The Holdmark argument
12 It was common ground that no work had been done under the contract since 16 July 2007, and that for one reason or another the contract had come to an end by, at the latest, 31 July 2007. It was also common ground that the contract stated no "reference date" for the purposes of s 8 of the Act.
13 So far as it is relevant, s 8 works as follows. Firstly, by subs (1), it gives to a person who carries out construction work under a construction contract an entitlement to progress payments. (I omit, as of no present relevance, any reference now or later in the Act to the supply of related goods and services.)
14 Secondly, by subs (2), the section provides for identification of the reference date. As para (b) makes clear, where the contract does not state a reference date, it is "the last day of the named month in which the construction work was first carried out...under the contract and the last day of each subsequent named month".
15 It follows from what I have said that the first reference date was the 28th, 30th or 31st of whatever was the last day of the first month in which construction work was carried out and subsequent reference dates were the last days of subsequent months.
16 In those circumstances, it is common ground I think (and if it is not common ground I conclude) that 31 July 2007 was a reference date for the purposes of the contract.
17 Mr Bland submitted that the first adjudicator, Mr Stojanovski, had no jurisdiction to permit Rubana to withdraw its adjudication application within the ten business days laid down by s 21(3)(a) of the Act for its determination (there being no question of an extension of time under para (b)). Thus, Mr Bland submitted, there was no right in 3D to make a fresh application following the procedure laid down in s 26. Further, Mr Bland submitted, there was no other basis on which a further adjudication application could be made.
18 I am prepared to assume, although I do not decide, that it was not open to Mr Stojanovski to permit the application to be withdrawn during the ten business day period for its determination. I am prepared to proceed on that basis because a decision on that point is not necessary, and in my view difficult questions relating to the proper construction and application of the Act should not be decided unless their decision is essential for the resolution of a dispute.
19 The next step in Mr Bland's argument, and the key point, is that 3D had no right to serve a further payment claim because 31 July 2007 was the last reference date under the contract. That submission was founded on my decision in Holdmark. In that case, I concluded, where a construction contract had come to an end, the last reference date for the purposes of a payment claim under s 8 and s 13 was the last reference date following the last performance of work under the contract. If that conclusion were correct, then it was not open to 3D to serve further payment claims after August 2007, because there would not have been any more reference dates by reference to which they could be served and, by s 13(5), "[a] claimant cannot serve more than one payment claim in respect of each reference date under the construction contract". However, I do not think that it is open to me to proceed on the basis that what I said in Holdmark was correct. The issue was considered by the Court of Appeal in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 at 443-444 [62]-[66]. Hodgson JA (with whom Mason P and Giles JA agreed) there said that Holdmark was wrongly decided. His Honour held, in substance, that it was not correct to say "that reference dates cease on termination of a contract or cessation of work" (see 443[63]). His Honour said, in the same paragraph, that:
the only non-contractual limit to the occurrence of reference dates is that which in effect flows from the limits in s 13(4): reference dates cannot support the serving of any payment claims outside these limits.