· no Payment Schedule issued - plaintiffs allege due under the Act on 19 May 2004
· no Progress Certificate issued - plaintiffs allege due under the Contract on 19 May 2004;
· the plaintiffs contend that an amount became due and payable on 19 May 2004;
· section 17(2) Notice - Intention to apply for adjudication 6 July 2004 (VS 5, Schokman aff 20.9.04);
· adjudication application dated 15 July 2004 [Received between 17-19 July 2004 (Schokman aff 20.9.04, para 17; MD 10, Derbyshire aff 18.11.04)];
· On 30 July 2004, the second defendant, O'Mara, faxed and sent by post to Xception, Notice of Acceptance of the Adjudication Application under s.19 of the Act (paragraphs 4 and 21 of Affidavit of Mark Derbyshire sworn 18 November 2004, Exhibit MD-1);
· letter from the Master Builders Association dated 27 July 2004 advising that a Mr O'Mara had been nominated as adjudicator and that "…He will be in contact with you to advise of the carriage of the matter..". [Received on 31 July 2004 (Schokman aff 20.9.04, para 18, VS 7)];
· there has become no need to determine a factual dispute referred to in the evidence between the parties as to whether Mr O'Mara faxed and sent by post to Schokman the same s.19 Notice on 30 July 2004 -the plaintiffs have not pressed their submissions relating to section 19 of the Act ;
· the first plaintiff contacted Sofia Mackow of the 2 August 2004 Master Builders Association and requested all further communications were to be directed to the plaintiffs' solicitors (Schokman aff 20.9.04, para 19; C Schokman aff 1.3.05, para 3);
· adjudication determination 12 August 2004 (VS 9, Schokman aff 20.9.04);
· letter from the adjudicator dated 12 August 2004 advising that an adjudication of the disputed payment claim had been completed [Received on 14 August 2004 (Schokman aff 20.9.04, para 20, VS 8)];
· the first plaintiff's evidence that he had contacted the Adjudicator on 16 August 2004 and said to him: "How could the adjudication have proceeded when we had no opportunity to present our case?" is likewise of no relevance, the section 19 attack on the validity of the adjudication having been withdrawn (Schokman 20.9.04, para 21; Schokman 27.9.04, para 2; C Schokman aff 1.3.05 Para 5-6; Cf O'Mara aff);
· letter from the adjudicator enclosing 17 August 2004 the adjudication determination [Received 21 August 2004 (Schokman aff 20.9.04, para 22)].
Dealing with the issues raised
The validity of the payment claim
5 Substantial written and oral submissions were addressed by both parties to the question of whether or not the payment claim was invalid. The matter is of some complexity. The issue is particularly complicated because of some vagueness in the 5 April 2004 agreement. Certainly the payment claim was sparse compared with earlier claims [for example compare the extensive detail given in MD 5 and 6]. I have grave reservations in relation to the contention that the payment claim identified the construction work to which the progress payment related so as to satisfy the dictate of section 13 [cf also a comparison of (1) the claimed 'previous payment' and (2) the April 2 Progress Certificate No. 14 document with annotated date paid stamps for 2 and 6 April 2004]. However, in the view which I take on the other issue dealt with below it is not necessary that the validity of the payment claim be determined.
Whether the section 17 (2) Notice was sent outside of the 20 statutory business days allowed
6 This issue concerns:
· the plaintiffs claim that the payment claim, if valid, was due and payable on 19 May 2004;
· the defendants claim that the payment claim was due and payable on 9 June 2004
7 The relevant scheme of the Act is as follows:
· section 11 of the Act defines "due date for payment" as the date provided under the Contract, or if the Contract makes no express provision, on the date occurring 10 business days after a payment claim is made;
· under s 14(4), if a payment claim is served and no payment schedule is provided within 10 business days after the payment claim is served or within the time required by the contract (also 10 working days), whichever expires earlier, the respondent becomes liable to pay the claimed amount. Section 15 sets out the consequences of not paying and the options available in pursuing the payment, either as a "debt" or via the adjudication process;