[2016] VCAT 1954
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2016-11-22
Original judgment source is linked above.
Section 77 of the Planning & Environment Act 1987; Boroondara Planning Scheme; General Residential Zone; Five apartments in a four-storey building; Height of the building; Whether maximum building height exceeded; Natural ground level; Question of law
Andrew Scollo, Maria Kayak, Ashley Nesbitt, Jacquie Sharples, Andrew Mackinnon & Kerry Fairbank, Robert & Christine Townsend, Nigel Lewis, Martin McIntosh, Tom Mole, Geoff Tauro, Peter & Brenda Bahen, Duong Le & Thanh Ho, Jane Hargreaves & Eleanor Lam
Faversham Mews Pty Ltd v Boroondara CC [2016] VCAT 1954
Question
Does the height of the proposed building comply with the maximum building height under clause 3.0 of schedule 1 to the General Residential Zone in the Boroondara Planning Scheme?
Answer
No
For Tom Mole, Geoff Tauro, Peter & Brenda Bahen, Duong Le & Thanh Ho, Jane Hargreaves & Eleanor Lam
No appearance (2 November 2016) & Mr Andrew Mackinnon (4 November 2016)
Mr Panos Nickas, Best Hooper Lawyers (2 November 2016)
Dr Robert Townsend made a separate submission and attached to his written submission was the statutory declaration of Donald Campbell Gray dated 30 October 2016. Mr Gray was not required to be examined about his declaration.
Construction of five apartments in a four-storey building, plus basement
Application under section 77 of the Planning and Environment Act 1987 to review the Council's refusal to grant a permit
General Residential Zone (GRZ) Schedule 1 (Suburban Precincts Without A Consistent, Open Backyard Character)
Heritage Overlay Schedule 530 (HO530) (Yarra Boulevard Precinct, Kew)
The land is on the south side of Stawell Street, about 110 metres west of Studley Avenue and opposite the intersection with Yarra Street. It is rectangular in shape, with a frontage of 21.95 metres, a depth of 33.34 metres and an area of 730 square metres. According to the applicant's 'plan of relocation features and levels' dated 28 October 2015 the land falls 6.7 metres from the southwest corner to the northeast corner. The land is developed with a part two-storey and part three-storey building containing four apartments.
On 4 November 2016, the Tribunal inspected the land, 31A Stawell Street and 17 Dunlop Avenue, accompanied by the parties
Mrocki v Bayside CC [2015] VCAT 1371
Shire of Gisborne v King [1994] VicRp 23; [1994] 1 VR 364
Church Street Hawthorn Pty Ltd v Boroondara CC [2016] VCAT 766
Rizzi v Rockdale Municipal Council (1994) 85 LGERA 13
Benedetti v Moonee Valley CC [2005] VCAT 2227
Hooper v Mornington Peninsula SC [2008] VCAT 2115
Tribe v City of Greater Geelong [2002] 2 VPR 224
Lampard v Bayside CC [2005] VCAT 234
VPD Group Pty Ltd v Greater Geelong CC [2014] VCAT 913
32.08-7 Maximum building height requirement for a dwelling or residential building
The maximum height of a building used for the purpose of a dwelling or residential building must not exceed the building height specified in a schedule to this zone.
If no building height is specified, the requirement set out in the relevant standard of Clause 54 and Clause 55 applies.[3]
3.0 Maximum building height requirement for a dwelling or residential building
A building used as a dwelling or a residential building must not exceed a height of 9 metres unless the slope of the natural ground level at any cross section wider than 8 metres of the site of the building is 2.5 degrees or more, in which case it must not exceed a height of 10 metres.[4]
Building height The vertical distance from natural ground level to the roof or parapet at any point.[7]
Ground level The natural level of a site at any point.[8]
To ensure that the height of buildings respects the existing or preferred neighbourhood character.
[1] I have considered the submissions of all the parties that appeared, all the written and oral evidence, all the exhibits tendered by the parties, and all the statements of grounds filed. I do not recite or refer to all of the contents of those documents in these reasons. Dr Mole's statement of grounds was a group statement comprising eight individuals. All of them, except Duong Le & Thanh Ho, were entitled to be parties because they had objected to the Council against the grant of a permit. Duong Le & Thanh Ho were not entitled to be parties because they were not original objectors. I joined them as parties before the conclusion of the hearing.
[2] I have disregarded any opinions expressed by Mr Champion, Mr Loy and Mr Reed about the meaning of NGL. As the meaning is a question of law, the experts' opinions about meaning are irrelevant.
[3] Boroondara Planning Scheme cl 32.08-7. Certain exclusions are specified but none are relevant in this proceeding.
[4] Boroondara Planning Scheme cl 32.08 schedule 1 cl 3.0.
[5] Strictly, the calculation must be made in relation to NGL, once it has been established, and not in relation to the existing surface level of the land. Despite this point, it is unlikely the outcome would be any different.
[7] Boroondara Planning Scheme cl 72. Refer to no exemption for roof top plant and whether the plant shown on the plans is included as part of the roof. The parties proceeded on basis that it would. I agree.
[9] Mrocki v Bayside CC [2015] VCAT 1371 [44].
[10] Macquarie Dictionary, 3rd ed (1997).
[11] Mrocki v Bayside CC [2015] VCAT 1371 [48].
[12] Shire of Gisborne v King [1994] VicRp 23; [1994] 1 VR 364, 370.
[13] VPD Group Pty Ltd v Greater Geelong CC [2014] VCAT 913 [11].
[14] Church Street Hawthorn Pty Ltd v Boroondara CC [2016] VCAT 766 [17].
[15] Rizzi v Rockdale Municipal Council (1994) 85 LGERA 113, 115.
[16] Benedetti v Moonee Valley CC [2005] VCAT 2227 [31].
[17] For completeness, this was Mr Nickas' primary contention. His alternative contention was that NGL is 'the ground level of the land immediately before it was disturbed'.
[18] For example, in Mrocki, a dwelling was being constructed when the Tribunal heard the proceeding and the Tribunal had to decide if the dwelling had more than two storeys (excluding a basement) under a requirement in a Design & Development Overlay. Part of a basement projected above ground level and if it projected 1.2 metres or more above 'ground level' is would be a separate storey and the dwelling would have in total three storeys. A three-storey dwelling was prohibited. The Tribunal had to consider the meaning of 'ground level'. In King, the Court was required to consider the expression 'alteration to the natural conditions or the topography' of the land in the definition of 'works' in the context of an application for an injunction. In Rizzi, the NSW Court of Appeal had to consider whether there was a breach of a development consent condition requiring a specified building height reduction as measured to 'existing natural ground level'.
[19] In particular, I do not consider myself bound by the Court's decision in King because it was considering NGL in the context of the definition of works in the PE Act and not in the context of a building height control. For completeness, neither Mr Rantino nor Mr Nickas relied on Lampard v Bayside CC [2005] VCAT 234. In Lampard, the Tribunal considered the meaning of NGL in the context of a clause in an agreement restricting the height of a wall measured from NGL immediately below the measured point of the wall. The Tribunal proceeded to consider the meaning of NGL having regard to the parties' intentions. It found the 'natural' contours of the land had been changed by 'successive developments over many years'. It ultimately found NGL was the actual level of the ground at the frontage of the land before constructing the wall. This decision has little persuasive value in this proceeding.
[20] Mrocki v Bayside CC [2015] VCAT 1371 [48].
[21] Hooper v Mornington Peninsula SC [2008] VCAT 2115 [37].
[22] Tribe v City of Greater Geelong [2002] 2 VPR 224, 227.
[23] Mr O'Farrell agreed that the meaning contended by Mr Rantino and Mr Nickas would be correct if the land in a particular case had not been disturbed before the making of an application, but emphasised this is not the case in this proceeding. It would rarely be the case in areas of existing urban development.
[25] Written submission of Dr Townsend, p 10.
[26] Dr Townsend states, at pages 7 & 8 of his written submission, that Stawell Street was reconstructed in 1956/57, based on the date of two photographs of the construction of Yarra Street held at the Kew Library. If this is correct, the 1956 aerial photograph appears to have been taken before the works started.
[27] The plan is reproduced in the application drawings as drawing no. TP002.
[28] The north elevation does not show either of those levels, although I infer the architect intended the solid line also be identified as ground level at the title boundary. However, there is no NGL shown as a dashed line. The south elevation shows 'existing ground level at title boundary' as dashed, but does not show NGL. It does show 'ground level' as a solid line below the dashed line. I infer from this that the proposed ground level at the boundary will be lowered.
[29] Mr Champion, in cross examination, conceded it was possible that the dashed NGL on the elevations was not NGL on the title boundary but at some internal plane on the land.
[30] There is one exception to this finding, which relates to the levels across the front (street) boundary where NGL is not the levels of the top of the on-boundary retaining wall. However, a finding of NGL along this boundary is not critical to the question of law because no part of the propoed building is located on or near this boundary.
[31] The required interpolation is relatively minor, having regard to the marginally disturbed levels along the northern part of the east side boundary. There are much greater disturbed levels along the southern part of the east side boundary.
[32] In this analysis, I have not taken into account the rooftop plant platform. The line joining the two points on the east-facing and west-facing edges of the roof bisects the plant platform. A further question then arises as to whether building height needs to be recalculated over the length of the bisecting line having regard to the 0.8 metres height of the platform. At the hearing, Mr O'Farrell and Mr Rantino agreed that the provision does not expressly excuse or remove from calculation any rooftop plant. I agree with them. I will not proceed to make any recalculations but simply observe that the area of the third floor (fourth storey) that exceeds the 10 metres height limit may be marginally greater in the area below the rooftop plant.
Faversham Mews Pty Ltd
Boroondara CC [2016] VCAT 1954
(1994) 85 LGERA 13
(1994) 85 LGERA 113