18 In Macleay Nominees Pty Ltd v Belle Property East Pty Ltd [2001] NSWSC 743 Palmer J referred to the need, in cases where an offsetting claim is advanced, to adduce some evidence to show the basis upon which the loss is said to arise and how that loss is calculated. In terms of the amount of the offsetting claim the evidence to my mind is sufficient to demonstrate an offsetting claim in the sum of $27,231. The real question that arises on this application is whether the plaintiff, in the light of the circumstances that have occurred, is still able to maintain that claim against the defendant. The defendant's claim is that they have a final judgment in the District Court which has not been set aside pursuant to the provisions of section 25 of the Act. They submitted that this provision prevents the statutory demand from being set aside. They also submitted that the determination that gave rise to the judgment prevents the plaintiff from making its claim on the basis of the principles of res Judicata or issue estoppel.
19 This requires consideration of the scheme of the Act with particular attention being paid to its recent amendments.
20 Part 2 of the Act provides for a statutory right to receive progress payments for construction work. Following its recent amendment the Act now defines progress payment under s 4 (a) to include a final payment for construction work carried out under a construction contract such as is the case here. The definition of construction work has also been widened by s5 to apply not just to "buildings or structures" but to "buildings, structures or works". Where a contract does not so provide the legislation deals with the intervals within which progress payments are to be made (s8), valuation of a progress payment and construction work (ss 9, 10) and the time allowed for a progress payment (s11).
21 Part 3 of the Act details the procedure for recovering progress payments and the adjudication process. In particular, ss 15 and 16, deal with the consequences of not paying a claim where a payment schedule is or is not in existence. Following the recent amendments sections 15 (4) and 16 (4) provide that defences and cross claims cannot be raised by a respondent where it has failed to pay a claimed amount and the claimant has commenced proceedings to recover that amount as a debt. These provisions are mirrored by s 25 (4) which has also been recently inserted into the Act. This provides, relevantly:
25 Filing of adjudication certificate as judgment debt
(1) An adjudication certificate may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly.
(2) An adjudication certificate cannot be filed under this section unless it is accompanied by an affidavit by the claimant stating that the whole or any part of the adjudicated amount has not been paid at the time the certificate is filed.
(3) If the affidavit indicates that part of the adjudicated amount has been paid, the judgment is for the unpaid part of that amount only.
(4) If the respondent commences proceedings to have the judgment set aside, the respondent:
(a) is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract, or
(iii) to challenge the adjudicator's determination, and
(b) is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.
22 According to the defendant section 25 (4), as it prohibits any cross claim or defence from being raised in respect of judgment for debt, effectively prevents the plaintiff from raising its offsetting claim by attempting to have the statutory demand set aside. This however on its face appears inconsistent with the words at the commencement of s 25 (4) which limit its operation to a particular form of proceeding.
23 There has been some discussion of ss 15, 16 and 25 and the tension they create with s32 of the Act, see: P Dawson "Security of Payment in the Building and Construction Industry: from 'Security' to 'Payment '" (2003) 19(2) BCL 107. Section 32 still preserves any contractual rights the parties may have and still allows for the application of normal civil law remedies in the event of a dispute. It provides:
32 Effect of Part on civil proceedings
(1) Subject to section 34, nothing in this Part affects any right that a party to a construction contract:
(a) may have under the contract, or
(b) may have under Part 2 in respect of the contract, or
(c) may have apart from this Act in respect of anything done or omitted to be done under the contract.
(2) Nothing done under or for the purposes of this Part affects any civil proceedings arising under a construction contract, whether under this Part or otherwise, except as provided by subsection (3).
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal:
(a) must allow for any amount paid to a party to the contract under or for the purposes of this Part in any order or award it makes in those proceedings, and
(b) may make such orders as it considers appropriate for the restitution of any amount so paid, and such other orders as it considers appropriate, having regard to its decision in those proceedings.
24 According to the plaintiff s32 indicates that an adjudicator's decision is not exempt from normal civil law remedies and its entitlement in law to assert a genuine dispute under s459G of the Corporations Act 2001 (Cth) remains unaffected. In his second reading of the Building and Construction Industry Security of Payment Amendment Bill 2002 before the New South Wales Parliament dated 12/11/02, the Minister said at 6541 of the new provisions:
?By raising in court defences such as that the work does not have the value claimed or that the claimant has breached the contract by doing defective work, some respondents have been able to delay making a progress payment for a long time. Those respondents have forced claimants to incur considerable legal costs. They have effectively defeated the intention of the Act. To overcome the problem, the bill clarifies that in court proceedings by a claimant to enforce payment of the debt due under the Act, a respondent will not be able to bring any cross claim against the claimant and will not be able to raise any defence in relation to matters arising under the construction contract. A respondent who wants to raise these matters must do so in a payment schedule in response to a payment claim under the Act, or in separate proceedings. ?
25 While the Minister was very clear in emphasising the importance of the new provisions in preventing procedural abuse it is apparent from his closing words that where a respondent wished to make a cross-claim or raise a defence they were still entitled to do so in separate proceedings. What does not seem to have been addressed is the situation that occurs in this case where there is sought to be an enforcement of the judgment by some other procedure.
26 The various amendments brought in by the amending Act to further the purpose of the Act are in their terms specifically limited to matters under the Act. In Musico v Davenport & Ors [2003] NSWSC 977 McDougall J held that there was no basis for reading the prohibitions in s25 (4) (a) as extending beyond the context to which they were expressed to apply: namely an application to set aside judgement. He was there dealing with an application for prerogative relief against an adjudicator. In view of this, s25 (4) must only apply to the proceedings actually brought to set aside a judgment debt and not, as is the case here, where the plaintiff in separate proceedings seeks to set aside a statutory demand made in respect of the debt. In such proceedings the plaintiff is simply relying upon the rights that he has under a construction contract to raise an offsetting claim. The raising of an offsetting claim, unlike the raising of a genuine dispute in respect of a debt, does not in any way challenge the existence of the judgement debt and in fact concedes it. It is to be remembered that the scheme in respect of statutory demands comprehends offsetting claims of all descriptions and not only ones in some way connected to the claim in the demand. It is a far wider situation than the evil to which the Act is directed which is exemplified in Modern Engineering v Gilbert-Ash [1974] A.C. 689 at 717-718.
27 This finding, although perhaps arbitrary, accords with the preservation by s32 of the parties' rights to bring proceedings apart from the Act and also with the original intention of the legislature in respect of adjudication under the Act which was that it should only be an interim step which did not prevent application to the courts in respect of the final amount due. In his second reading speech of 8 September 1999 to the passage of the Act the Minister said, at 105: