[2008] VCAT 267
Victorian Civil and Administrative Tribunal
2008-02-19
Original judgment source is linked above.
Limitations period for commencement of building actions - s5 Limitations of Actions Act 1958, s134 Building Act 1993 - Part IVAA of the Wrongs Act 1958 - premature to consider whether an apportionable claim
Hardiman v Gory (Domestic Building) [2008] VCAT 267
(1) The following actions shall not be brought after the expiration of six years from the date on which the cause of action accrued -
(a) Subject to subsections (1AAA), (1AA) and (1A), actions founded on simple contract (including contract implied in law) or actions founded on tort including actions for damages for breach of a statutory duty;
Despite anything to the contrary in the Limitations of Actions Act or in any other Act or Law, a building action cannot be brought more than ten years after the date of issue of the occupancy permit in respect of the building work...(emphasis added).
The Building Bill defines a clear starting date - the date of issue of an occupancy permit - and a clear conclusion date of 10 years after the date of issue. This will remove the existing ambiguity surrounding the time during which the building owner retains the right to issue proceedings.
This will provide property owners with additional protection in terms of years beyond the very short number of years that now exist. '
In my view, the prefatory phrase should be simply read as 'but for the provisions of this section, section 5 of the Limitations of Actions Act would apply.
(a) a claim for economic loss or damage to property in an action for damages (whether in tort, in contract, under statute or otherwise) arising from a failure to take reasonable care; and
(b) a claim for damages for a contravention of section 9 of the Fair Trading Act 1999.
Hardiman
Gory