[2024] NTSC 61
General information, not legal advice.
Supreme Court of the NT
2024-08-22
Brownhill J
Original judgment source is linked above.
CONTRACT - Remedies - Damages - Assessment of damages - General principles - 'Ruling Principle' -Onus of proof on the Plaintiff - Damages must be proved with degree of precision as reasonably available - Entitlement to damages limited to damages that arise naturally - Plaintiff has a duty to mitigate of loss - Plaintiff cannot recover losses which are avoided - Plaintiff cannot be placed in a superior position to which they would have been if the contract had been performed.
DAMAGES - Claim for interest - Calculation of interest on damages - s 84(1) Supreme Court Act 1979 (NT) - Interest as damages - Requirement to prove loss not satisfied by first plaintiff - Award of nominal damages.
DAMAGES - Assessment of damages - Prima facie measure - Whether prima facie measure applies - Whether s 52(3) Sale of Goods Act 1972 (NT) applies - s 52(3) Sale of Goods Act 1972 (NT) not applicable to claim for damages.
DAMAGES - Assessment of damages - Prima facie measure at common law - Whether prima facie measure applies - Defendant did not plead any prima facie measure of damages outside of the Sale of Goods Act 1972 (NT) - Departure from the general rule when in the 'interests of justice'- Prima facie measure displaced.
DAMAGES - Assessment of damages - Whether legal costs incurred in relation to another proceeding are claimable as damages - Whether there is a causal connection between legal costs and the defendant's breach of contract - Legal costs incurred may reasonably be supposed to have been a probable result of the defendant's breach - Entitled to share of legal costs.
BREACH OF CONTRACT - Counter-claim - Whether res judicata, issue estoppel or Anshun estoppel preclude counter-claim being made - Res judicata, issue estoppel and Anshun estoppel do not arise - Whether defendant is entitled to recover moneys paid - Defendant is entitled to recovery.
Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1, The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64, Hadley v Baxendale (1854) 9 Ex 341, TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130, Sabouni v Revelop Building and Developments Pty Ltd [2021] NSWCA 31, Troulis v Vamvoukakis [1998] NSWCA 237, Barrow v Arnaud [1846] EngR 10; (1846) 8 QB 595, Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613, Motor Accidents (Compensation) Commission v Motor Accidents Insurance Board (No 2) [2023] NTSC 71, Haines v Bendall [1991] HCA 15; (1991) 172 CLR 60, IM Properties Plc v Cape & Dalgleish [1998] EWCA Civ 862; [1999] QB 297, Hungerfords v Walker [1989] HCA 8; (1988) 171 CLR 125, Ajaimi v Giswick Pty Ltd (No 3) (2022) 67 VR 529, Hobartville Stud Pty Ltd v Union Insurance Co Ltd (1991) 25 NSWLR 358, Johnson v Perez [1988] HCA 64; (1988) 166 CLR 351; Vieira v O'Shea [2012] NSWCA 21, Ng v Filmlock Pty Ltd [2014] NSWCA 389; (2014) 88 NSWLR 146, McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 CLR 457, Moffet Farms v Pauls Services & Sales Pty Ltd (1991) 7 SR (WA) 351, Shaw v Gadens Lawyers [2014] VSCA 74, Willoughby v Clayton Utz (No 2) [2009] WASCA 29; (2009) 40 WAR 98, referred to.
Supreme Court Rules 1987 (NT) Order 59.02(3).
JW Carter, W Courtney and GJ Tolhurst, 'Issues of Principle in Assessing Contract Damages' (2014) 31 Journal of Contract Law.
JW Carter, Carter's Breach of Contract, 2nd ed, 2018, LexisNexis Butterworths.
FE Accommodation Pty Ltd & Anor v Gold Valley Iron Ore Pty Ltd [2024] NTSC 61
Liability trial - findings and determination of liability
The parties' approaches to assessment of damages
What was the content of the unperformed promise?
(a) $1.5 million remaining of the purchase price for the Camp, payable to the first plaintiff pursuant to cl 2.3 of the Contract of Sale;
(b) $3.5 million in licence fees for the Camp, payable to the first plaintiff pursuant to cl 2.7(d) and the fifth schedule of the Contract of Sale; and
(c) $1 million remaining of the purchase price for the Plant and Equipment, payable to the second plaintiff pursuant to cl 2.4 of the Contract of Sale.
(a) the $6 million payable to them under cl 15; less
(b) the monies received from the sales of most of the Camp and the Plant and Equipment to Britmar and NRR; plus
(c) legal costs caused by the defendant's breach; plus
(d) interest, calculated on a cash flow basis taking account of the time at which these amounts were received or paid.
(a) the contract price of $7 million; less
(b) the market value on 30 August 2018 of all of the Camp and the Plant and Equipment;
(c) excluding legal costs as they were not caused by the defendant's breach; and
(d) excluding interest as the 'benefits' to the plaintiffs from termination of the Contract of Sale exceeded the benefits the plaintiffs would have received if the Contract of Sale had been performed.
Assessment of the plaintiffs' damages - interest claim
Amount owing under cl 15 on 30 August 2018 $5,000,000
Amounts paid by Britmar and NRR under asset sale deed (6,000,500)
Legal costs in relation to Federal Court proceeding 174,929[44]
Amount owing under cl 15 on 30 August 2018 $1,000,000
Amounts paid by Britmar under asset sale deed ( 500,000)
Legal costs in relation to Federal Court proceeding 47,708[46]
... [E]ven in the extreme case of recovery only being obtained from a third party some days prior to a hearing date, then if that recovery reduces the sum for which judgment can be obtained, I do not think that the court would have any power to award interest up to the date of recovery. ... [W]here recovery does reduce the sum for which a plaintiff can obtain judgment, then in my view the court would not have power to award interest up to the date of that recovery.
... Despite the injustice, on the wording of s 35A, in my view the judge did not have power to award interest up to the date of that recovery.
There is, in our view, a critical distinction between an order that interest be paid upon an award of damages and an actual award of damages which represents compensation for a wrongfully caused loss of the use of money and which is assessed wholly or partly by reference to the interest which would have been earned by safe investment of the money or which was in fact paid upon borrowings which otherwise would have been unnecessary or retired. On the one hand, there is no common law power to make an order for the payment of interest to compensate for the delay in obtaining payment of what the court assesses to be the appropriate measure of damages for a wrongful act. If such interest is to be awarded at common law, it must be pursuant to statutory authority. On the other hand, there is no acceptable reason why the ordinary principles governing the recovery of common law damages should not, in an appropriate case, apply to entitle a plaintiff to an actual award of damages as compensation for a wrongfully and foreseeably caused loss of the use of money.
(a) Under the heading 'Loss and damage' - that on 11 September 2020, judgment in favour of the plaintiffs was delivered, with reasons finding that the plaintiffs' termination of the Contract of Sale was valid and the plaintiffs are entitled to have their damages for the defendant's repudiation assessed.
(b) Under the heading 'Damages for repudiatory breach of contract' - that the plaintiffs are entitled to be paid damages representing the loss suffered by the plaintiffs as a result of the defendant's breach, which is particularised as follows:
The quantum of the plaintiffs' loss, and the basis upon which such loss is quantified, is set out in the expert report of Brian Morris ('Morris Report')...
(c) Under the heading 'The Camp and the Conveyor' - that the plaintiffs entered into the asset sales deeds with Britmar and the facts of Britmar's payments to the plaintiffs under those deeds are pleaded.
(d) Under the heading 'Remedies' - that the plaintiffs claim against the defendant: damages as set out in the Morris Report; interest; and costs.
The proper approach to assessing the second plaintiff's damages
Plant and Equipment owned by the second plaintiff
(a) the six fuel pods transported to Mataranka and then to Alice Springs, being one x 20 feet (or five metres long) and five x 40 feet (or 12 metres long);
(b) the 24 Removed Items recovered by the second plaintiff and transported to yards in Alice Springs ('Table 4 Items');[103] and
(c) the 28 Removed Items remaining at the locations to which they were taken by the defendant.
Amount owing under cl 15 on 30 August 2018 $1,000,000
Principal paid by Britmar under G&C asset sale deed ( 500,000)
Interest paid by Britmar under G&C asset sale deed ( 6,765)
Legal costs in relation to Federal Court proceeding 37,180
(1) The first plaintiff is entitled to judgment against the defendant for nominal damages only and the defendant is to pay the first plaintiff nominal damages of $1.
(2) The second plaintiff is entitled to judgment against the defendant for damages and the defendant is to pay the second plaintiff damages of $382,555, plus interest at the rate prescribed by Order 59.02(3) of the Supreme Court Rules for the period from 30 August 2018 to the date of judgment.
(3) The defendant is entitled to restitution against the first plaintiff on the counterclaim and the first plaintiff is to pay the defendant restitution of $500,000, plus interest at the rate prescribed by Order 59.02(3) of the Supreme Court Rules for the period from 30 August 2018 to the date of judgment.
(4) The defendant's counterclaim against the second plaintiff is dismissed.
[1] FE Accommodation Pty Ltd & Anor v Gold Valley Iron Ore Pty Ltd [2020] NTSC 61 ('Liability Reasons') at [181], [195].
[2] Gold Valley Iron Ore Pty Ltd v FE Accommodation Pty Ltd & Anor [2021] NTCA 2 ('Appeal Reasons') at [113].
[3] Application to the High Court for special leave to appeal was refused on 2 December 2021.
[6] Liability Reasons at [53]-[57].
[11] Liability Reasons at [13], [71], [80].
[12] Liability Reasons at [154.11].
[13] Liability Reasons at [154.14].
[14] Liability Reasons at [154.14].
[15] Liability Reasons at [148], [181].
[16] Liability Reasons at [153], [181].
[17] Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1 ('Clark v Macourt') at [7] per Hayne J, at [26] per Crennan and Bell JJ, at [60] per Gageler J (in dissent), at [106] per Keane J, all citing Robinson v Harman [1848] EngR 135; (1848) 1 Ex 850 at 855; [1848] EngR 135; 154 ER 363 at 365 and Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 at [13].
[18] The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 80 per Mason CJ and Dawson J.
[19] Ibid, cited in Clark v Macourt at [28] per Crennan and Bell JJ.
[21] Clark v Macourt at [119] per Keane J, citing European Bank Ltd v Evans [2010] HCA 6; (2010) 240 CLR 432 at [11]- [13] per French CJ, Gummow, Hayne, Heydon and Kiefel JJ.
[22] TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130 at 157 per Hope JA (Meagher JA agreeing) and at 161 per Priestly JA.
[23] Clark v Macourt at [17]-[18] per Hayne J, citing British Westinghouse Electric & Mfg Co Ltd v Underground Electric Railways Co of London Ltd [1912] UKLawRpAC 43; [1912] AC 673 at 689 per Viscount Haldane LC.
[24] Clark v Macourt at [27] per Crennan and Bell JJ, citing The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 82 per Mason CJ and Dawson J, at [59] per Gageler J (in dissent), citing Haines v Bendall [1991] HCA 15; (1991) 172 CLR 60 at 63.
[25] Clark v Macourt at [27] per Crennan and Bell JJ, citing The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 82 per Mason CJ and Dawson J.
[26] Sabouni v Revelop Building and Developments Pty Ltd [2021] NSWSC 3 at [41] per Black J, citing Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 83 per Mason CJ and Dawson J, at 125 per Deane J, at 153 per Gaudron J.
[27] Ibid, citing Uszok v Henley Properties (NSW) Pty Ltd [2007] NSWCA 31 at [135] per Beazley J.
[28] Ibid at [42], citing New South Wales v Moss [2000] NSWCA 133; (2000) 54 NSWLR 536 at [72] and Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd [2003] HCA 10; (2003) 77 ALJR 768 at [38].
[29] Ibid, citing Schindler Lifts Australia Pty Ltd v Debelak [1989] FCA 311; (1989) 89 ALR 275 at 319 per Pincus J, approved in JLW (Vic) Pty Ltd v Tsiloglou [1994] VicRp 16; [1994] 1 VR 237 at 243 per Brooking J and Troulis v Vamvoukakis [1998] NSWCA 237 at 27 per Gleeson CJ.
[30] Troulis v Vamvoukakis [1998] NSWCA 237 at 29 per Gleeson CJ, approved in McCrohan v Harith [2010] NSWCA 67 at [128] per McColl JA (Campbell JA and Handley AJA agreeing).
[31] Sabouni v Revelop Building and Developments Pty Ltd [2021] NSWSC 31.
[32] Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1 ('Clark v Macourt').
[42] Appeal Reasons at [87]-[88].
[45] For the reasons set out in footnote 44, that this amount should be $815,043.
[47] For the reasons set out in footnote 46, that this amount should be $462,820.
[48] See Written Opening of the Plaintiffs for the trial on the assessment of damages dated 9 April 2024, [9]; oral submissions at Transcript, pp 178-179, 181; Plaintiffs' Further Outline of Submissions dated 16 April 2024, [29]-[30].
[49] Motor Accidents (Compensation) Commission v Motor Accidents Insurance Board (No 2) [2023] NTSC 71 at [7] per Blokland J, citing Territory Sheet Metal Pty Ltd v Australia and New Zealand Banking Group Ltd [2010] NTSC 3; (2010) 26 NTLR 1 at [192].
[50] Clark v Macourt at [17]-[18] per Hayne J, citing British Westinghouse Electric & Mfg Co Ltd v Underground Electric Railways Co of London Ltd [1912] UKLawRpAC 43; [1912] AC 673 at 689 per Viscount Haldane LC.
[51] See, for example, Haines v Bendall [1991] HCA 15; (1991) 172 CLR 60 at 66-67 per Mason CJ, Dawson, Toohey and Gaudron JJ and the authorities there cited.
[52] Ibid at 306 per Waller LJ (Robert Walker and Hobhouse LJJ agreeing), and at 307 per Hobhouse LJ.
[53] See Ajaimi v Giswick Pty Ltd (No 3) (2022) 67 VR 529 at [28] per M Osborne J.
[54] See Northern Territory v Griffiths [2019] HCA 7; (2019) 269 CLR 1 at [355] per Edelman J, citing Hungerfords v Walker; Commonwealth v Chessell (1991) 30 FCR 154 at 161-162 per Sheppard J and 163 per Wilcox J, citing Hungerfords v Walker; Hobartville Stud Pty Ltd v Union Insurance Co Ltd (1991) 25 NSWLR 358 at 364 per Giles J.
[55] Hobartville Stud Pty Ltd v Union Insurance Co Ltd (1991) 25 NSWLR 358 at 364 per Giles J. See also Commonwealth v Chessell (1991) 30 FCR 154 at 161-162 per Sheppard J and 163 per Wilcox J. See also Pooraka Holdings Pty Ltd v Participation Nominees Pty Ltd (1991) 58 SASR 184; Walker v FAI Insurance Ltd (1991) Tas R 258; State Bank of New South Wales v Yee (1994) 33 NSWLR 618; Commonwealth v Chessell (1991) 30 FCR 154.
[56] See Oral submissions at Transcript, p 179; Plaintiffs' Further Outline of Submissions dated 16 April 2024, [23]-[25].
[57] See Plaintiffs' Further Outline of Submissions dated 16 April 2024, [33]-[35].
[58] Transcript, pp 75-77; Exhibit P3, Appendix 11.
[59] Exhibit P3, [2.1]-[2.14], [5.7]-[5.8], [6.6]-[6.7]. The payment times under the Contract of Sale was varied by the parties by a deed of variation executed on 28 September 2017 (Ex D1).
[61] Exhibit P3, [2.16]-[2.17].
[63] Exhibit P5, [2.19]-[2.21]; [2.25]-[2.26].
[64] Exhibit P5, [2.22]-[2.23]; [2.27]-[2.28].
[70] Further Amended Statement of Claim, [72].
[71] JW Carter, W Courtney and GJ Tolhurst, 'Issues of Principle in Assessing Contract Damages' (2014) 31 Journal of Contract Law, 171 at 185.
[76] JW Carter, Carter's Breach of Contract, 2nd ed, 2018, LexisNexis Butterworths, [13-04], p 596.
[77] Ibid, pp 596-697. See also JW Carter, W Courtney and GJ Tolhurst, 'Issues of Principle in Assessing Contract Damages' (2014) 31 Journal of Contract Law, 171 at 197: 'It goes without saying that prima facie measures may be displaced by the facts'. It is expressly acknowledged in Clark v Macourt that the prima facie measure can be displaced: see at [28], [30] per Crennan and Bell JJ, at [107], [132] per Keane J. See also at [68] per Gageler J.
[78] JW Carter, W Courtney and GJ Tolhurst, 'Issues of Principle in Assessing Contract Damages' (2014) 31 Journal of Contract Law, 171 at 199.
[79] The term 'goods' is defined to include all chattels personal other than things in action and money, and to include emblements and things attached to or forming part of the land which are agreed to be severed before sale or under the contract of sale: s 5(1), SGA. No party suggested that the Camp and Plant and Equipment were 'things attached to or forming part of the land'.
[80] The term 'seller' is defined to mean a person who sells or agrees to sell goods: s 5(1), SGA.
[81] Despite being located in Div 1, headed 'remedies of the seller', s 53 refers to an action for damages by the buyer for non-delivery of the goods.
[82] The term 'buyer' is defined to mean a person who buys or agrees to buy goods: s 5(1), SGA.
[94] Liability Reasons at [85], [91], [96].
[96] See, for example, Joseph & Co Pty Ltd v Harvest Grain Co Pty Ltd (1996) 39 NSWLR 722 at 726-727 per Moore DCJ, citing Thompson (WL) Ltd v Robinson (Gunmakers) Ltd [1955] Ch 177 at 187 per Upjohn J.
[97] Affidavit of Vivian Clarence Oldfield, 5 December 2023, [38.2], [38.3], [41].
[98] Affidavit of Vivian Clarence Oldfield, 5 December 2023, [41].
[101] Segenhoe v Akins [1990] 29 NSWLR 569 at 582-583 per Giles J and the authorities there cited.
[103] See Table 4, Affidavit of Vivian Clarence Oldfield, 5 December 2023. I note that Table 4 includes the six fuel pods, but I have separated them out given the separate reference to them earlier in these reasons.
[104] Affidavit of Vivian Clarence Oldfield, 5 December 2023, Table 4 and [98].
[105] Affidavit of Vivian Clarence Oldfield, 5 December 2023, [99].
[106] The amount of the deduction put in argument was $175,000 for the seven fuel pods, but that was in error because the argument also deducted from the calculation of damages the amount effectively paid by RRT for the items referred to in paragraph [133] above, which included $25,000 for one of the seven fuel pods.
[113] There was no evidence before me regarding the value or condition of the drilling rig distinct from the other Table 4 Items.
[114] As referred to above, assessment of damages as at the date of breach is a general rule which may be displaced whenever it is necessary to do so in the interests of justice: Johnson v Perez [1988] HCA 64; (1988) 166 CLR 351 at 357 per Mason CJ; Vieira v O'Shea [2012] NSWCA 21 at [45] per Basten and Meagher JJA (Handley AJA agreeing); Ng v Filmlock Pty Ltd [2014] NSWCA 389; (2014) 88 NSWLR 146 at [56] per Gleeson JA (Tobias AJA agreeing).
[115] Affidavit of Vivian Clarence Oldfield,5 December 2023, [31]-[34], Annexure VCO7.
[117] Exhibit P3, [4.17]-[4.18].
[119] $5,000,000 / $6,000,000 x 100.
[120] $1,000,000 / $6,000,000 x 100.
[121] Liability Reasons at [189].
[122] Liability Reasons at [65]-[79].
[123] Affidavit of Oldfield, 5 December 2023, Annexure VCO4, Recital F.
[124] See Appeal Reasons, at [32]-[34].
[125] These amounts do not take into account GST.
[126] Further Amended Defence and Counterclaim filed on 14 December 2020, [27C(c)].
[128] McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 CLR 457 at 477-478 per Dixon J (Rich and McTiernan JJ agreeing). See also at 470 per Starke J.
[129] See Moffet Farms v Pauls Services & Sales Pty Ltd (1991) 7 SR (WA) 351 at 355 per Hammond J, citing Dies v British and International Mining & Finance Corp Ltd [1939] 1 KB 724 at 742, 744 per Stable J.
[130] Amended Defence and Counterclaim filed on 11 December 2018, [16].
[131] Liability Reasons at [12]-[13].
[132] Liability Reasons at [181].
[133] See Blair v Curran [1939] HCA 23; (1939) 62 CLR 464 at 531-532 per Dixon J; Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589 at 597 per Gibbs CJ, Mason and Aickin JJ.
[134] As to what materials can be considered for determination of a res judicata or an issue estoppel, see Willoughby v Clayton Utz (No 2) [2009] WASCA 29; (2009) 40 WAR 98 at [17]- [29] per Pullin JA (Wheeler and Miller JJA agreeing). The materials are the order of the Court, the pleadings and the reasons for decision.
[136] Shaw v Gadens Lawyers [2014] VSCA 74 at [59] per the Court.
[137] See Sherwin v Commens [2008] NTSC 45 at [68] per Southwood J; Motor Accidents (Compensation) Commission v Motor Accidents Insurance Board (No 2) [2023] NTSC 71 at [7]- [9]; MBP (SA) Pty Ltd v Gogic (1991) 171 CLR 657 at 666 per the Court.
FE Accommodation Pty Ltd & Anor
Gold Valley Iron Ore Pty Ltd [2024] NTSC 61
(2013) 253 CLR 1
(1991) 174 CLR 64
(1989) 16 NSWLR 130
(1954) 90 CLR 613
(1991) 172 CLR 60
(1988) 171 CLR 125
(2022) 67 VR 529
(1991) 25 NSWLR 358
(1988) 166 CLR 351
(2014) 88 NSWLR 146
(1933) 48 CLR 457
(2009) 40 WAR 98
(2009) 236 CLR 272
(2010) 240 CLR 432
(2000) 54 NSWLR 536
(2003) 77 ALJR 768
(1989) 89 ALR 275
(2010) 26 NTLR 1
(2019) 269 CLR 1
(1991) 30 FCR 154
(1991) 58 SASR 184
(1994) 33 NSWLR 618
(1996) 39 NSWLR 722
(1939) 62 CLR 464
(1981) 147 CLR 589
(1991) 171 CLR 657