[2015] NSWCA 348
Court of Appeal (NSW)
2015-11-13
Beazley P, Gleeson JA, The J, Schmidt J
Original judgment source is linked above.
ounsel: B J Gross QC; K Earl (Appellant) M Windsor SC; K Young (First Respondent) G Parker SC (Second Respondent)
Solicitors: Baker & Edmunds Solicitors (Appellant) Thompson Cooper Lawyers (First Respondent) Turks Legal (Second Respondent) File Number(s): CA 2014/127274 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Common Law Citation: Grills v Leighton Contractors Limited (No 2) [2013] NSWSC 1951; Grills v Leighton Contractors Limited Pty Ltd (No 3) [2014] NSWSC 349 Date of Decision: 23 April 2014 Before: Schmidt J File Number(s): SC 2008/317603
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the judgment] The principal judgment in this matter was given by the Court of Appeal in Grills v Leighton Contractors Pty Limited [2015] NSWCA 72. The appellant was, relevantly, successful in setting aside a finding of contributory negligence as against him, with the effect that judgment sums which had been awarded in his favour in the court below required adjustment. By notices of motion filed some months after the Court gave judgment, the appellant and the State of New South Wales (the State) applied for a number of variations to the orders made. The appellant, in relation to his notice of motion, contended: (1) That the Court, by its judgment of 27 March 2015, failed to set aside orders (1) and (2) made by the trial judge or to make new orders for the appropriate judgment sums; and (2) That he was entitled to an order for interest, as from the date of the judgment below, on the total amount of damages to which he was entitled from each of the Leighton Contractors Pty Limited (Leighton) and the State, rather than on the amounts apportioned between them. The State, in relation to its notice of motion, contended: (1) That the order of the Court by which it was made liable for a portion of the appellant's costs of the appeal should be set aside as being wrong in law, having regard to the Workplace Injury Management and Workers Compensation Act 1998 (NSW), s 346.
Held by the Court: In relation to the appellant's notice of motion: (i) The Court's omission to make the orders required to give effect to its judgment was a clerical mistake requiring correction, and the Court's power to make such correction pursuant to UCPR, r 36.17 was enlivened. [11] (ii) Although there is no settled convention as to the date on which an appellate judgment takes effect, there are significant practical advantages to it doing so from the date of the first instance judgment. As the parties appeared to accept, the appellant should have interest from that date. [13], [21]-[23] Erect Safe Scaffolding (Australia) Pty Ltd v Sutton (No 2) [2008] NSWCA 289; Nichol v Allyacht Spars Pty Ltd [1988] HCA 48; 165 CLR 306; Najdovski v Crnojlovic (No 2) [2008] NSWCA 281 (iii) The State's liability to pay interest (as opposed to the amount of interest payable and whether any amount remained due) was unaffected by the fact that it may have overpaid the appellant. [30]-[31] (iv) It was not appropriate that Leighton be embroiled in a dispute between the appellant and the State, or that as a result of that dispute it be required to pay interest on a greater sum that that which it was obliged to pay the appellant. In those circumstances, an order should be made pursuant to the Civil Procedure Act 2005 (NSW), s 101 that interest be calculated only on the portions of the judgment sum by which it was ordered that each of Leighton and the State could discharge their liability to the appellant. [32] In relation to the State's notice of motion: (i) The Workplace Injury Management and Workers Compensation Act 1998 (NSW), s 346 applies such that the Court was in error in ordering that the State pay a portion of the appellant's costs of the appeal. [46] (ii) The Court did not intend that Leighton be liable for all of the appellant's costs of the appeal for which costs orders were made. The appellant must therefore bear that portion of his costs for which the State was erroneously made liable. [50] (iii) It is appropriate, notwithstanding the State's delay in making an application to the Court, that the Court exercise its discretion to vary its orders pursuant to UCPR, r 36.17, in the circumstance that had the matter been brought to the Court's attention at an earlier time, it would have made the correction at once; that the State's liability to pay costs was not a matter of discretion; and that no prejudice to any of the parties was established. [48]-[51]. Storey & Keers Pty Ltd v Johnstone (1987) 9 NSWLR 446; Newmont Yandal Operations Pty Limited v The J Aron Corporation and the Goldman Sachs Group [2007] NSWCA 195; 70 NSWLR 411; Wardle v Agricultural & Rural Financers Pty Ltd (No 3) [2013] NSWCA 207; 303 ALR 298
Judgment
The appellant's notice of motion
The State's notice of motion
Costs of the notices of motion
Orders
Amendments 13 November 2015 - Typographical corrections at [41], [45] and [50] DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 13 November 2015
Grills
Leighton Contractors Pty Limited