Was Proyalbi's 14 August 2012 payment claim invalid?
13Grid Projects claims that Proyabli's 14 August 2012 payment claim was invalid because: -
"Proyalbi was not entitled to any progress payment after 30 June 2012 because no further work was carried out or undertaken to be carried out after the reference date of 30 June 2012. Proyalbi had already issued a payment claim for the reference date of 30 June 2012. It was not entitled to issue the payment claim made by [the 14 August 2012 invoice] because it was not entitled to a progress claim for a later reference date."
14Section 8(1) of the Act provides that "on or from each reference date" under a construction contract, a person who has undertaken to carry out construction work "is entitled to a progress payment".
15The question of "reference date" is dealt with by s 8(2) of the Act. Section 8(2) states what "reference date" means "in this section". Ms Oakley, who appeared for Grid Projects, submitted that it was "clear" that, despite these words, the term "reference date" is used in the same sense throughout the Act. Mr Roberts SC, who appeared for Proyalbi, accepted that this was so.
16Section 8(2) is in the following terms: -
"(2) In this section, reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or
(b) if the contract makes no express provision with respect to the matter - the last date of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month." (emphasis in original)
17Section 8(2) contemplates two different circumstances. One is where a date can be determined "in accordance with the terms of the contract" as "the date on which a claim for a progress payment may be made in relation to work carried...under the contract". The other is where "the contract makes no express provision with respect to" the date on which such a progress claim can be made.
18The present case falls into the second category, as the contract made no such "express provision".
19In that case, the "reference date" is the "last date of the named month in which construction was first carried out...under the contract" and "the last day of each subsequent named month".
20My attention has not been drawn to any authority that considers the meaning of the expression "named month" in this section. In Rubana Holdings Pty Ltd v 3D Commercial Interiors Pty Ltd [2008] NSWSC 1405, McDougall J described the operation of s 8 of the Act at [12] to [16] but did not, in terms (as it was not relevant for his Honour to do so) deal with this aspect of the section.
21In my opinion, in the context in which it appears in s 8 of the Act, the expression "named month" means the month "named" in the claim for a progress payment as being the month in which the work referred to in the claim for progress payment was undertaken.
22Thus, the "last day of the named month in which the construction work was first carried out" in this case was 30 November 2011; as construction work was first carried out in November 2011.
23Similarly, "the last day of each subsequent named month" was the last day of each subsequent month in which work was undertaken, as named in a claim for progress payment.
24The last month "named" in a claim for progress payment as being a month in which work was undertaken was June 2012; hence the last "reference date" to arise under the contract was the last day of that month: 30 June 2012.
25Proyalbi served a payment claim (that of 2 July 2012) in respect of that "reference date".
26Section 13(5) of the Act provides: -
"A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract."
27On the face of it, that would appear to prevent Proyalbi from serving a second payment claim (such as that of 14 August 2012) in respect of that reference date.
28The difficulty with this approach is that it appears to be inconsistent with that favoured by Hodgson JA (with whom Mason P and Giles JA agreed) in Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 at [63] where his Honour said: -
"However, s 8(2) of the Act does not provide that reference dates cease on termination of a contract or cessation of work. This may be the case under s 8(2)(a) if the contract so provides but not otherwise; while s 8(2)(b) provides a starting reference date but not a concluding one. In my opinion, the only non-contractual limit to the occurrence of reference dates is that which in effect flows from the limits in s 13(4): reference dates cannot support the serving of any payment claims outside these limits."
29Section 13(4), to which Hodgson JA referred, provides, relevantly, that a payment claim can only be served within 12 months after construction work was last carried out.
30As can be observed, Hodgson JA did not refer to the requirement in s 8(2)(b) that the "reference date" be determined by reference to the "last day of each subsequent month".
31Since Brodyn, the Court of Appeal has considered a factual situation similar to that in the present case in Dualcorp Pty Limited v Remo Constructions Pty Limited (2009) 74 NSWLR 190.
32In that case, Allsop P held that the Act was "not intended to permit the repetitious use of the adjudication process to require an adjudicator or successive adjudicators to execute the same statutory task in respect of the same claim on successive occasions" (at [2]).
33His Honour said: -
"[9] Here, Dualcorp, after undertaking the works, left the site in November 2007. It claimed to have substantially completed the works under the contract in November 2007.
[10] A payment claim was made on 29 January 2008 attaching six invoices, four of which were dated 24 January 2008 and two of which were dated 29 January 2008. The relevant reference date was not identified on the claim or invoices.
[11] On 3 March 2008, Dualcorp purported to serve a second payment claim annexing the same invoices and claiming the same amount. Again, no reference date was identified on the documentation.
[12] Whether or not this was a final claim or a progress claim does not matter. The claim represented by the six invoices must have been in respect of only one reference date - either 15 December 2007 or 15 January 2008, if pursuant to Annexure A, Item 11 or the reference date pursuant to the operation of cl 8.13, if a final payment claim. In either case, there must have been one reference date under the contract or the last day of the month as provided for by the [Act], s 8(2)(b).
[13] I see no warrant under either the contract or the Act, s 8 for permitting a party in Dualcorp's position to create fresh reference dates by lodging the same claim for the same completed works in successive payment claims. That is not the intended operation of the last phrase of s 8(2)(b) ('and the last day of each subsequent named month').
[14] Here, the work had been done; Dualcorp, the subcontractor, had left the site; it claimed payment by six invoices; six weeks later it repeated that claim by reference to the same invoices and, in my view, in respect of the same reference date. Dualcorp was prevented from serving the second payment claim. The terms of s 13(5) are a prohibition. The words 'cannot serve more than one payment claim' are a sufficiently clear statutory indication that a document purporting to be a payment claim that is in respect of the same reference date as a previous claim is not a payment claim under the [Act] and does not attract the statutory regime of the Act.
[15] For these reasons, Dualcorp was not entitled to proceed to judgment on a claim founded on the operation of the Act premised on the second payment claim of 3 March 2008 being a payment claim under the Act."
34As Ms Oakley acknowledged, the views expressed by Allsop P in Dualcorp "might be considered to differ" from those expressed by Hodgson JA in Brodyn.
35The tension between Allsop P's observations, and those of Hodgson JA has been recognised in at least one earlier decision of this Court. In Allpro Building Services Pty Ltd v C&V Engineering Services Pty Ltd [2009] NSWSC 1247 McDougall J said at [10]: -
"For the reasons that I gave in Rubana Holdings Pty Ltd v 3D Commercial Interiors Pty Ltd [2008] NSWSC 1405 at [19]-[21], I do not think it is open to a court of first instance to proceed on the basis that the relevant aspect of the decision in Brodyn was incorrect. Although Rubana was decided before Dualcorp, that does not seem to me to change the position. If there is something in Dualcorp which renders it appropriate for this aspect of the reasoning in Brodyn to be re-examined, that is a matter for the Court of Appeal."
36However, later decisions of single judges in the Court appear to favour acceptance of the views expressed by Allsop P: eg City of Ryde v AMFM Constructions Pty Ltd [2011] NSWSC 1469 per Brereton J at [33] and The Trustees of the Roman Catholic Church for the Diocese of Lismore v T F Woollam and Son [2012] NSWSC 1559 per McDougall J at [41] - [49].
37The facts in Dualcorp were different from those in the present case. In Dualcorp the party in the position of Proyalbi had served a payment claim, applied for and obtained an adjudication in respect of that payment claim and then, dissatisfied with the result, served a further identical payment claim and sought an adjudication in respect of that second payment claim.
38Further, the majority (Macfarlan JA, with whom Handley AJA agreed) decided the case of the basis of issue estoppel (at [68]).
39Nonetheless, I consider the remarks of Allsop P (especially at [13]) to be of direct relevance to the issue before me, to be consistent with my reading of the Act, and to compel the conclusion I have expressed at [27] above. McDougall J came to the same conclusion in similar circumstances in The Trustees of the Roman Catholic Church at [48]-[49].
40Proyalbi could have, but did not, make a s 17 adjudication application following receipt of Grid Projects' payment schedule of 11 July 2012. It did not do so; and it is now too late (s 17(3)(c)).
41By reason of s 13(5) of the Act, Proyalbi was not, in my opinion, entitled to serve a second payment claim (that of 14 August 2012) in respect of the "reference date" of 30 June 2012. That purported payment claim did not provide a jurisdictional basis for the Adjudicator to make the Determination; that is, the Adjudicator had no jurisdiction to make a determination on the basis of the purported payment claim of 14 August 2012.
42The Adjudicator came to a contrary view. But that does not bind me. The existence of a valid "payment claim" was a pre-requisite to the Adjudicator's jurisdiction, in the absence of which he had no jurisdiction: see Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393 per Spigelman CJ at [33] to [55]; Basten JA at [95] and McDougall J at [199] to [237].
43That finding is sufficient to dispose of the proceedings. The Determination was made without jurisdiction and is void.
44Nonetheless, in deference to the arguments put by counsel on the remaining issues, I shall consider them, albeit briefly.