(i) The alleged progress claim (no. 7) was not supported by such information as the Superintendent reasonably required, and therefore no entitlement to payment arose under clause 42.1;
(ii) Further, or in the alternative, the alleged progress claim was not made in conformity with the contract because such claims could only be made monthly, whereas this claim was not;
(iii) Further, or in the alternative, no contractual entitlement arose in the absence of a statutory declaration required by clause 43;
(iv) Further, or in the alternative, most of the items comprising the claim had previously been claimed in progress claim no. 6, and rejected by the Superintendent;
(v) Further, or in the alternative, the alleged progress claim was ambiguous, uncertain and of no effect by reason of the endorsement thereon of the words: "This claim is made under the Building & Construction Industry Security of Payment Act "..
10 The serious issue in respect of the plaintiff's claim under the Act is that the plaintiff could only serve a payment claim within the meaning of section 13 of the Act if, at the time of serving the payment claim, the plaintiff was entitled to a contractual progress payment and as it was not entitled under the contract the plaintiff had no entitlement under the Act. It was also suggested that on the proper construction of the Act the contractual claim had to be payable before the right to make a statutory claim arose
Discretionary reasons for not entertaining or granting the motion for summary judgment
11 The defendant relied upon the comments made by Bergin J in Baulderstone Hornibrook Pty Ltd v HBO & DC Pty Ltd [2001] NSWSC 821. Her Honour at paragraphs 7 to 11 set out the history of the way in which the commercial division was supposed to operate. Her Honour noted the various references in the Practice Note that as a general rule applications for summary judgment will not be entertained. She made reference to the amendment of the rules in January 2000 and referred to Part 1 rule 3 which provides: --
"The overriding purpose of these rules in the application to civil proceedings, is to facilitate the just, quick and cheaper resolution of the real issues in such proceedings."
12 Her Honour then referred to the current Practice Note 100 and in particular to paragraph 25 which is in the following terms: --
"The observation in the commentary of Practice Note 89, that as a general rule applications to strike out or for summary judgment will not be entertained, requires emphasis. Sometimes applications are appropriate, but increasingly applications are made which have little to commend them and only cause delay and additional costs. Practitioners should expect greater strictness in declining to entertain such applications.'
13 Her Honour noted that part of the Practice Note emphasises that it is only if it is clear that the just, quick and cheaper resolution of the case would be assisted by hearing an application for summary judgment that such applications could be entertained.
14 Her Honour had to consider the circumstances of that case which included the fact that the matter was raised at the time it was sought to obtain a hearing date for the motion for summary judgment and in the circumstances declined to hear the motion. In the present case these proceedings have been on foot since the summons was filed on 4 June 2002. On its return on 14 June 2002 it was stood over for a week so the defence could be filed and on 21 June after the filing of the defence the matter was fixed as a motion for summary judgment and appropriate directions given. Apparently no submissions were made at that stage that the motion was inappropriate.
15 When the matter first came before me the point was raised as a preliminary matter. I declined to accede to the application and when the matter came back before me on the adjourned hearing the application was repeated. I declined to accede to it for the reasons that I then gave. On both occasions the parties had incurred the expenses of preparing for a hearing and in practical terms refusing to continue with a hearing of the motion would save nothing. In these circumstances I think that I should proceed with the hearing. Applications of this nature should in the ordinary course be made at the time it is sought to set the motion down for hearing.
The plaintiff's claim for summary judgment
16 I have already set out above the terms of the relevant clauses in the general conditions. These clauses are substantially the same as those which were considered by Rolfe J in Algons. The case was one where the sub-contractor brought a motion for summary judgment and the contractor endeavoured to raise a defence by way of equitable set off. The issue for his honour was whether, on a proper construction of the contract, the contractor was bound to pay the amount of the progress claim without recourse to the equitable set off, on the basis that the amount was now due and payable. His Honour found that the contractor was bound to pay the amount without regard to any other claim or set off. His Honour also held that in the circumstance (which happened in the case) that no payment certificate was issued the parties were returned to the position where there was an obligation on the contractor to pay the progress claim.
17 In Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 49 the Full Court was concerned with a situation where the payment certificate was issued after the 14-day period allowed under a clause, which in material respects was the same as that which I am considering. They concluded that in the circumstance where a payment certificate was issued late and therefore invalidly the practical consequence is that that there is no valid payment certificate in existence and therefore "no certificate" for the purposes of clause 42.1. The result was that the principal must pay the contractor's claim.
18 The court referred to the decision of Rolfe J in Algons and quoted and accepted part of his reasoning. The part that the Full Court quoted was in fact not from His Honour's decision referred to by the Full Court but a later unreported decision of His Honour between the same parties on 14 October 1997. As it sets out the commercial justification for the strict approach adopted by His Honour it is worth noting what His Honour said. At page 7 he said: --
"As appears from my earlier reasons the effect of a payment certificate is to require the recipient to pay the amount stated. Failure to do so can lead to summary judgment and there is no right to dispute the amount payable until the dispute resolution procedures are activated. Accordingly, the recipient of the certificate is required to pay money during the course of the contract which, at the end of the day, it may be found it does not owe. The requirement to pay money may lead to financial difficulties for the payer, just as the failure to receive money during the course of the contract may cause financial difficulties to the payee. Also the payee may not be able, at the end of the day, to refund any overpayment. Considerations such as these lead me to the conclusion that a certificate must comply strictly with clause 42.1 if it is to have the consequences specified."
19 The defendants did not suggest that these principles were wrong and clearly they would normally entitle a plaintiff to summary judgment. Instead it raised a number of matters which it submitted gave rise to a triable issue in the context of a summary judgement application relying upon the well known principles in General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 C.L.R. 125.
The defendant's triable issues on the contract claim
20 I turn to a consideration of each of the matters raised by the defendant in this respect.
The progress claim (no. 7) was not supported by such information as the Superintendent reasonably required, and therefore no entitlement to payment arose under clause 42.1
21 In its defence the defendant particularised the information as being the request contained in the letter from the superintendent to the plaintiff dated 3 May 2002. The letter was in the following terms: --
"I refer to your submissions of a progress report and advise that your report is inadequate. In particular, you have not itemised your request for variations so that they can be properly assessed, you have not explained your intentions with regard to outstanding Superintendent's directions, you have not provided a summary of hold points released to date or of outstanding hold points or of hold points in dispute, and you have not provided a summary of testing carried out to date.
I advise that I will not be in the position to review your progress claim until I have received and reviewed a satisfactory progress report."
22 The entitlement to receive information is based upon the opening subparagraph of clause 42.1 of the general conditions. That provision requires the contractor to deliver "to the superintendent claims for payment supported by evidence of the amount due to the contractor and such information as the superintendent may reasonably require". On a first reading of this clause it would seem that the claim when delivered needs to be supported by the appropriate information. The superintendent would need to have identified the information prior to the lodgement of the claim. Making a request after the lodgement of the claim would not be in accordance with the clause.
23 No doubt because of this argument, in submissions, the defendant went beyond the terms of the material pleaded in its defence and suggested that the information reasonably required was that which had been sought by the superintendent in his letter of 18 April 2002. Although outside the terms of the defence it is appropriate here to consider that material to see whether it might give rise to a triable issue. The letter of 18 April 2002 was in the following terms: --
"I have reviewed my files including those handed to me by the previous superintendent and have not found any progress reports as is required under clause 22 of the special conditions of contract. I advise that your submission of progress claims do not constitute progress reports.
Accordingly I confirm the advice of 17 April 2002 that I am unable to agree to your proposed progress meeting on 18 April 2002 until such time as I have received from you a progress report on the whole of the contract to date in the format that I have attached.
I direct that you provide me with a progress report in accordance with the attached format by 4.00 pm on 30 April 2002."
24 The letter enclosed a form headed "contractor's monthly report", which was the one which was filled out and submitted under cover of letter of 29 April 2002 from the contractor to Council. Although he expressed his view that he sent the letter for the purpose of assessing the next progress claim when it was submitted, that is not apparent to the contractor on the face of the letter. For the purpose of this application I will proceed on the basis that the information was required as a result of this letter.
25 It can be seen from the letter of 3 May that the superintendent was of the view that the information supplied in that report was not sufficient. Without going into the merits of whether or not sufficient information was supplied or whether it was supplied within time it is useful to consider whether, in the absence of the information, the superintendent was entitled to refuse to consider the progress claim and thus not issue the payment certificate. The defendant's contention was that the time period would not commence to run for the purposes of clause 42.1 if there was not the supply of such information as the superintendent "may reasonably require".
26 The plaintiff's submissions on this aspect were that the superintendent's dissatisfaction or, indeed, the failure to include the information with the progress claim, is of no consequence under the terms of the contract. It was submitted that his contractual obligation under clause 42 is to make an assessment and to issue a certificate or alternatively the consequences provided for in the condition would follow. The plaintiff submitted that the superintendent could not use his dissatisfaction in order to suspend his obligation to assess. Rather what he should do is to carry out his obligation to assess in the light of the information before him. If the information he then has is insufficient then no doubt in his assessment he would not include items which were not supported by what the superintendent considered to be information which he reasonably required.
27 The defendant's submission was in effect that the supply of the information was a condition precedent to the superintendent's obligation to consider and assess. It is to be noticed that at the end of the second paragraph of the clause the superintendent is to set out the amount that in his opinion is to be paid. He is to set out his calculations in writing of the amount and his reasons for the difference. That procedure certainly allows the superintendent to cater for the situation where insufficient information in his opinion or, indeed, no information has been supplied. If the contractor is foolish enough to not comply with the reasonable request of the superintendent he cannot be heard to complain if the superintendent treats his claim harshly. In these circumstances it is hard to see how the obligation on the superintendent that he "shall issue" should be suspended. The reasoning behind the cases to which I have referred would not support such a construction. It would be necessary to imply a condition precedent to the effect contended for by the defendant. Such a condition would be inconsistent with an express term of the contract, namely, "if no payment certificate has been issued, the principal shall pay the amount of the contractor's claim". This express term has no qualifications to its operation.
28 Whether or not the information supplied to the superintendent was within the terms of the clause is a factual matter, which in the present case if it were relevant would raise a triable issue. Similarly the failure to supply the information in the monthly report along with the progress claim would raise a triable issue. The question is whether one can imply a condition precedent that suspends the obligation to assess. In my view, having regard to the express terms of the contract one cannot and, accordingly, I do not think that there is a triable issue on this ground.
The progress claim was not made in conformity with the contract because such claims could only be made monthly, whereas this claim was not
29 The contract in this matter was entered into on 3 October 2001. Clause 42.1 refers to claims for payment being made at the time stated in the annexure. The annexure specifies "monthly". The evidence establishes that progress claims were made on the following dates: 30 October 2001, 7 December 2001, January 2002, 31 January 2002, 1 March 2002, 27 March 2002 and 26 April 2002.
30 The submission of the defendant was that on the proper construction of the contract a progress claim made on 26 April 2002 could not consistently with the contract be made until 3 May 2002. I was not directed to any authority in support of the defendant's proposition but the dictionary definition of the word "monthly" is of assistance. The Shorter Oxford English Dictionary definition of the word is as follows: --
"Once a month; in each or every month; month by month."
31 Given that the previous progress claim was in the month of March I see no basis for suggesting that a claim made on the 26th of April would not fall within the definition of monthly. In the circumstances I see no triable issue on this aspect.
No contractual entitlement arose in the absence of a statutory declaration required by clause 43
32 Clause 43 of the contract provides for the supply of a statutory declaration as to the payment of subcontractors. In this case no such declaration accompanied the progress claim No 7 and the evidence discloses that the contractor provided a declaration to the superintendent on 13 August 2002. This date is of course well after the commencement of these proceedings in June 2002. The terms of clause 43 of the contract are as follows: --
43 PAYMENT OF WORKERS AND SUBCONTRACTORS
(a) Before the Principal makes each payment to the Contractor, the Superintendent may, not less than five days before a Payment Certificate is due, in writing request the Contractor--
(i) to give the Superintendent a statutory declaration by the Contractor or, where the Contractor is a corporation, by representative of the Contractor who is in a position to know the facts declared, that all workers who have at any time been employed by the Contractor on work under the Contract have at the date of the request been paid all monies due and payable to them in respect of their employment on the work under the contract; and
(ii) to provide documentary evidence to the Superintendent that at the date of the request all workers who have been employed by a Subcontractor of the Contractor have been paid all monies due and payable to them in respect of their employment on the work under the Contract.
"(b) Not earlier than 14 days after the Contractor has made each claim for payment under Clause 42.1, and before the Principal makes that payment to the Contractor, the Contractor shall give to the Superintendent a statutory declaration by the Contractor or, where the Contractor is a corporation, by a representative of the Contractor who is in a position to know the facts declared, that all subcontractors have been paid all moneys due and payable to them in respect of the work under the contract.