithstanding that the Clause put beyond doubt that VWSA "shall not be liable upon any claim by the Subcontractor in respect of any matter under or arising out of or in connection with the Subcontract or any alleged breach thereof" unless such items (a) to (d) are complied with."
41 In paragraph 7 (f)(iv), Veolia dealt with the claim insofar as it was based on suspension:
"(iv) In response to paragraph 3 "Veolia gave numerous directions … and disruption" then VWSA submits:
(a) VWSA gave no directions to Kruger Engineering to suspend work whether under Clause P34.1 or otherwise.
(b) VWSA repeats its response in item (iii) above.
(c) The Subcontract does not provide for suspension by the Subcontractor and or any Administrator appointed by Kruger Engineering of the nature referred to in Kruger Engineering's letter dated 15 June 2006, nor does it provide for any additions to the Subcontract Sum as a result of any such suspension.
(d) Kruger Engineering has not particularised or substantiated the timing or duration of any alleged suspension. Contrary to the assertion in Kruger Engineering's letter dated 15 June 2006, item 10, to the effect that the Administrator's letter dated 21 February 2006 "informed Veolia that the work is suspended", in fact that letter does not refer to suspension. In any event prior to and by 21 February 2006 Kruger Engineering was not carrying out work on the Site."
42 It will be seen that this response did not refer expressly to clause P47. Whether or not it was intended to call up clause P47 through the repetition of paragraph 7 (f)(iii) is a matter of conjecture.
43 Veolia returned to the delay costs claim in paragraph 7 (f)(xxiii), some ten pages later. It said relevantly:
"(xxiii) In response to paragraphs 27 to 46 "Veolia failed to meet … set out in the attached Schedule 1" then VWSA submits:
…
(c) VWSA denies that "suspension was directed under Clause P34.1". Consequently there can be no proper basis for Kruger Engineering to rely upon the provisions of Clause P34.3 as that clause relates to costs incurred "by reason of a suspension under Clause 34.12". There was no such suspension.
…
(e) Kruger Engineering has not demonstrated or substantiated that there was late and discontinuous access to the site or that Veolia failed to provide access in accordance with Clause P27.1.1. Even if it could provide any such demonstration and substantiation Kruger Engineering is not able to demonstrate that as a result of such access matters Kruger Engineering fulfilled the provisions of Clause P47, items (a) to (d), and/or P35.5 nor can it demonstrate that there were any relevant directions under Clause 40.1 which "shall be valued under Clause 40.2" relevant to its time-based claim."
44 The question was addressed yet again in attachment C to the payment schedule. I interpose that it is plain from the first paragraph of that attachment that Veolia recognised the two bases on which the payment claim was brought:
" … The claim is based upon an alleged breach under Clause P27.1.1 of that Subcontract or alleged suspension allegedly directed under Clause P34.1. …".
45 In paragraph 3 of the attachment, Veolia restated its reasons for rejecting the claim. Again, it addressed both aspects:
"3. The Payment Claim refers to Subcontract No. 400-896 ("the Subcontract"). Based upon the terms of that Subcontract and in spite of the position adopted by VWSA in its previous payment schedules, then Kruger Engineering, in its Payment Claim: