JUDGMENT
1 His Honour: This is an application to set aside a statutory demand served on the plaintiff by the defendant. The statutory demand is dated 4 November 2008 and seeks an amount of $43,258.95. In the schedule to the demand the description of the debt showed that it arose from a judgment entered in the Local Court Downing Centre on 18 August 2008.
2 The parties were involved in a construction contract and the defendant was the builder for the plaintiff developer.
3 The judgment to which the demand relates was one which was obtained in the District Court following an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (the Act). The adjudication was issued on 1 August 2008 for an amount of $43,114.95. The adjudication was in respect of progress claims and not a final payment.
4 The application is made on the basis that the plaintiff has an offsetting claim substantially exceeding the amount of the judgment. The offsetting claim is based upon a claim for liquidated damages as a result of delayed completion and a claim for rectification costs for works on the property.
5 The liquidated damages claim is a substantial claim that was included in the adjudication application by the plaintiff for an amount of $380,279. The amount liquidated damages for $2,333.50 per day for 163 days.
6 The defendant's answer to the claim was to make an extension of time claim through the superintendent appointed under the construction contract. Extensions of time claims are allowed in the contract for delays resulting from issues such as variations or bad weather. The superintendent's allowed date for practical completion was 12 December 2007.
7 The defendant relied on a report saying it was entitled to further extensions of time extending the date for practical completion to 10 April 2008. In fact completion was obtained on 23 May 2008 and the adjudicator accepted the defendant's application and extended the time to 10 April 2008. He did not vary the date for practical completion. He found liquidated damages for an amount of $100,319.
8 After disputes arose about the work and the plaintiff engaged another company, Intek, to carry out the works necessary to rectify the defective and incomplete work. For example, there are accounts for some of the rectification work for an amount of $140,921.31. The question of defects was raised before the adjudicator and because there was a defect's liability to provide for the rectification of faults or omissions this meant that those matters should be dealt within the defects and liability period and should not be subtracted from the progress claims then made.
9 The material before me demonstrates that in respect of each of these areas of claims the plaintiff has an offsetting claim that is not fictitious or illusory in an amount exceeding the amount of the statutory demand. The defendant does not seriously debate that conclusion.
10 Instead the defendant raises a fundamental objection as to whether these claims, which would normally be resolved in proceedings under the contract pursuant to s 32 of the Act, can be offsetting claims for the purposes of s 459H of the Corporations Act. A claim concerning a defect in an affidavit was abandoned.
11 There is a well-established first instance line of authority that has permitted the setting aside of a statutory demand in the context of the Act where a plaintiff can demonstrate whether a genuine dispute or an offsetting claim under the Corporations Act 2001 (Cth). See Max Cooper & Sons (Builders Pty Ltd v M & E Booth & Sons Pty Ltd [2003] NSWSC 929; Demir Pty Ltd v Graf Plumbing Pty Ltd [2004] NSWSC 553 per Campbell J; Greenaways Australia Pty Ltd v CBC Management Pty Ltd [2004] NSWSC 1186 per Barrett J; Aldoga Aluminium Pty Ltd v De Silva Starr Pty Ltd [2005] NSWSC 284 per Palmer J; and Falgat Construction Pty Ltd v Masterform Pty Ltd [2005] NSWSC 525 per Macready AsJ.
12 Recently in BBB Constructions Pty Ltd v Frankipile Australia Pty Ltd [2008] NSWSC 982, Brereton J spoke of the current state of the law in these terms:
"[2] Although in the past it was contentious, it is now well established that the circumstance that a creditor's statutory demand is founded upon a debt arising from an adjudication under the Building and Construction Industry Security of Payment Act does not preclude the setting up of an offsetting claim pursuant to s 459H on an application to set aside such a demand: Greenaways Australia Pty Ltd v CBC Management Pty Ltd [2004] NSWSC 1186; Demir Pty Ltd v Graf Plumbing Pty Ltd [2004] NSWSC 553at [18]-[20]; and, in particular, in respect of an offsetting claim Aldoga Aluminium Pty Ltd v De Silva Starr Pty Ltd [2005] NSWSC 284."
13 The defendant submitted that there is a body of law which is authority for the proposition that where Parliament has evinced a clear intention for the payment of statutory sums of money "forthwith" - under an express statutory regime - the provisions of the Corporations Act relating to offsetting claims cannot operate to circumvent those payments. The "pay now, argue later" philosophy of the Act, which has been echoed in numerous cases, was said to be at the heart of the legislation. The defendants referred to the well known object of the Act set out in s 3 which are (emphasis added):
"3 Object of Act
(1) The object of this Act is to ensure that any person who undertakes to carry out construction … is entitled to receive, and is able to recover, progress payments ...
(2) The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement …
(3) The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves:
…
(c) the referral of any disputed claim to an adjudicator for determination, and
(d) the payment … so determined."
14 Their submissions continued that consistent with the 'pay now and argue later' philosophy of the Act, sections 15(4), 16(4) and 25(4) prohibit a respondent from bringing a cross claim or raising any defence when the claimant seeks to enforce payment under the Act. The only rights a claimant has once there has been a 'final' adjudication determination and subsequent judgment (as in this case) - are rights preserved under s 32 of the Act. Put another way, the defendant submitted that there is a body of law which is authority for the proposition that rights expressly preserved by s 32 of the Act - which remain in contemplation when the statutory debt is created by the adjudication determination and judgment - require payment 'forthwith' under the Act and thereby cannot operate as an offsetting claim.
15 The cases to which they referred were several first instance decisions and a recent decision of the New South Wales Court of Appeal. The first of these was Blue Hills Village Management (Liverpool) Pty Ltd v Babcock & Brown International Pty Ltd [2009] NSWSC 87, concerning an interim costs order made by the Court, which was payable forthwith. Barrett J held at [20]:
"[20] I am of the opinion that, in the particular circumstances of this case, there is no right to set-off the principal claims in the Commercial List proceedings against the separate and immediate obligation to pay the $70,000 payable forthwith. The plaintiff has not made out its case of offsetting claim within s 459H(1)(b)."
16 The case concerned an application under s 459G of the Corporations Act for an order setting aside a statutory demand with respect to an order made by the Court for indemnity costs, which the parties agreed to be in the minimum sum of $70,000. The same parties were involved in significant proceedings in the Supreme Court giving rise to a dispute of more than $15m. It was not in dispute that the plaintiffs' $15m claims were not arguable.
17 The order for interim costs thrown away was made in favour of the defendants and against the plaintiffs, due to the vacation of hearing dates. The order was that such costs were to be payable "forthwith." Following correspondence between the parties, a figure of $70,000 was agreed as a sum owing, due and payable at the time the statutory demand was issued (at [10], see also [7] to [9]).
18 Barrett J rejected the plaintiff's argument that the above was enough to give rise to an offsetting claim and thus an entitlement to an order setting aside the statutory demand pursuant to s 459H of the Corporations Act. His Honour noted the following submission put by the defendant in that case:
" [10] On the hearing before me, the present plaintiff conceded that, before the issue of the statutory demand, an agreement had been reached for the payment of $70,000 and that that sum was owing, due and payable at the time the statutory demand was issued and served. The present plaintiff does not accept, however, that, as the present defendants contend, the circumstances in which the agreed sum of $70,000 became so owing, due and payable are such as to put the admittedly genuine and arguable claim in the sum of more than $15 million in the Commercial List proceedings outside the definition of "offsetting claim" in s 459H(5) as it applies in this case.
…
[15] It must follow, so the submission runs, that the clear indication involving payment of $70,000 "forthwith" and acceptance of the "payment forthwith" proposition precludes, by necessary implication, resort to the principal claims in the Commercial List proceedings by way of set-off."
19 His Honour accepted the above submissions and at [17] held:
"I accept Ms Richardson's submissions. The context leaves no room for doubt, in my view, that the $70,000 was to be paid before adjudication of the principal claims in the Commercial List proceedings and regardless of the pendency of those claims and the outcome in those proceedings. That was the reason for separation out of the $70,000 and the requirement for payment forthwith. If the plaintiff's contention about a right of set-off were correct, the $70,000 would not be payable until the determination of the Commercial List proceedings. That would entirely defeat the purpose of both the court's direction as to costs and the parties' agreement based on it."
20 The defendant submitted that the above reasoning is of equal if not greater force to judgments under the Act for the following reasons: