[2012] VCAT 659
Victorian Civil and Administrative Tribunal
2012-05-24
Ms J, Mr P
Original judgment source is linked above.
3.1 The indemnities referred to and contained in Section 2.1, shall only apply if the builder dies, becomes insolvent or disappears".
"On 31.05.2006 a letter was sent to you reversing the acceptance of the claim and the claim was formally declined".
Since the builder returned and organised rectification of the defect using a scope of works which was not disputed by you at the time of the claim - and, that according to our file notes you agreed that the matter was between yourself and the builder, the claim was then formally declined following these events - I would now consider it to be extremely unlikely that since the policy has now expired that your claim can be re-opened and re-investigated".
"We have read the Building Assist report where comments were made regarding the pitch of your roof; however they did not attribute the water ingress to this therefore under the policy there was no loss.
They did identify other defects in the scope of works was produced, and accepted by you and Jason Keogh Plumbing completed the works asserted by the successor.
Your policy coverage has expired and it is over 5 years since the repairs and this is the First notification you have given Lumley of any concerns regarding your homes.
After consideration of the above facts we are unable to accept any further liability in this matter."
(1). The following actions shall not be brought after the expiration of six years from the date on which the cause of action accrued-
- (a) Subject to subsections (1AAA), (1AA) and (1A), actions founded on simple contract (including contract implied in law) or actions founded on tort including actions for damages for breach of a statutory duty;"
"134. Limitation on time when building action may be brought
Despite any thing to the contrary in the Limitation of Actions Act 1958 or in any other Act or law, a building action cannot be brought more than 10 years after the date of issue of the occupancy permit in respect of the building work (whether or not the occupancy permit is subsequently cancelled or varied) or, if an occupancy permit is not issued, the date of issue under Part 4 of the certificate of final inspection of the building work."
"...an action (including a counterclaim) for damages for loss or damage arising out of or concerning defective building work."
This is such an action. The defence taken under the Limitation of Actions Act therefore fails because that section is not applicable in this case.
"A permit, when granted under the hand of the surveyor, is a written certification which both authorizes building work and declares that the building work as described in the application will comply with the Act and the Regulations."
"...were intended to ensure that buildings are properly constructed in the interests of health and safety and, I should think, also in the interest of achieving or maintaining a standard of building appropriate to the municipality or area of the municipality concerned."
"The private building surveyor will be required to work in a professional and impartial manner. His or her conduct will be regulated by the scrutiny of the Building Control Commission, and the proposed legislation includes significant penalties. Building surveyors whose work falls short of standards required can be deregistered or fined. Those formal powers will be complemented by the peer group scrutiny of other builders and building surveyors, and the scrutiny of the insurer. Without a good professional record and an acceptable standard of professional practice, insurers will not maintain the insurance cover required by a building surveyor on an ongoing basis."
"A registered building practitioner must perform his or her work in a competent manner and to a professional standard."
"...is evidence that the building is suitable for occupation. It is not evidence that the building to which it applies complies with the ACT or the regulations. The same is the situation if a certificate of final inspection is issued, which happens where an occupancy permit is not required."
39. The court nonetheless held that a person seeing an occupancy permit would be reassured that the building surveyor had been satisfied at least that the building work authorised by the building permit was work which would comply with the ACT and the regulations, that the surveyor had at least conducted the mandatory inspections. In paragraph 148 of the joint judgment of Ormiston and Ashley JJA, their Honours set out a number of factors favouring the erection of a duty of care to the subsequent owners. When one reads these they would generally be found to apply to most situations encountered in these cases.
"In important respects the decision of the Court of Appeal turns on the particular nature of the obligations owed under applicable Victorian statutes by a building surveyor who issued certain permits required by that legislation in connection with the construction and occupation of a new dwelling for the predecessors in title of the plaintiffs, certificates which it was necessary for the plaintiff's predecessor in title to produce upon sale of the land to the plaintiffs........An appeal in the present matter would enjoy insufficient prospects of success to warrant a grant of special leave.". (Moorabool Shire Council & Anor v. Taitapanui & ors [2006] HCA Trans 328 - 16 June 2006)
41. Accordingly, a building surveyor will generally owe a duty of care to the owner and to subsequent owners in the issue of the building permit, the occupancy permit and for the required inspections.
"24AI. Proportionate liability for apportionable claims
(1) In any proceeding involving an apportionable claim-
(a) the liability of a defendant who is a concurrent wrongdoer in relation to that claim is limited to an amount reflecting that proportion of the loss or damage claimed that the court considers just having regard to the extent of the defendant's responsibility for the loss or damage; and
(b) judgment must not be given against the defendant for more than that amount in relation to that claim.
...............................................................................................
(3) In apportioning responsibility between defendants in the proceeding the court must not have regard to the comparative responsibility of any person who is not a party to the proceeding unless the person is not a party to the proceeding because the person is dead or, if the person is a corporation, the corporation has been wound-up."
"(a) a claim for economic loss or damage to property in an action for damages (whether in tort, in contract, under statute or otherwise) arising from a failure to take reasonable care;"
"(1) A concurrent wrongdoer, in relation to a claim, is a person who is one of two or more persons whose acts or omissions caused, independently of each other or jointly, the loss or damage that is the subject of the claim.
(2) For the purposes of this Part it does not matter that a concurrent wrongdoer is insolvent, is being wound up, has ceased to exist or has died."
Jacobi & Ors
Motalli & Anor
(2004) 205 ALR 522