© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2004] NSWSC 840
Supreme Court of NSW
2004-03-26
Original judgment source is linked above.
CITATION : Beckhaus v Brewarrina [2004] NSWSC 840 revised - 1/12/2004 15 to 26 March 2004 HEARING DATE(S) : 17 to 20 May; 31 May, 2004 1 and 8 June 2004 JUDGMENT DATE : 16 September 2004 JURISDICTION: Technology & Construction List JUDGMENT OF : Master Macready at 1 DECISION : Paragraphs 318, 318.
CATCHWORDS : Building and Construction - Contract - Claim for payment under contract to build earthwork levees - Whether payment claim valid - Cross-claim - Whether lump sum contract - Whether amount properly allowable for provisional variations - Whether practical completion achieved - Whether contractual requirements for progess claim met - Whether any breach of contract in respect of construction of levees - Whether Building and Construction Industry Security of Payment Act 1999 (NSW) applies -Misleading or deceptive conduct in the tender process. - Held: Practical completion not achieved. Contract was lump sum contract containing appropriate conditions for provisional quantities. Council entitled to damages for rectification of certain parts of the levees. Misleading and deceptive conduct established but no damges flow. LEGISLATION CITED : Trade Practices Act 1974 (Cth) Fair Trading Act 1987 (NSW) Beckhaus Civil Pty Ltd v Council of the Shire of Brewarrina [2002] NSWSC Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd [2003] NSWSC 266 CASES CITED : Fyntray Constructions Pty Ltd v Macind Drainage and Hydraulic Services Pty Ltd [2002] NSWC Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705 Henville v Walker (2001) 206 CLR 459 PARTIES : Beckhaus Civil Pty Ltd v Brewarrina Shire Council FILE NUMBER(S) : SC 55025/02 COUNSEL : M. Rudge SC & D. Robertson for plaintiff M.Christie & V. Culkoff for defendant SOLICITORS : Dutton Lawyers for plaintiff Paul Ward-Harvey for defendant
55025/02 - BECKHAUS CIVIL PTY LIMITED v THE COUNCIL OF THE SHIRE OF BREWARINNA (A BODY INCORPORATED SOLELY BY REASON OF THE LOCAL GOVERNMENT ACT 1993 (NSW)) JUDGMENT 1 Master: These are proceedings in which the plaintiff claims against the Council a sum of $838,969.10 being the claimed balance under a contract for the construction of a series of earthwork levees around the town of Brewarrina in North Western New South Wales. There is a cross-claim by the Council against the plaintiff and its principal Mr Dennis Beckhaus. The cross-claim is brought against the plaintiff for breach of contract and seeks damages for rectification of the construction work carried out by the plaintiff. The cross-claim is also brought against the plaintiff and Mr Beckhaus under the Trade Practices Act 1974 (Cth) and the Fair Trading Act 1987 (NSW). This claim alleges that there was misleading and deceptive information given as to the plaintiff's financial standing and the existence of a quality assurance program in the pre-tender process. 2 There is also a second cross-claim, which is brought by the plaintiff against Civil Engineering Testing Services Pty Ltd. That company carried out a series of geotechnical tests during the course of the contract on behalf of the plaintiff. The third cross-defendant did not appear to contest the second cross-claim and the plaintiff seeks to proceed against it in the event that it is unsuccessful in its defence of the defendant's cross-claim. The principal of the third cross-defendant gave evidence in the proceedings. 3 A judge of the court has referred the whole of the proceedings to me for hearing. Plaintiff's claim 4 The first claim made by the plaintiff is for the sum of $702,678.45 being the full amount of progress claim number 7 dated 26 April 2002. In the alternative a claim is made for the same amount under the Building and Construction Industry Security of Payment Act 1999 (NSW). 5 The plaintiff also claims on an alternative basis for damages for work done on the basis that it had completed the works under the contract and was entitled to recover its entitlement under the contract and variations which occurred during the course of the contract. The plaintiff had applied for practical completion in March 2003 which the Council denied. This alternative claim is in the sum of $838,969.10. During the course of the hearing the Council did not adduce evidence in respect of some variations and having regard to the size of some of them it was conceded that the plaintiff was entitled to succeed on variations numbered 1-9 and 12-15. The remaining variations, which are in issue, are numbers 10, 11,16,17,18,20 and 21. The plaintiff concedes variation number 19 in respect of gravel purchased by the plaintiff from the Council in an amount of $23,374.00. Short chronology 6 The levees around the town of Brewarrina were originally constructed in 1976. In 1991 there was an audit conducted by the New South Wales Department of public works in respect of the levees in which recommendations were made for further work to upgrade the levees. 7 After the flood in the year 2000, during which the population of Brewarrina were heavily engaged in saving the existing levees, the Council commissioned a redesign of the levees with a view to upgrading them to make them more effective. There was a design of new works to upgrade the levees by PPK Environment & Infrastructure Pty Ltd ("PPK"). There was a tender process and PPK recommended to the Council that the tender of the plaintiff company be accepted. This report was made on 9 August 2001 and on 25 September 2001 the Council accepted the recommendation. 8 The contract was entered into 13 October 2001 and work commenced the following day. The contract incorporated the general conditions of contract 2124-1992 which provided for the position of a superintendent. Mr Komp, an employee of the Council, was appointed superintendent on 16 December 2002. 9 Work continued under the contract through until March 2002 when it became apparent to the Council that the plaintiff, having nearly completed the works, was about to apply for a certificate as to practical completion. On 21 March 2002 the Council removed Mr Komp as superintendent and Mr Corven was appointed as superintendent. He immediately set about what the plaintiff described as employing a contractual broom against the plaintiff and on 22 March 2002 he issued a series of directions to the plaintiff. 10 As a result of receiving the various test results Mr Corven sent a series of letters at the end of March outlining his views as to the plaintiff's non-compliance with the contract. On 26 April 2002 progress claim 7 was lodged with the Council. The amount of the claim was for $702,678.45 payable by the Council to the plaintiff. 11 On 28 May 2002 Mr Corven issued progress certificate No 7 requiring payment by the plaintiff to the Council of $952,874.47. 12 These proceedings were commenced on 4 June 2002 and went through a number of interlocutory stages. These included an application for summary judgment on the plaintiff's claim which I granted and an appeal to the Court of Appeal in which that summary judgment was set aside. Council's cross-claim for breach of contract 13 There were many witnesses called by the Council in respect of their cross-claim including experts in various fields of the geotechnical sciences and other engineering specialties. The principal experts for the Council were Professor Fell and Dr Truscott. Professor Fell inspected the levees in early 2003 and concluded that much of the fill in the levy banks was uncompacted, the fill material was highly erosive, the levees could be breached at several locations under conditions of high flood and that lives may be lost as a consequence. Dr Truscott carried out geotechnical investigations in the first half of 2003 and concluded the one or more of the levees would fail in the event of a flood and that the safety of the levees required urgent attention. Dr Burman gave the principal geotechnical evidence on the part of the plaintiff. Both he and other witnesses called by the plaintiff disputed the correctness of the Council's testing and hence the opinions expressed by Dr Truscott and Professor Fell. 14 The Council's evidence on its cross-claim addressed both questions of liability and costs of rectification. It is necessary in order to understand the matter, to describe in a general sense the nature of the works carried out under the contract and the issues which have arisen as a result of the testing carried out during and after completion of construction of the levees. A short description of the works 15 The town was originally protected by what are known as the southern and northern levees. The contract included the upgrading of the northern levee and a small part of the southern levee. The balance of the southern levee became redundant because of the construction of new levees on the site of Charlton road and Tarrion Creek road. There was also constructed a new levee around parts of north Brewarrina which had not before been protected by the then existing southern and northern levees. The layout of the levees can be seen on the general layout plan, which is contained in various exhibits before the court. The construction of the levees on the site of the existing roads required a new road to be constructed on the top of the completed earth levee. 16 The levees were constructed with earth fill taken from particular locations known as "borrow pits". At the commencement of work these areas were tested for appropriate soil properties and in particular to see how much meadow lime needed to be added in order to achieve an appropriate linear shrinkage, which was a requirement of the contract. 17 At a point between the northern and southern levees there was constructed a levee with concrete walls which was referred to in the evidence as the Doyle street levee. There is an issue in respect of the concrete testing carried out in respect of that concrete work.
Principal issues arising under the cross-claim 18 The following main issues were identified in general terms in the opening submissions:
Whether the construction of the levees achieved the contractual requirements, which specified a compaction to 95 percent minimum dry density,
Whether the contractual requirements for stabilisation of the levee bank material as set out in clause 8.10 of the specification, which required linear shrinkage of the soil to be less than 12 percent had been achieved,
Whether key trenches, which were required under the specification at the foot of the new levy banks, were installed,
The effectiveness of various road pavements which were constructed on the top of the levee banks, and
Whether soil around the culverts, which were part of the construction, had been sufficiently compacted. 19 It will no doubt be appreciated that the resolution of the above questions depend substantially upon the various geotechnical tests which were carried out both during the course of contract and after completion of the contract works. The various geotechnical tests were carried out by different organisations and they were generally referred to in the evidence and in expert reports by reference to the name of the organisation that carried out the tests. 20 During construction the plaintiff had an extensive programme of compaction and linear shrinkage testing carried out under the terms of the contract by the third cross-defendant Civil Engineering Testing Services Pty Ltd, a company that has been referred to in the evidence and reports as "CETS". At the commencement of the contract the Council had a small number of tests carried out by way of audit by the company K & H Construction Services. This led to a confrontation between the plaintiff and the Council and in the event the Council carried out no further testing until the plaintiff had left the site. 21 In April 2002 after the plaintiff left the site, Douglas partners carried out a limited set of tests for the Council and gave a report, which generally recommended that the appropriate compaction had been achieved. On 25 March 2002 there were excavations for 13 tests carried out by Barnson Pty Ltd ("Barnson") at various locations to determine linear shrinkage. Notice of this testing was given to the plaintiff who attended and received duplicate samples. 22 In April 2003 Barnson carried out a series of compaction tests under the direction of Gutteridge Haskins and Davy ("GHD") on behalf of the council. A further test series was carried out in July 2003. These tests were carried out by the Council without the Council informing the plaintiff that the tests were to be conducted. They have generally been referred to in the evidence and the documents as the Barnson tests. 23 In August 2003 Golder & Associates ("Golder") carried out a series of tests on the plaintiff's behalf and in the presence of the representatives of Barnson, GHD and the Council. At the same time there was some parallel testing by Barnson on behalf of the Council..
Plaintiff's claim 24 The plaintiff's claim is expressed on an alternative basis. Its principal claim is that it is entitled to the sum of $842,944.40 for breach of contract in respect of the work, which it has performed under the contract. The breach alleged is a breach of the provisions of clause 3.1 of the general conditions of contract, which requires the principal to pay for work executed and completed under the contract. This claim is made on the basis that the plaintiff will be successful in either defeating the Council's cross-claim which alleges that the works were not properly performed and contained a number of defects or successful to the extent that there has been substantial performance of the contract with the Council being allowed a deduction for defects. 25 As a secondary breach the plaintiff alleges that in breach of clause 42.5 of the general conditions, the Council failed to issue a certificate of practical completion for the works. Although the obligation to make payment under clause 3.1 of the general conditions is arguably not conditioned upon the issue of a certificate of practical completion, such a certificate is important for other purposes under the contract. Under clause 42.8 the entitlement to the release of retention monies by the contractor is by reason of a number of the provisions of the contract conditioned upon the issue of a certificate of practical completion. The certificate of practical completion is also necessary in order to claim interest on overdue payments under clause 42.9 of the contract. 26 Leaving aside the question of the cross-claim and the defects alleged by the Council, the following matters arise on this part of the claim.
Q. You sought that information pursuant to clauses 8.3, 8.4 and 8.5 of the technical specification? A. I believe they're appropriate clauses, yes.
Q. Your second letter in behind tab 3, the letter of 22 March written one day after you embarked upon your job as superintendent; you see that? A. Yes, that's correct.
Q. You accept now that to have been an oral agreement between Beckhaus and Mr Komp that such survey information was not required? A. Yes.
Q. Notwithstanding that you assisted upon his supply? A. No.
Q. Mr Stratigis ultimately provided you with a survey that he had carried out? A. No, he provided me with some calculations based on the drawings.
Q. When you discovered this agreement. Did you write back and say: We no longer now require survey information or not. A. Yes - Not in those terms.
Q. You didn't, did you? A. But I did say this morning when you drew my attention to one of these documents clause 17 - item 17 that I had agreed that I understood there was an agreement.
Q. Before you wrote any of the letters that you wrote seeking documents and information to Mr Beckhaus in March, did you go and sit down and have a hand over meeting with Mr Komp to find what you could ask for and what you wouldn't having regard to what had gone on before? A. No, I didn't.
Q. You think that would have been something that a superintendent who is charged with acting reasonably and impartially ought to have done? A. Was that a question?
Q. Yes. Do you think that a superintendent charged with the obligation of acting impartially and fairly, ought to have spoken to the previous superintendent in some hand over meeting before going ahead with issuing directions? A. Mr Komp still-.
Q. Do you think it was something that ought to have been done? A. In normal circumstances Mr Komp did do work for council and I did have several conversations with him.
Q. You didn't have any discussions before you wrote your letters of the 22 or so March? A. That's irrelevant. The information which was required in the contract wasn't in the documents handed to council.
Q. If it wasn't in council's file irrespective of whether it was required by Mr Komp or not, you took the view that you could demand it? A. It was required under the contract.
Q. If the information that was required under the contract was not in the council's file and irrespective of whether or not Mr Komp during his administration had required it, you took the view that you had justification for demanding this provision? A. Yes.
Q. You regard such a stance as being one which demonstrates, on your part, that you were acting reasonably and impartially? A. Yes, these were simple requests for information. If the contractor had an agreement with the previous superintendent that the information was not required, then surely he would have advised me of that upon receipt of my requests for information." 104 Mr Corven had not taken the trouble to acquaint himself fully with the project and the arrangements in hand between the contractor and the previous superintendent. It seems to me somewhat unreasonable that at the end of the contract, after the opportunity for survey had passed, for him to then insist upon survey information rather than the logs of the material taken. In these circumstances I do not think that the superintendent was acting reasonably. 105 It follows that there was no breach of the condition in respect of progress claim no 7. The cross-claim 106 The cross-claim includes claims for damages for breach of contract and damages and orders pursuant to various sections of the Trade Practices Act 1974 (Cth) and the Fair Trading Act 1987 (NSW). I will deal first with the claim for damages for breach of contract. It is to be borne in mind that the council thus has cross-claimed and has the onus of proof in respect of the cross-claim. In this regard section 140 of the Evidence Act 1995 (NSW) should be noted. It repeats in some respects the common law and is in these terms: "140 Civil proceedings: standard of proof (1) In a civil proceeding, the court must find the case of a party proved if it is satisfied that the case has been proved on the balance of probabilities.
(2) Without limiting the matters that the court may take into account in deciding whether it is so satisfied, it is to take into account: (a) the nature of the cause of action or defence, and (b) the nature of the subject-matter of the proceeding, and (c) the gravity of the matters alleged." 107 The reason for mentioning this section is that much emphasis has been placed in the Council's submissions upon the gravity of the consequences if the levies should fail. I have earlier referred to the general conclusions expressed by Professor Fell and Dr Truscott and their accounts in terms of danger to the population of the town of Brewarrina. Reference was made to the 1991 audit which referred to the substantial costs which would result from flooding which would cause extensive damage to the town and include injuries, loss of life and trauma. 108 In this respect, the project with which this case is now concerned is like many civil engineering projects in the State insofar as it is one that is undertaken for the public good and the public safety. As to precisely how I should take into account the issue in respect of public safety was not addressed in submissions. To the extent that there are submissions that there has been a wilful disregard of the contractual requirements, no doubt any decision on that matter would need to take into account the seriousness of any such conduct in terms of public safety. It does not however mean that because public safety is involved there should be a lesser standard of satisfaction in respect of a decision on the cross-claim. 109 It should also be appreciated in respect of this case that although one expert expressed views about the inadequacy of the design of the levies the appropriateness or otherwise of the design is not a question that is raised in these proceedings. The proceedings only deal with the construction of the levees as specified in the contract. 110 It will be necessary to look at the evidence of the Council's principal experts on each of the main areas concerned in the cross-claim. I will first deal with the most critical area, namely, whether or not an appropriate standard of compaction was achieved in accordance with the contract specifications. In doing this I will first look at the nature of the evidence given by Professor Fell and Dr Truscott and then move to a detailed consideration of the basic facts upon which their conclusions are based. Compaction 111 The principle requirement for the compaction of earthworks is contained in clause 8.9 of the technical specification. For the purposes of this case the important clause is clause 8.9.2 which is in the following form: " 8.9.2 Levee Embankments This clause applies to Zone A Clayfill as well as Material Replacing unsuitable Material, and backfill to the Discharge Pipes and Stormwater Drainage Pipes. Materials shall be uniformly compacted in finished layers not exceeding 300mm in thickness by the use of a padfoot roller or similar which provides a kneading method of compaction. The use of power tampers in compacting thin layers shall be applied for al areas which cannot be compacted using a roller. Materials shall be placed and compacted to achieve a minimum Hilf Density Ratio of 95% (Standard) when tested in accordance with test method AS1289 - 5.7.1. The Hilf moisture variation shall be within - 3% dry to )% wet of the Optimum Moisture Content. Care shall be exercise during lapses of construction to prevent surface drying of these zones. Should this occur then approved corrective action shall be employed. This action shall consist of either scarifying the surface, rewetting and compacting to the above standard or removal of the upper dry material t the satisfaction of the Superintendent." 112 Section 3 of the specification dealt with stormwater drainage including culverts, reference to which is made throughout the evidence. Clause 3.7 of the specification provides for a similar percentage and maximum density and provides that the compaction shall be in layers not exceeding 150 mm of compacted thickness. Professor Robin Fell's evidence 113 Professor Fell considered the likely mechanism for failure of the levee and concluded that the most likely failure mode was by internal erosion and piping which was likely to be through the embankment around pipes and conduits and behind cutaway walls. He identified the factors most likely to affect a failure as being: "The degree of compaction of soil - if the soil is poorly compacted there will be permeable zones in which seepage and initiation of erosion can occur.
The erodibility of the soil as measured by laboratory tests, and as observed in the field, and how this is modified by compaction; and the adding of lime or gypsum which inhibits dispersion.
Whether the soil cracks to a depth such that when the flood waters reach the cracked soil, erosion can initiate." 114 Professor Fell then went on to consider the question of compaction and referred to the results of the density tests which had been carried out and to which I have earlier referred. He also referred to and relied upon some dynamic cone penetration tests which were done by Gutridge Haskins and Davies in 2003. These tests were referred to in the evidence as "DCP" tests. On the assumption that all such results were accurate, apart from the CETS tests he concluded as follows: "19 From this it is concluded that:
(a) Much of the fill in the Charlton Road Levee was compacted to the Specified 95% density ratio, but a significant amount was not well compacted.
(b) The fill in the Northern and Southern overlays was not well compacted. About 7% (the red zones) is virtually uncompacted, about 28% (the yellow zones) is poorly to inadequately compacted, and 65% probably satisfactorily compacted. If only the (more reliable) density in place testing is used, only about 15% passes the specification.
(c) The fill above the pipes and culverts is very poorly compacted. Virtually all falls into the "red" or "yellow" zones. It seems likely much of the fill was not compacted at all or if it was, it was in thick layers with inadequate rolling and moisture content control.
(d) The backfill behind the retaining walls on the North Brewarrina level is all in the "red" or yellow" zones, and it seems fill behind three of the four walls was not compacted at all.
(e) The remaining fill in the North Brewarrina Levee is a mixture of well compacted and inadequately compacted soil." 115 Having based his results on the tests, other than the CETS tests, he then had to explain those tests. The CETS testing, as I have earlier recounted, showed that in respect of compaction the finished material achieved the desired result. In paragraph 22, Professor Fell suggested that the CETS tests results could be ignored for the following reasons: "22 The question arises why the CETS Testing showed the fill was well compacted, where the later testing shows otherwise. Possible explanations are: (a) Most of the testing was on the Charlton Levee which Douglas testing showed mostly met specification. (b) The testing was done on selected, well compacted soil; for example, on the top of layers which were well compacted. (c) No testing was done on backfill around pipes, culverts and wall backfill.
The density of the material around the culverts and immediately adjacent to the levee retaining walls is so low that the levee is likely to wash out at at. least one of these locations during a flood considerably less than the design flood. This situation is aggravated by the high linear shrinkage results. This matter is considered critical to the security of Brewarrina and remedial works are required urgently.
Generally the density of the material in the overlays on the Southern and Northern Levees is also low and remains about the same as for the levees dumped in the 1970's. The only improvement is the random reduction in linear shrinkage. Hence, most of these levees are no better than the old, dumped levees.
The materials in the Charlton Road and Tarrion Creek Levees are also generally below the required density and have linear shrinkages above 12%. This, together with the low densities in the pavements, means the pavements cannot be relied on to prevent cracking and cracks are likely to extend below the 1 % flood level. These levees will therefore leak and probably fail during floods less than the design flood.
Density testing and the DCP results on North Brewarrina Levee indicate that this is not adequately compacted. Also the linear shrinkage results indicate a significant amount of the levee material has a linear shrinkage greater than 12%. Hence this levee cannot be relied upon to protect North Brewarrina in the event of a significant flood.
The above matters are critical to the safety of the levees and require urgent attention." Council's case on the aspect of compaction 119 The plaintiff presented three broad bases upon which it attacked the conclusions of Professor Fell and Dr Truscott. These were:
"The grouping of Golder's relative density results are self-explanatory, with the possible exception of the considered adequate group based on values between 90 and 94% which is a level of compaction that might be considered adequate in the circumstances but below the specified level of compaction. The reasoning behind this grouping is that: It is unrealistic to expect that the level of compaction of fill placed in early 2002 might not vary over a period of about 2 years. The fill consists of expansive clays that will be affected by climatic and other environmental factors. Soils are not inert materials, they can and do change with time and changes in environmental conditions and in many instances the prediction of actual field behaviour is uncertain within the present state-of-the-art. The 95% specification requirement is itself an arbitrary figure based on common practice rather than on any quantified geotechnical characteristic specifically relevant to the performance of the levees. The nature of compacted fill does not change dramatically below the 95% level: rather there is generally a regular change in geotechnical characteristics. Compacted fill at less than 95% continues to exhibit those factors required for satisfactory levee performance albeit to somewhat different extents. Similarly changes can also occur as a result of changes in moisture content at a given compaction level By way of example, the saturated permeability of clay tends to a minimum value around Standard optimum moisture. Substantially wet and dry of optimum permeability is essentially independent of compaction level, but varies by several orders of magnitude between wet and dry. Typically the effect of a lower level of compaction at say 3% dry, might be one order compared to two orders at optimum. If a permeability of below say 1 E-7m/s might be expected at 95% Standard and -3% then at 90% a higher permeability would be expected but might be say 1 E-6m/s. Impermeability would be compromised but not necessarily to a detrimental extent. On the other hand, unsaturated permeability is largely independent of compaction level and would not be materially compromised. A suite of permeability test on a range of fill materials compacted to different relative density and moisture variation levels would be required to define these issues: It is generally accepted that there will be variations below the specified limit in properly compacted and tested fills and that such variations are unlikely to significantly affect performance of the fill." 194 Before dealing further with this question which is relevant to the compliance with the contractual specification, I think it probably appropriate that I deal with some of the submissions made as to Dr Burman's credit. In terms of his experience it was suggested that Dr Burman had no experience with levees adjoining rivers designed to protect the town or area from floods. This may well be so but he had adequate experience in relation to dams and other relevant structures and in my view he is qualified. 195 It was suggested that from time to time Dr Burman was evasive, giving qualified answers to questions. I have considered the references to which reference was made where Dr Burman used words such as "in general" and they do not change the opinion of him that I formed by watching him give evidence. He was a careful witness and, if necessary, he would qualify an answer if indeed he believed a qualification was required. On only one occasion I found it necessary to remind him not to add a rider in answering a question when it was not called for. He took this on board and there was no further problem in that regard. In my view he gave evidence in a most appropriate manner. 196 In relation to the comments on his Table 8 which I have referred to above, he was taken to task for having referred to a period of about two years instead of one year. The actual time between April 2002 and August 2003 was, in fact, sixteen months and I do not consider it an exaggeration. 197 One of the criticisms Dr Burman made of Professor Fell's and Dr Truscott's findings was as follows: "The Barnson compaction tests produced some spectacularly low levels of compaction. There were a significant number of tests with values in the low to mid 70%s and one as low as 67.6%. In my almost 40 years of experience as a geotechnical engineer I have never encountered, directly or indirectly, values as low as those reported by Barnson. My immediate reaction to such low values is that there must have been something wrong with the testing that produced these results. Nor would I be alone in such a reaction as it is a commonly express view among experienced geotechnical engineers that compaction levels at or below the 80%s are physically implausible." 198 Dr Burman was tackled in cross examination upon a report of his which was not in evidence but which simply referred to the existence of some tests that achieved a result of 77% plus a minus 3.4%. Given the level of Barnson results which Dr Burman was referring to was one as low as 67.6%, reference to him having seen one which was put to him in cross examination is not really an appropriate direct comparison. It seems plain that he was talking about some very low results. I do not find this criticism a substantial one. Plainly what Dr Burman was doing was indicating that the actual figures of the Barnson tests were lower than figures that he ever seen earlier. The cross examination did not demonstrate that he had seen figures as low as were reported in the Barnson tests. There was some suggestion that he may have seen tests as low as 60% but Dr Burman indicated that that was a particular laboratory test and the re-examination clearly demonstrated that he was referring to some tests that Dr Truscott had done as a result of his experimentations in the subject case, but which for reasons which Dr Burman advanced in re-examination were quite irrelevant. The last sentence of the quote that I have included above is also criticised in the sense that it did not use the words "in general". Dr Burman uses the word "implausible" rather than impossible and in my view he is right. Cross examination on this aspect did not detract from the real view which Dr Burman was expressing in the paragraph by reference to the actual Barnson results which went as low as 67.6%. 199 Dr Burman was criticised for referring to the fact that the Troxler gauge was out of certification. He knew that it was within calibration as his cross examination plainly admitted. The point that Dr Burman was bringing to the Court's attention was the procedures involved because if after the report the calibration check showed it was out of calibration, it would make the results useless and confirm what was sloppy procedure. 200 Dr Burman was criticised for having omitted some tests in his report that he had arranged to have done by Coffey. Since the tests did not relate to compaction Dr Burman was right in his reasons for omitting them, namely, that they did not add to the store of knowledge on the matter in question and that to tender those tests would not have taken the matter any further. Reference was made to cross examination on certain pin hole dispersion tests and pocket penetrometer tests undertaken by Mr Russell of Coffey at the direction of Dr Burman. It was suggested that these confirmed similar results to that of Barnson. There was no identification of such similar tests by Barnson and the relevant tests on which the cross examination proceeded were not tendered. In these circumstances nothing can be made of this inconclusive cross examination. 201 Reference was made to the fact that Dr Burman had criticised the use of the CETS tests by Professor Fell and Dr Truscott and then used them himself. He was cross-examined about some DCP results which he relied upon in 1998 but once again these were not put before the Court. It was plain from Dr Burman's cross examination that his views had changed over time. It should be borne in mind that Dr Burman had good reason for not accepting the DCP tests as being less reliable because they did not correlate with the actual in situ density tests. Given the limited amount of information about the occasion in 1998 I do not find this criticism valid. 202 The submissions on Dr Burman's credit pointed out that he had contacted both Mr Pilgrim and Mr Russell. Precisely what criticism is levelled is hard to understand since any discussions with Mr Pilgrim were before Dr Burman made a statement to the Council. Furthermore, Mr Russell never became a witness for the Council as the Council withdrew his affidavit and did not seek to read it. 203 There was criticism of the fact that after Dr Burman was engaged in November 2003 he did not have further tests undertaken. It was not suggested to Dr Burman that it was his decision to carry out any further tests and accordingly this not a matter of moment. 204 There was a submission that in respect of the engagement of Mr Russell by Dr Burman to do some tests that he gave a false answer as to whether he asked Mr Russell to undertake the testing on his behalf after he had prepared his report dated 2 February. A careful reading of the evidence concerning Exhibit 24 and the various testing makes it plain that there were tests by Mr Russell of Coffey before and after his report. The proposition put forward by the Council is not supported by the evidence and, if the proposition had been put to Dr Burman he probably could have dealt with it quite easily. 205 A consideration of all the matters put forward by the Council in respect of Dr Burman's credit do not detract from the view which I formed of him that he was a careful and accurate witness with appropriate knowledge. 206 I return to the Table 8 referred to by Dr Burman which I have set out above. In cross examination the Council sought to deal with the matters which it commonly referred to as Dr Burman's de-compaction theory. A perusal of the material that I have quoted above does not indicate that he advocated such a theory but rather that he simply pointed to the fact that there can be changes to environmental conditions over time. He referred to this in the first bullet point in the table. 207 A careful reading of his comments does not purport to be an absolute explanation of the differences obtained in the Golder tests and those obtained by the CETS tests during construction. 208 When considering the Council's submissions on this aspect it is important to note Dr Burman was assuming that the compaction achieved was at least 95%. The Council's submissions referred to the CETS tests as showing substantial numbers of results over 100% but what that submission failed to take into account was that those results included many pavement tests which are required to exceed 100%. 209 It is to be noted that Dr Truscott referred to the possibility that an increase in moisture levels could account for the differences between the Barnson and Golder tests. This aspect of changes of moisture content was explored in the cross examination of Dr Burman and he agreed that at best a reasonable rule of thumb is that a 1% change in moisture would result in a 1% change in density and that in respect of the 5% change in moisture content the relationship was very approximate. It is apparent from Table 6 at page 18 of Dr Burman's first statement that the variation in moisture content between some tests could be as much as 3%. 210 All that can be said about this is that even if there has been some change in moisture content then there might be a similar percentage affect on the test results. That leaves other factors, the only one of which was not explored fully in relation to the Golder tests being whether there was any possible disturbance of the sample in the method of excavation.
211 In summary Dr Burman only postulated a partial explanation of the difference between the results and the specified requirements under the contract. 212 One of the problems about the tests is, of course, that they were spread over all the different levees. For instance, for the Tarrion Creek levee and Charlton Road there were two tests while at North Brewarrina there were three tests. In the Southern levee there were only two tests whereas in the Northern levee there were eight tests. Of the seventeen tests, six, being at least one in each levee, achieved the standard of compaction required under the contract and nine were between 90% and 95%. Two tests failed. In other words they were below 90%. This is a very small spread of results over each levee and there is no evidence that has dealt with the significance of those results in a statistical sense. Hence one has the substantial number of CETS tests during construction which achieved appropriate levels. In these circumstances I do not think that the Golder tests really assist in determining whether the levees in general were compacted as required under the contract. 213 It is also relevant in a general sense, although they are also subject to the same problem as the Golder tests, that the Douglas Partners tests all provided satisfactory results immediately after the conclusion of the works. 214 I am satisfied having regard to the CETS tests which I regard as accurate, and having regard to the undoubted evidence of compaction while the works progressed under the daily supervision of Mr Komp, that the levees themselves were compacted in accordance with the relevant specification. 215 I note of course the opinions of Professor Fell and Dr Truscott but their opinions are predicated on the acceptance of the Barnson testing which I have rejected. They also suffer from what was submitted by the plaintiff to be a problem in that their opinions do not seek to describe or elucidate the process by which the logical step between the test data and their ultimate conclusions in respect of the condition of the levees was made. 216 In respect of Professor Fell and Dr Truscott, when their reports and affidavits were tendered or read, objection was taken to the relevant conclusions on the basis that such conclusions offended the principles which were recently referred to by the Court of Appeal in Makita (Australia) Pty Ltd v Sprowles. At paragraph 85 Heydon JA set out the principles for the admissibility of expert opinion evidence. There he said: "In short, if evidence tendered as expert opinion evidence is to be admissible, it must be agreed or demonstrated that there is a field of 'specialised knowledge'; there must be an identified aspect of that field in which the witness demonstrates that by reason of specified training, study or experience, the witness has become an expert; the opinion proffered must be 'wholly or substantially based on the witness's expert knowledge'; so far as the opinion is based on facts 'observed' by the expert, they must be identified and admissibly proved by the expert, and so far as the opinion is based on 'assumed' or 'accepted' facts, they must be identified and proved in some other way; it must be established that the facts on which the opinion is based form a proper foundation for it; and the opinion of an expert requires demonstration or examination of the scientific or other intellectual basis of the conclusions reached: that is, the expert's evidence must explain how the field of 'specialised knowledge' in which the witness is expert by reason of 'training, study or experience', and on which the opinion is 'wholly or substantially based', applies to the facts assumed or observed so as to produce the opinion propounded. If all these matters are not made explicit, it is not possible to be sure whether the opinion is based wholly or substantially on the expert's specialised knowledge. If the court cannot be sure of that, the evidence is strictly speaking not admissible, and, so far as it is admissible, of diminished weight. And an attempt to make the basis of the opinion explicit may reveal that it is not based on specialised expert knowledge, but, to use Gleeson CJ's characterisation of the evidence in HG v R (1999) 197 CLR 414, on 'a combination of speculation, inference, personal and second-hand views as to the credibility of the complainant, and a process of reasoning which went well beyond the field of expertise' (at [41])". 217 There was debate as to the admissibility of the reports and at transcript 120 I ruled that at that stage the reports would be admitted but that the question of whether such evidence was properly admitted or, alternatively their weight, could be argued at a later stage. 218 As was made plain in the debate as to admissibility there are two principal problems with both reports in this area. The first of these is their statistical relevance of extrapolating a small number of tests over the large area of the levee banks. The second area is the logical step from the existence of non-compaction or compliance with requirements for linear shrinkage, to the proposition that the levee banks are likely to fail. I turn now to the first of these matters. 219 In their submissions the plaintiff made the following points: "In essence the plaintiff's objection to the conclusions expressed by Dr Truscott and Professor Fell in respect of which Makita objections have been taken is that the opinions do not seek to describe or elucidate the process by which the logical step between the test data and their ultimate conclusions in respect of the condition of the levees was made. Even accepting the Barnsons/GHD testing as reliable (which the plaintiff submits elsewhere it clearly is not) the data upon which the defendant's experts have sought to draw conclusions consists of the results of tests taken at a very small number of discrete points spread over five levees. Those tests can themselves be divided between tests taken at culverts, tests taken in pavements and tests taken in embankments (ignoring for the moment the contest over whether all these tests were in fact taken in fill required to be compacted in the course of the contract). These discrete points are a very small proportion of the total population of areas of fill. Even at the chainages where tests were taken the test results only relate to the specific point at which the test was taken, they do not necessarily reflect the condition of the entire embankment at that point. It is not permissible to draw the conclusion that any test or group of tests is representative of any area within the embankments without careful justification. The appropriate method of so doing (if possible) would have been by properly documented statistical analysis. Such statistical analysis would have required identification of those areas which were considered to constitute a statistically valid population and the reasons why they are so considered. For example, the areas surrounding culverts cannot be considered to be part of the same population as the embankments since they were clearly constructed and compacted by different methods. Equally, there are significant differences between levees constructed as overlays and those constructed from scratch. In the plaintiff's submission, a proper analysis of these issues would have required justification for treating even discrete parts of the same levees as part of the same population. Both Dr Truscott's and Professor Fell reports are signally devoid of any such analysis. The next step in seeking to generalise from a limited number of tests to a whole population must be the statistical analysis itself. It is simply not appropriate to draw the conclusion that a limited number of tests is representative of the whole population from which they were drawn without proper statistical analysis. No attempt at such analysis is contained in any of Dr Truscott's or Professor Fell reports. One factor that ought to loom large in any attempt to assess whether the test results indicate that the levees were not properly compacted at the time of construction is an assessment of the degree of accuracy of the tests themselves. Again there is no consideration of this issue by either Professor Fell or Dr Truscott. As canvassed elsewhere in these submissions the evidence shows that the degree of precision of Hilf compaction tests is no more than 4%. When allied with the 2% limit of accuracy of the Nuclear densometer gauges, it is apparent that relative density testing may be out by as much as 6%. As Dr Truscott noted in cross examination (T376-377) in considering whether some results below 95% could be considered as indicative of an improperly compacted levee bank it 'depends how below and it depends how many'. In other words, it requires a statistical analysis, and neither of the defendant's experts has sought to perform such an analysis." 220 If one looks at Professor Fell's reports, one sees his somewhat incomplete and an inaccurate reference to the testing in Table 1 and the dynamic cone penetration tests in Table 2. After referring to these tests in paragraph 17 he then gives his results in paragraph 19. These are repeated in a slightly different form in the answer provided at paragraph 46. It is plain that he gives no logical reason or explanation as to how he comes to the conclusions as to the level of compaction in the different levees from the particular results. When one looks at Dr Truscott's evidence and particularly his conclusions at section 12 of his report one does not see in the preceding material any explanation as to why test results are indicative of the whole of the levees. 221 There was no evidence from any of the experts that one should engage in some statistical analysis. However, this is really self-evident and it is worth noting that the parties specified a regime under their contract which led to there being upwards of 300 compaction tests during the course of the job. In contrast, the Golder tests numbered only 18 tests. Presumably the engineers who drew the specification requirements for testing gave consideration to what would be an appropriate level of testing to ensure the desired result. 222 In considering these objections it is probably useful to bear in mind the purpose for which the matter is being considered, namely, there is a decision to be made as to whether or not the plaintiff complied with the contract in respect of the compaction requirement. If it did not, the next question that arises is whether there has been a substantial performance of the contract. This question of substantial performance clearly must take account of, if one were to rely on Professor Fell's and Dr Truscott's evidence, the second question in respect of their reports to which I have referred above. Namely, whether there is a proper elucidation of their reasons for moving from the proposition that the levees contain weaknesses and the proposition that the levees are likely to fail. In this respect the plaintiff's submissions were as follows: "The second step in respect of which Professor Fell and Dr Truscott fail to provide proper elucidation of their reasons consistently with the requirements of Makita v Sprowles is in moving between the proposition that the levees contain weaknesses and the proposition that the levees are likely to fail. Although there is discussion of 'piping' and cracking, there are a number of intermediate steps which are left unexamined. It is first necessary to draw the conclusion that areas of weakness extend right through the levees (that is through a whole cross-section). If that conclusion cannot be drawn it is necessary to identify the extent of the areas of weakness and then identify the manner in which such limited areas of weakness are said to expose the levees to the risk of failure. A proper analysis of the foregoing issues would require some quantitative assessment of the impact of such deficiencies in the construction of the levees as could properly be established on the extent of piping and cracking (in particular by reference to that which could have been expected in the levees had such deficiencies not been present). Neither Dr Truscott nor Professor Fell sought to or was apparently able to carry out such quantitative analysis. In respect of linear shrinkage the best Dr Truscott could do was 'if it is lower it is better if it is higher it is worse' (T396.4) and 'it is not just as good whether it is significantly worse I don't know' (396.42). At the same time all the tests concerning the dispersivity of the fill used in the construction of the levee suggested it was not dispersive. It is dispersive soils that are more susceptible to piping. (T473.42) Finally the defendant's experts seek to dismiss the CETS results on the basis that they cannot be correct. Yet again there is no attempt to engage in any form of statistical analysis to assess whether the subsequent test results actually demonstrate that that is the case. If the subsequent test results were to be used to impugn the CETS results it was incumbent upon the defendant's experts to provide a coherent explanation for that conclusion. Again, in contravention of the requirements of Makita v Sprowles , no such explanation is provided. For the foregoing reasons the plaintiff submits that those parts of the various expert reports to which Makita objections were taken should not be admitted into evidence. However, even if this submission is not accepted, consistently with the penultimate sentence of paragraph 85 of Makita v Sprowles , the evidence should be accorded little weight."
223 It is plain that Professor Fell and Dr Truscott are substantially basing their ultimate conclusion that the levees would fail upon the fact that a failure at only one point is necessary in order to for there to be a total failure of the levees by flooding the township. In their submissions the defendant referred to Professor Fell's evidence in this regard in the following terms: "All experts agreed that failure at only one point would result in a total failure of the levee. The Defendant has identified many potential failure points. Prof Fell's evidence was clear: 'It must be realised that even one poor layer through the levee is sufficient for erosion an piping to initiate and may lead to failure of the levee. That is why specifications for dams and levees require full compliance' (Fell affidavit 9 March 2004, para 13). At paragraph 31 Prof Fell confirmed that in his view 'much of the soil in the embankments is not treated with lime and does not meet the requirements for linear shrinkage'. By 'much' he meant between 35% and 60%. He also gave the following evidence: 'The levees are much more likely to develop internal erosion and piping problems than if they had been compacted to specification. It must be recognised that it takes only one layer of poorly compacted soil to give a path for seepage and initiation of erosion. There are many such layers in the northern and Southern levees, and around pipes, culverts and walls, and most likely some layers in the Charlton, North Brewarrina and Tarrion Creek levees' (Fell affidavit 28 July 2003, para 48). He also indicated that 'since the poorly compacted soil is distributed throughout the fill, it is likely that the levees will have to be completely rebuilt' (at para 50)."
224 The plaintiff's criticism of this approach is that Professor Fell has without any explanation or analysis extrapolated from the tests at a particular point in the levees to the proposition that there are many such layers of poorly compacted soil in the northern and southern levees. These criticisms are probably appropriate. 225 One perhaps gets nearer to it when one looks at Dr Truscott's evidence because what was important for him was that if one does not get consistent results then that is an indication the material has not been placed in a consistent manner. His evidence in chief was that a levee could fail at any location where the fill is sufficiently loose or cracks extend too deep. Hence the entire levee must meet acceptable standards in order to avoid the risk of failure. In cross examination he gave the following evidence:
"Q: That would not be or that information does not necessarily give an indication of the conditions which may there be encountered across the site?
A: If you're talking about the investigation in the natural materials, correct. If you are talking about something that is man made and supposedly been put in a controlled manner, then you need to do a certain number of tests to demonstrate that what the material is like and then provided the thing has been built in an uniform manner, then you can project it across the rest of the site.
Q: Do you accept that the actual characteristics of the subsurface material may vary significantly even between adjacent test points and may be influenced by sample intervals?"
A: I don't think they're influenced by sample intervals. It can vary across the site. No question.
Q: You agree that the results may vary across the site significantly?
Q: One could not project upon the balance of probabilities that information disclosed at one test location would be on the standard that I put to you, an indication of the material to be found at an adjacent location?
A: If you're talking about an embankment that has been built by a contractor or whatever, then you should be able to do it - should be able, yes. You should be able to say if I have tested here and here, you have to have enough tests. If you have enough tests, and it depends upon the test results. If in doing the testing, you find that you are getting consistent results over the whole, whatever you've tested, then you can. If you can't get any consistent results, then it is an indication that the material has not been placed in a consistent manner".
(T324.47-325.1-14; see also T 391). 226 The Council submitted that enough independent tests were conducted (including by Golder) to determine that the levee banks were consistently shown to be uncompacted and deficient in lime to satisfy the contractual requirements. Dr Truscott was of the view that on the Golder tests alone he would still have said that the levees were not properly built. It seems that Dr Truscott is making an assumption that it flows from tests in isolated spots. He does not really explain how that particular test or result showing the lack of compaction at a particular spot is likely to lead to failure. 227 For all these reasons I would attach little weight to the opinions of Professor Fell and Dr Truscott. 228 One of the areas that the experts did refer to was the area around the culverts. They identified the culverts as a place which is particularly susceptible to erosion. I will now turn to consider the question of the compaction of the culverts. Compaction of the culverts 229 Professor Fell and Dr Truscott expressed opinions in their reports as to the compaction of the fill above the culverts. Professor Fell said: "The fill above the pipes and culverts is very poorly compacted … It seems likely much of the fill was not compacted at all or if it was, it was in thick layers with inadequate rolling and moisture content control (Ref 2, Cl19c) and … Failure is most likely around the very poorly compacted soil above the pipes and culvert (Ref 2, Cl77)." 230 Dr Truscott also dealt with the matter in these terms: "There has been minimal if any compaction of the zone A clay fill at the culverts and this fill has not been compacted in accordance with the requirements of the technical specifications. The culverts are the most vulnerable areas during floods and levee failure will almost certainly occur with this level of compaction (Ref 3, Sect6.2). All test data shows that the culverts were not properly installed and present an unacceptable risk of failure by piping along the culverts in the event of flood (Ref 3, Sect7.1)." 231 It is plain that both experts were relying on the testing in April 2003 and as well as the Golder tests in August 2003. In respect of the April tests there were ten field density tests in eight test pits at four culvert locations. The tests showed what had been described as spectacularly low results giving an average of some 75.2%. For reasons which I have already advanced I do not consider that these tests are sufficient to base an opinion upon because of the deficiencies in the procedures. It is plain that Dr Burman like Professor Fell and Dr Truscott recognised that culverts and other embankment penetrations are well recognised points of potential weakness in water retaining structures. Dr Burman expressed the view that further investigation of these areas would have been prudent. 232 Unfortunately the Golder tests only included two field density tests at culverts. They indicated that at a depth of .15 that the field dry density was 95% and a depth of 1.2 was 90.5%. The Barnson parallel test from a depth of 1.2 indicated a result of 88.0%. The tests carried out in April 2003 at this particular location by Barnson gave relative density results of 77% and 70% respectively which is a substantial variation from the Golder results. This certainly indicates the likely errors in the Barnson tests. 233 Having regard to the fact that there were only two tests at culverts on which one can rely, clearly both Professor Fell's and Dr Truscott's wide ranging conclusions cannot be drawn. On an interesting note, the linear shrinkage tests at culverts all complied with the contractual requirement of 12% with one only being above the limit in the Charlton Road levee at 16%. 234 Professor Fell and Dr Truscott made reference to the dynamic cone penetration results. However these alone were not sufficient I would not have thought having regard to the matters I have earlier dealt with in relation to them as a foundation alone for the opinions expressed. 235 There is again the actual evidence as to whether compaction took place at the culverts during the course of construction. The evidence disclosed the following as summarised in the plaintiff's submissions in paragraph 8.
"Komp, the Superintendent under the contract during construction, witnessed compaction occurring at culvert locations [T768.41 to T769.4, T771.1 to .31]. He was not challenged on this evidence under cross examination;
The daily records of Beckhaus Civil support that compaction occurred at culverts [paragraph 29 of Exhibit C, Exhibit D at pages 11, 13, 18, 20, 23, 27, 35, 41 as examples only - the list is not exhaustive];
Macartney's evidence is that compaction was carried out at culverts [paragraph 29 of Exhibit C];
Whilst Macartney under cross examination admitted that the specified number of compaction tests was not taken at culvert locations [T86-87], his evidence that compaction was actually performed at culverts was not seriously challenged [T89-90, T94.20-53].
Tests results taken by CETS at culvert locations confirm that compaction was satisfactory: refer to attached table." 236 The fact that sufficient tests were not taken at the culverts as appears from Mr Macartney's evidence precludes me from coming to a conclusion that there has been compliance with the specification requirements for the frequency of testing in respect of the culverts. However, the evidence before me clearly demonstrates that there has been substantial compliance with the contractual requirements for compaction over the culverts. Linear shrinkage testing 237 The provisions of the contract which governs this matter are first, clause 8.7 of the specifications which deals with embankment materials and construction. The relevant part of that clause is as follows: "The levee embankments shall consist of Zone A Clayfill material as indicated on the Drawings. The Zone A Clayfill shall be selectively won from borrow or excavated from the existing Northern or Southern Levees and stabilised with gypsum in accordance with Clause 8.10. 8.7.1. Levee Embankment & Key Trench The levee embankment and Key Trench shall be constructed of Zone A Clayfill material, being clay material selectively won from the borrow area of existing Northern or Southern Levees and having a maximum linear shrinkage value of 12%. The frequency of testing for compliance with the linear shrinkage requirements will be such that a minimum of one (1) sample is taken for each 3,000m3 of Zone A material. Each sample shall be tested to determine the Atterberg Limits in accordance with AS 1289 3.1.1, 3.2.1 and 3.3.1. Zone A material shall be placed and compacted in accordance with Clause 8.9 of this Specification." 238 The stabilisation with Gypsum is referred to in clause 8.10 which is in the following form: " 8.10 Gypsum Stabilisation Gypsum shall be added to Zone A Clayfill at a minimum rate of 5% (by dry weight). Should this rate be insufficient to meet the required 12% linear shrinkage criteria, additional gypsum shall be added in 1% increments until the Contractor can verify that the criteria is satisfied. The cost of additional rates of Gypsum Stabilisation will be borne by the Superintendent and shall be calculated as per the rate given in the Schedule of Prices. Gypsum shall have a calcium sulphate content of at least 65% by mass of the supplied material. Gypsum shall not be added to the clay materials on the embankment fill. Gypsum shall be evenly spread over the area to be stabilised and mixed thoroughly to produce a uniform material. Gypsum may be substituted with 3% Hydrated Lime by dry weight subject to the Superintendent's approval." 239 Although these documents are part of the technical specification they are amended by contractual correspondence referred to at page 70 of Exhibit "J" under which "3% meadow lime (exDML Attunga) in lieu of 5% Gypsum" became part of the contract. This is clearly an amendment to clause 8.10. 240 There was a difference between the parties as to the construction of the clauses. The plaintiff suggested that the minimum amount of 3% did not have to be added if the material already met the 12% linear shrinkage criteria. The Council submitted that the amount of 3% was a minimum that had to be added and that more should be added if it did not result in a meeting of the 12% linear shrinkage criteria. It would seem on an ordinary reading of two clauses together there are two conditions, namely, the addition of the relevant amount of Gypsum plus more if necessary to make sure the maximum linear shrinkage value is 12%. 241 It is perfectly obvious from the evidence given in the case that the purpose of having achieved a particular linear shrinkage was to reduce the likelihood of deep and wide cracking in the embankment which might allow initiation of internal erosion and piping failure under flood conditions. In addition the adding of lime or Gypsum does inhibit dispersion if the soil is dispersive and makes it less likely to begin to erode or if erosion begins to slow the rate of erosion. It follows that the addition of lime reduces the shrinkage potential of the soil and thus reduces the depth of potential cracks. 242 The addition of 3% of meadow lime to all the materials may be a condition of the contract but a breach does not seem to have any consequence. This follows because the parties clearly contemplated that what is to be achieved is the placing of materials which had a maximum linear shrinkage of 12%. The whole testing regime in the contract is there merely to measure this requirement and there is no need for a demonstration of adding the particular 3% meadow lime. 243 There was cross examination of Mr Beckhaus as to the amount of lime that was actually used on the project. It is apparent that approximately 970,000 cubic metres of earth was worked under the contract which equates to approximately 165,132 tons of soil. The addition of 3% lime required about 4,953 tons of lime which at $70.00 per ton would involve a cost of $346,710.00. Delivery dockets for the project indicated deliveries of 328.86 tons of lime which is a value of about $25,000.00. The daily reports showed somewhat less being received on site. As I have indicated earlier these are somewhat unreliable. 244 All this probably indicates is that the plaintiff was adding sufficient lime to ensure that it met the contractual requirement that the material should meet the 12% maximum linear shrinkage specification. It clearly did not comply with the contract requirement to add at least 3% by weight to the material. This no doubt is the result of a misunderstanding of the contract. 245 As required by the contract there was of course testing by CETS throughout the course of the contract in respect of linear shrinkage. There were also linear shrinkage tests done by the various bodies that carried out compaction tests to which I have already referred. In addition to this there were some tests conducted on 24 October 2001 by K&H Construction Services Pty Ltd. These tests were conducted only for linear shrinkage at the request of Mr Komp, the superintendent. The actual test results which were taken at six places showed results ranging from 14% to 18%. These results were conveyed to the plaintiff and as a result the areas were reworked with additional lime being added. It is clear from Mr Komp's evidence that this rework was in respect of the area which had been tested and found wanting. Mr Komp did not have any further check tests done and, accordingly, throughout the rest of the construction, the testing by CETS showed that the results achieved the required level of 12%. 246 I turn to deal with the testing post completion for linear shrinkage. 247 It will be recalled that the Douglas Testing proved substantially satisfactory in respect of compaction. At the same time as they tested in April 2002 immediately after completion they did ten linear shrinkage tests the details in respect of the results are as follows:
(a) Two tests were taken in the Charlton Road levee one showing 8% and one giving a result of 14.5%. (b) One test only was taken in the Tarrion Creek levee giving a result of 18.5%. (c) One test only was taken in the Southern levee giving a result of 18.5%. (d) Four tests were taken in the Northern levee three of which were less than 12% and one of which was 15.5%. The test result of 15.5% was taken at a depth of .35 metres in the section of the levee where the top .5 metre of the levee was not removed by Beckhaus Civil at the direction of Mr Komp. Therefore such test was most likely taken within the existing old levee material and can be disregarded. (e) Two tests were taken in the North Brewarrina levee giving a result of 12% and 15.5%. 248 With regard to the Barnson tests in April 2002 the actual excavation of the test material was carried out by a person who was not a NATA registered tester. Given the simple nature of the excavations this is probably not a problem. The relevant results of the tests appear to be as follows:
(a) At Charlton Road two tests in the vicinity of a culvert showed results of 16% and 13%. (b) In the Northern levee fourteen tests were taken, eleven of which were equal to or less than 12% and two results were marginally above at 12.5% and one result at 17%. (c) Eight tests were taken in the Southern levee, two of which were 12% and the remaining six tests being either 15% or 16%. (e) Eight tests were taken in the North Brewarrina levee, two of which were less than 12% and the remaining six varying between 12.5 and 14%. (f) No linear shrinkage tests were taken at the Tarrion Creek levee. 249 In respect of the Golder linear shrinkage testing done in August 2003 the results appear to be as follows:
(a) There were six tests in the Northern levee, one of which was 14.5% and the reminder were either 12% or less. (b) In North Brewarrina levee there was one test at 12.5%. (c) In the Southern levee there were two tests showing results of 16% and 18%. (d) At Charlton Road there was one test showing a result of 16%. (e) At Tarrion Creek there was one test showing a result of 17%. 250 It is perfectly plain that the results indicate a variety of failures and a variety of occasions when the specifications were met. The only suggestion from Mr Moojen as to why this might have happened is that there might have been clay lumps in the particular samples but there was nothing to really substantiate this. The real problem with all this material is the question of whether or not one can extrapolate any result across the whole levee in respect of these results. To start with, on some occasions there was only one test in the whole levee. This raises the key question to which I have referred above as to the basis for assuming that because some results showed failures, all the material in the levees was below the requisite compaction. 251 It is notable that there was no substantial criticism of any of the testing in respect of this material or any suggestion of a variation over time. Given the existence of these failures it is hard to conclude there has not been some breach of the specifications. Once again it is whether or not such a breach would have any effect that is important. In this respect given my conclusion that there has been substantial compliance with the compaction requirements it is necessary to look at the evidence as to what these results, even if they are representative, do to the use of the levees. 252 There are a number of matters that arise in relation to the addition of lime. One matter that should be mentioned is that the addition of lime has the potential to change highly dispersive soil to non-dispersive soil. This is of course a desired outcome because non-dispersive soil resists piping and erosion to a far greater degree. The only tests to determine whether or not soil has been placed in the levee banks was non-dispersive were those carried out by Douglas Partners immediately after the conclusion of the project. There were ten tests taken over all the levees and all the test results showed that the soil was non-dispersive. There were also some tests taken on borrow pit samples but it is plain that there were no laboratory tests taken on fill materials or borrowed pit samples where the borrowed pit was actually used as a source of fill material which indicated dispersive soil. 253 This leaves the major question as to the effect or otherwise of not achieving the 12% linear shrinkage called for under the specification. Professor Fell is clear that the lime was required to be added and mixed with the soil to reduce the shrinkage of the soil so that the depth of the cracking was kept to acceptable levels consistent with the freeboard that was specified in the design of the dam. He could not say why a level of 12% was selected in the specification but he assumed it was based on experience with similar soil. Indeed, Professor Fell agreed that it is not usual practice to specify a linear shrinkage as criteria for the construction of dams. Professor Fell's conclusions that appear at paragraph 63 of his report were that between 50% and 90% of the soil in the embankments do not meet the specification and that that is spread throughout the levee banks. He said that it is likely that there are untreated layers in areas that persist from the upstream to downstream of the levee banks. No basis was given for this conclusion nor is there any basis for the earlier conclusion as to how much does not meet the specification. The consequences he says are that the banks are more likely to develop internal erosion and piping problems than if they had been treated as required by the specification. His opinion at paragraph 74 as to any cumulative effect seems to rely on the fact that the soils were potentially dispersive but this is not shown on the evidence. 254 Additionally, Dr Truscott was of the view that the lime was to be added to reduce linear shrinkage to at least 12% to reduce expansive shrinkage behaviour of the soil to reduce cracking potential. He went on to express some opinions as to the effect of the failure to add lime which are predicated upon the layer thickness required for 300 mm not having been complied with. It is plain on the evidence before me that it was complied with and accordingly little can be taken from these conclusions. 255 The plaintiff raises the same objections based upon Makita in respect of the conclusions which have been reached in that there has been no demonstration of any statistical basis for the general conclusions expressed. On this aspect it is interesting that Dr Truscott when shown the test results from Barnson in respect of the Northern levee on which there was substantial compliance, stated that he had no problem with the Northern levee in terms of linear shrinkage. When he was shown two tests in respect of Charlton Road he also agreed that just two tests would not allow one to deduce anything in relation to that levee bank about the state of the levee so far as concerned linear shrinkage. The two tests he was shown were ones showing results of 16% and 13%. 256 Having regard to his views on the Northern levee it would seem that there has been compliance with the contract. In respect of the other levees such results as they are show a different picture indicative of 12% not having been achieved for the majority of cases. However, whether such results given their small number are sufficient to lead one to conclude that the whole of the levees do not meet the specification depends upon whether one can extrapolate such a result from a small number of tests. There is nothing in the plaintiff's expert's material that deals with this and it would seem that this is a flaw in their evidence which would lead me to give it little weight. 257 Dr Burman adopted the mean of the results in order to come to some conclusions. The basis of this is somewhat doubtful as that is not what is required under the contract. His conclusion was: "There is probably a significant non-compliance in respect of the southern levee, substantial compliance to the Northern levee and North Brewarrina levees probable compliance for Charlton Road levee but the level of compliance for Tarrion Creek levee is unproven." 258 In relation to what might be described as a quantative effect of any non-compliance, Dr Burman noted the following in respect of the matter: "In my view the 12% linear shrinkage requirement was an arbitrarily selected limit that is not directly related to a relevant geotechnical performance perameter (spelling). No factual evidence has been produced to indicate that the 12% value is critical to or a determinative of levee performance, neither has either Professor Fell or Dr Truscott stated that a degree of non-compliance with a 12% requirement would prejudice stability of the levees. They have not claimed that the 12% linear shrinkage limit corresponds to the onset of cracking, or a structurally significant cracking in the levee banks." 259 His comments on Professor Fell's and Dr Truscott's evidence are correct. They may well have testified as to the purpose of adding the lime which I have referred to above but as pointed out by Dr Burman they have not taken the matter further. 260 Both experts were asked some questions about the quantification of any departure from the specification. Professor Fell gave this evidence: "Q. Am I correct in understanding that linear shrinkage is not usually used when constructing dams? A. That's correct. Could I qualify that. It is quite common to, if you specifying the earth fill material for the core of the dam to indicate a rank of what are the 'outer limits'. There is the liquid limit, plastic limit and linear shrinkage is usually quoted there. This is usually simply to define the soil that has been used will be material that is broadly consistent with what the designer understood.
Q. It is very unusual for the linear shrinkage specification to have made with respect to this levee bank? A. It is the first time that I have seen linear shrinkage specifically specified.
Q. If you had a linear shrinkage result of 15 or 16 as opposed to the specified 12, it would be impossible to say whether that had any practical effect on the levee? A. I would not be able to quantify the difference.
Q. You couldn't say with any degree of accuracy whether a higher linear shrinkage significantly changes the risk? A. As I said, in a qualitative sense, the soils with a higher linear shrinkage you would expect to shrink more than the soils with a lower linear shrinkage, but to absolutely quantify that, no, I can't." 261 This was returned to in re-examination and he gave this further evidence: "CHRISTIE:
Q. I might go backwards so to speak in terms of the questions asked by Mr Rudge. There are a few questions I would like to ask you. You were asked some questions about linear shrinkage and you were asked to draw a comparison between linear shrinkage of, let's say, 15 and 16 percent as opposed to 12 percent? A. Correct.
Q. I think you told his Honour that there was a difference but it was not possible to quantify that difference. What did you mean by "quantify" in this context? A. Well, what I meant was that it would be not possible to say that soil with a linear - sorry I don't know how to differentiate between the soil with a linear shrinkage of 16 percent and 12 percent in respect to whether or not the soil will erode; or in fact I have no relationships between that and the likelihood that a levee or a dam would fail. By comparison I do have and it is in one of those documents that was tabled at the beginning of my evidence, quite good data to relate the likelihood of a failure by piping for degree of compaction and whether a soil is dispersive or not. In a sense, it was in - by comparison. I don't know how to quantify it." 262 Dr Truscott commented in respect of the Southern levee probably the one which shows the worst results leaving aside the CETS tests as follows:
"Q. If we look at the southern levee, there are 8 tests, two of which are 12 percent and the rest of which are between 15 and 16 percent; do you see that? A. Correct.
Q. Would the answer that you give me in relation to the Charlton road concerning the difference between 12 percent and some higher figure whether it is quantifiable and whether it has any effect, you just can't say? A. I can say in a non mathematical sense that obviously it is not as good as if it was 12 percent but whether that means the risk is significantly changed, it is -.
Q. You can't say? A. You can't say, no. I mean I'm not going to try and pretend, no. I can say it is not just as good. Whether it is significantly worse, I don't know.
Q. Then we look at the north Brewarrina levee. Is the result there you see is the answer you gave to a similar question that I just asked in relation to the southern levee the same for the north Brewarrina levee. These results are some what closer to 12 percent? A. Yes, I think they probably depend on the borrow area but I - the answer's the same, yes. I mean it is not as good as it should be but whether it is significantly worse, I don't know.
Q. You just cannot say sitting there that it is or it is not significantly worse from the point of view of the integrity of this dam? A. All I can say, I don't know - I think you used the word "fit for purpose", I don't know.
Q. You can't say that it isn't? A. Not really, no, as regards to linear shrinkage that is.
Q. As regards linear shrinkage? A. Yes." 263 Plainly when Dr Truscott considers linear shrinkage alone he is not prepared to give any evidence that the levee banks are not fit for the purpose having regard to what differences were thrown up by the later tests. 264 Professor Fell and Dr Truscott apparently totally disregarded the CETS testing in their conclusions. 265 Bearing in mind my conclusion that there has not been demonstrated a sufficient departure from the compaction requirement it seems to me that there has been substantial compliance with the contract in respect of linear shrinkage. This flows from the fact that such testing as there is, seems to indicate a compliance in the Northern levee which is agreed to be sufficient. In respect of the other levees the evidence is of little weight because there is no basis expressed for the conclusions reached. In particular I am satisfied that in respect of linear shrinkage the levees are fit for their intended purpose. Road Pavements 266 The Council puts forward four different areas to suggest that the plaintiff did not complete this work appropriately. They were:
(a) Pavement compaction not in accordance with the contract requirements. (b) Pavement thickness not in accordance with the contract requirements. (c) Lack of freeboard on the levees. (d) Alleged recent cracking and pavement failures supposedly in support of the above allegations which were observed by Dr Truscott and Mr Whiteside. Pavement Compaction 267 Clauses 9.4 and 9.5 of the specification required a relevant density ratio of not less than a value of 100%. Testing was to be carried out randomly on each lot. In respect of Charlton Road and Tarrion Creek there are sealed surfaces over the compacted pavement. Tests were carried out by Barnson at the base course and sub-grade for both of these roads. The test results for the base course range between 90% and 98% compared with the specification requirement of 100%. Density tests carried out by Douglas Partners on behalf of the Council in April 2002 reported results of 95% to 100%. During construction CETS tests for Charlton Road showed results over seventeen tests between 99.9% and 102.8% and for Tarrion Creek between 100.7% and 103.1% over five tests. A comparison with nearby tests between the test sites between Barnson and CETS indicates a substantial difference in results. In respect of the testing of the pavement it is likely that there would be less problems with that testing because there would be less likely to be any disturbance of the sample because of the standard compaction testing in the laboratory, the variance between field moisture content and because optimum moisture content is not significant. In these circumstances, and bearing in mind my earlier comments on Barnson testing, I prefer the CETS tests. Another reason for accepting them is that Dr Truscott said that the density in areas close to the surface was likely to vary over time. 268 Mr John Harrison, a civil engineer experienced in roads, gave evidence on the subject. He gave evidence that if the road had been compacted at 95% rather than 100% it should prematurely fail but his observations of the road did not indicate any premature failure. 269 In these circumstances I am satisfied that the pavement met the required technical compaction requirements. 270 In respect of the Northern, Southern and North Brewarrina levees Dr Truscott says that the compaction requirements of the pavement on these (which of course are not sealed by bitumen coating) have not been met. There were two tests in the Northern levee, one in North Brewarrina and two in the Southern levee. Given the small number of tests and the lack of explanation of what this ultimately means I find that there is substantial performance of the contract in this regard. Pavement depth 271 The pavement gravel under clause 9.3 of the specification was to be sourced from Redhill Quarry. The quality was to be as directed by the Superintendent or his representative. During the execution of the work the superintendent approved the re-use of existing pavement gravel as pavement gravel for the new roads in lieu of and in addition to the specified Redhill Quarry gravel. 272 It seems clear that the measurement of pavement thickness by Dr Truscott did not take into account the thickness of the gravel which was re-used by the contractor from existing pavements. I am satisfied that the normal required depth of pavement thickness of 300 mm was achieved. In respect of North Brewarrina Mr Komp approved a lesser thickness of gravel. This occurred in respect of an access road at North Brewarrina where the superintendent authorised a thickness of 100 mm. Apparently the reason for permitting it was because of an existing Telecom access line across the area. Given the directions of the superintendent there are no breaches in this regard. Lack of freeboard on the levees 273 Dr Truscott identified some areas of the crest of the Charlton Road and the Southern levees that are considerably lower than specified. Dr Truscott gave evidence that the survey showed that in respect of the Charlton Road and Southern levees the crests were considerably lower than was specified. He indicated that the other levees were satisfactory. When one looks at the plans one finds that in respect of Charlton Road there is a maximum flood level of 117.3 metres with a minimum crest level of 117.8 metres. It is clear that the centre line measurements of the road even on curves were above that minimum contract requirement. The actual apparent loss of freeboard that was identified by Dr Truscott in his Table 3 attached to his statement appears to be as a result of the super elevation on the curved sections rather than a failure of the levee to attain minimum crest level as designed. There is one spot between chainage 55 and 60 where the 117.8 is not achieved. Discrepancies are .13 of a metre and .4 of a metre. That appears to be where it merges into the Southern levee. In respect of the Southern levee at chainage 5.54 and 9.843 there is a similar discrepancy and this is where the two levees meet. In the Southern levee there is a further break at chainage 257.577 but that is deliberate because it is where a road passes through the Southern levee that would normally be blocked in flood times. On the Northern levee there is a similar low spot that appears to be caused by a road passing through the levee which I assume would normally be blocked if a flood was anticipated. 274 Dr Burman concedes that on the Southern levee there may be some areas where top up is required and he is no doubt referring to the ones that I have just mentioned. Accordingly, it would seem that there may be some basis for some rectification work in this area but given the small extent it would seem to me that there is substantial compliance and the defendant should have some claim for an amount necessary to rectify the levee in this area of the Southern levee and also in respect of the Charlton Road levee where I have indicated above. Recent observations of cracking and pavement failure 275 There was an inspection of the site on 7 May 2004 after there had been rainfall of some 65mm at Brewarrina. Dr Truscott and Mr Whiteside observed longitudinal cracking in the seal along both the Tarrion Creek and Charlton Roads. Cracking was apparently 600 to 1500mm in from the edge of the seal. Dr Truscott also observed a pavement failure at the edge of the seal. His opinion was that the cracking was caused by settlement at the edge due to the poorly compacted fill or swelling of the poorly compacted fill as the rainwater penetrated the sides of the road. He blamed inadequate pavement thickness and inadequate compaction which he had earlier identified. 276 Photographic evidence produced by Dr Burman and Dr Truscott identified longitudinal cracking in the Tarrion Creek Road. 277 In respect of pavement failures it appears that apart from disturbances where test pits were dug in the course of the investigations for this case the only failure is in the gravel shoulder beside the bitumen fill. It will be recalled that the defendant specified and determined the nature of this gravel. It appears that such matters are minor and as Dr Burman says, it is really a maintenance issue for the defendant. In respect of longitudinal cracking photographs demonstrated the existence of these cracks which were not wide. Evidence was given by Dr Truscott that this was a result of inadequate pavement thickness and inadequate compaction. On both of these I have found against Dr Truscott. Mr John Harrison, an engineer, specialising in roads, gave evidence that such cracking is typical of roads in Western New South Wales after rainfall and the repair of the road is simply a maintenance issue. He also indicated that to avoid such problems one needed to seal the shoulders. In this case, this was not required under the contract between the parties. 278 There was also an issue raised following the inspection about scouring on the sides of the roads. It seems that this also is a maintenance issue as nothing has been done, for instance, to grass the sides to prevent scouring which would normally occur. 279 It seems to me that in respect of these recent observations, the evidence sought to be adduced does not assist the Council. Key trenches 280 Dr Truscott carried excavations at ten locations to check cut off trench details. The data is summarised in Table 8 and of the ten test pits only two pits on the Southern levee exposed key trenches. Dr Burman examined these details in relation to the plan and in three cases the test pits appear to have been sighted where the levee had been over-built rather than in the design location of the key trench. Therefore the absence of a key trench at that point is irrelevant. 281 There is a substantial amount of other evidence that does indicate that key trenches were installed at Tarrion Creek, Charlton Road and the Southern and Northern levees. These included daily reports, a video of the excavation at Tarrion Creek and express evidence of Mr McCartney that they were constructed. Mr Komp also gave evidence that he observed key trenches being constructed at Tarrion Creek levee. When he was called he gave evidence that that paragraph also applied to other levees. He was not cross-examined on this matter. There are also in evidence hold point release forms signed by Mr Komp on behalf of the Council which confirmed the presence of key trenches. Given that he signed these it seems clear that there was an inspection. 282 In the circumstances I am satisfied that key trenches were installed as required under the contract. Doyle Street levee 283 It seems clear that there is no real question about the structural adequacy of the wall. There are some cracks which are shrinkage cracks in the wall and the witnesses seem to accept that these could be easily repaired by coating with a sealant on the road side of the levee. 284 Earlier in these reasons I dealt with the appropriateness of the concrete testing and the test results. It is plain that the concrete tests undertaken in the footing in the earlier part of the wall showed two failures where the concrete did not achieve the strength of 25 mpa. These failures were made known to Mr Komp, the Superintendent, and he accepted them and directed the plaintiff to leave the footings as he was of the view that there was a sufficient safety factor in the design for it not to be a problem. This is clearly an acceptance of defective work under s 30.5 of the General Conditions and there has been no demonstration of any loss or suffering as a result. 285 The Schmidt hammer tests were carried out once the defendant raised a problem in relation to the concrete testing and they were satisfactory. On 24 April 2002 the designer of the wall, Mr Saran, carried out a detailed inspection, reviewed the testing and concluded that the levee wall conformed to the design requirements and therefore was considered structurally acceptable. 286 The only matter of concern that seems to have been raised by Dr Truscott was the cracking and Mr Saran gave evidence that was likely to have been caused by concrete shrinkage and was not a structural defect. He thought the water ingress would be minimal but Dr Truscott thought that there was a path which should be prevented. In my view the concrete wall is substantially fit for its purpose but the defendant should be allowed some allowance for surface treatment of the cracks to the wall. Plaintiff's claim in restitution for total failure of consideration 287 Having regard to my findings that there has been substantial performance of the contract this claim will not lie. In any event given the fact that the contract provides for:
(a) Progress payment (b) Adjustment on default (clause 46.6) (c) Damages (clause 44.1, 44.2 and 44.10) (d) A schedule of quantities allocation of separate sums for separate parts of the work. (e) An express division into two severable portions
the contract is not an entire contract. Trade Practices Act 1974 (Cth) and Fair Trading Act 1987 (NSW) claims 288 The further amended cross-claim alleges liability on the part of Beckhaus Civil under s52 of the Trade Practices Act 1974 (Cth) and s42 of the Fair Trading Act 1987 (NSW). In the case of Dennis Beckhaus the cross-claim also alleges accessorial liability in respect of the alleged breaches by the plaintiff. The claims relate to three alleged representations set out in paragraphs 14 and 16 of the further amended cross-claim. They were
(i) Beckhaus Civil had assets worth $2 million; (ii) Beckhaus Civil had an annual turnover of between $3 million and $6 million; and (iii) Beckhaus Civil operated a third party accredited quality system. 289 The first two representations are alleged to have been made orally by Dennis Beckhaus at the post tender meeting on 8 August 2001 and to have been repeated in writing by the minutes of the post tender meeting. 290 The third representation is alleged to have been made in writing both in the tender submission (page 70 of Exhibit J, the relevant wording is "Beckhaus Civil operates a third party accredited quality system for all projects") and in the "Resume" of Completed Contracts attached to a fax of 2 August 2001 (page 31 of Exhibit J, the relevant wording is "a third party accredited quality system has been in operation since 1990."). 291 The response of the Cross-Defendants to these allegations is that:
(a) The representations were not made in the terms alleged; (b) No representation that may be established to have been made was misleading or deceptive; (c) The evidence does not establish any reliance on any representations that may be proved to have been made; (d) Mr Beckhaus has not been shown to have been knowingly involved in any misleading or deceptive conduct; (e) No damage has been shown to have been sustained by the Council by reason of any representations that may be found to have been made. 292 I turn now to consider each of the representations. Representation as to financial position of Beckhaus Civil 293 Mr Witherdin was a civil engineer who worked for a company formerly known as PPK Environment & Infrastructure. That company was retained by the Council to coordinate and evaluate tenders for the construction of the Brewarrina levees. Mr Witherdin also recommended a preferred tenderer based on the tender assessment criteria, which had been established for the purpose. 294 Prior to preparing his evaluation report that was eventually submitted to the Council, Mr Witherdin attended a tender interview on 8 August 2001 at Singleton. Mr Dennis Beckhaus was present. In his affidavit Mr Witherdin gave evidence that Mr Beckhaus said: "Beckhaus Civil has an annual turnover of between $3 million and $6 million. It does not work off huge overdrafts. It pays accounts within 30 days. It has a current cash surplus of $200,000.00 in the bank and assets worth $2 million." 295 A record of the meeting formed part of the contract. The minutes record Mr Dennis Beckhaus of Beckhaus Civil being present and under the heading "Financial Status" there is a listing of the five statements, which Mr Witherdin alleges were made in his affidavit. 296 Mr Beckhaus' evidence of the relevant conversation was that in response to a question, "Would you please advise your current financial position" he responded in these terms: "Our turnover is generally in the area of $3 million but it has been as high as $6 million. We don't work off huge overdrafts. We pay our accounts within 30 days. We have a current cash surplus of about $200,000.00 in the bank. We have assets worth about $2 million." 297 One will notice the clear difference between referring to Beckhaus Civil and Mr Beckhaus' use of the word "our" or "we". This arises because there are at least three companies involved in his operation. There is Beckhaus Civil Pty Ltd, the plaintiff in the action, Beckhaus Civil Engineering Pty Ltd and Beckhaus Pastoral Pty Ltd. The first two companies are described by Mr Beckhaus as operational companies for the performance of various contracts and the third is the company which owns the plant and equipment which is hired out to the first two companies. Although I will refer to this in more detail later in general terms it is plain that if Mr Beckhaus was referring to the group of companies then his statements would have been substantially accurate. If they simply referred to the plaintiff, Beckhaus Civil, they were completely inaccurate and misleading. For example, the plaintiff's total assets for the year ended 30 June 2001 was $713,345.00 and its net assets were $349,677.00. It hardly need be mentioned that it was only Beckhaus Civil that entered into the contract, not the other two companies. 298 It is also plain that the statement made by Mr Beckhaus as to cash surplus of $200,000.00 and an annual turnover of between $3 million to $6 million was perfectly true in relation to the plaintiff, Beckhaus Civil. It is only the statement of assets worth $2 million that does not apply to the plaintiff, Beckhaus Civil. This difference was eventually taken up with Mr Beckhaus in cross examination at T 288 in these terms: "Q. When you indicated that the current cash surplus of $200,000 in the bank was in place, you said that because you knew from your own knowledge that there was about that much in the bank?
Q. And the balance sheet behind tab 13 would tend to support that, wouldn't it? A. It would, yes.
Q. Then going to the first bullet point, that was based on your understanding of the turnover of Beckhaus Civil for the preceding years? A. The 200,000 was based on--
Q. No, sir, I am asking you to look at the first bullet point. A. To which?
Q. The first bullet point, "Annual"? A. The first?
Q. The first bullet point under 7.5. A. Oh, sorry. "Annual Turnover", yes.
Q. Again, that was based on your knowledge of the turnover of Beckhaus Civil in the previous years? A. Yes.
Q. Then you see there is reference to assets worth $2 million? A. Yes.
Q. That was a false statement, wasn't it? A. False statement, no.
Q. Beckhaus Civil didn't have assets of $2 million? A. No.
Q. You disagree with me? A. Sorry? Yes, they didn't have, Beckhaus Civil didn't, no.
Q. And you were not asked questions at the meeting about other companies, were you? A. No.
Q. How can you tell his Honour that the statement as recorded in the minutes is not false? A. How can I tell him? The statement was made in relation to all the other companies. I mean in a pure sense, it was false.
Q. And do you tell his Honour that that is what you meant in your own mind when you made the statement? A. I certainly did.
Q. But you didn't say it, did you? A. I didn't say it? I very much doubt whether I was asked these questions.
Q. Could you answer the question please, Mr Beckhaus? A. I am beginning to doubt whether I was ever asked these questions.
Q. And I am asking you to answer the question please? A. Sorry, go back again. Where did we get to?
Q. You explained to his Honour, I think it is fair to summarise, that when you said assets worth $2 million, or words to that effect, you were referring not only to Beckhaus Civil? A. Correct.
Q. You didn't actually refer to those other companies in your discussions on that occasion, did you? A. No." 299 The version of the conversation put by Mr Beckhaus in his affidavit was put to Mr Witherdin. He stated that he did not recall that conversation and could not recall it either way. He conceded that he may have said it and that he did not recall it given the passage of time. He preferred to rely on the minutes as a basis for his recollection and it will be recalled from the minutes that in the substantive part they make no reference either to "Beckhaus Civil" or to "we" or "our". 300 In these circumstances I am prepared to accept that Mr Beckhaus' reported conversation in his affidavit is correct. 301 It is to be borne in mind that what Mr Beckhaus was attending on the day in question was a post tender meeting and that the tender had been submitted by the plaintiff, Beckhaus Civil. He was well aware of the relevance of the fact that the assets were held in another company because he structured his affairs that way so as to preserve the assets in case anything happened to the contracting companies. In the context of a meeting for this purpose, namely, considering the tender of the plaintiff, Mr Beckhaus' reference to "we" and "our" having regard to the circumstances and the particular facts to which he was referring, for example, the turnover and the money in the bank, were clearly directed by him to refer to Beckhaus Civil. It was no doubt understood by those to whom the statements were made in that sense. Plainly, as Mr Beckhaus concedes, the statement was false in relation to the assets. Mr Beckhaus did nothing to suggest to those at the meeting that it was other companies that had assets of this amount and that they would be available to the plaintiff. In the circumstances I am satisfied that the statement made by Mr Beckhaus was intended by him to refer to the plaintiff and that it was false. Representation as to a third party accredited quality system 302 I have set out above the relevant representations which were made. Clearly these or at least one of them implies that such a system was in place at the time of making the representations. Mr Beckhaus concedes in his affidavit that the previous third party accredited quality system which was in force in Queensland expired on 23 March 1997. In cross examination Mr Beckhaus conceded that the statement was inaccurate because it did not say, "currently accredited". 303 Given the fact that the assessment of the tenderers required amongst other things the various tenderers to be allocated a score out ten for quality control, such a statement would be likely to mislead or deceive Mr McNabb who dealt with quality control issues in relation to the tender. Causation and reliance upon the representations 304 Specific evidence was given by Mr Witherdin to whom I have referred about whether or not he would have made the recommendation which he did make to the Council as to the preferred tenderer if he had known the true situation. In respect of financial capacity he said: "I say that I would not have recommended the acceptance of the Beckhaus Civil tender, particularly in the light of the magnitude of the overstatement of assets. PPK would not recommend a contractor in such a financial position. The low value of the net assets of Beckhaus Civil, in conjunction with its very low tender price, would present a risk regarding the potential insolvency of Beckhaus Civil and a real risk to the completion of the project. In addition it would raise a concern about Beckhaus Civil making spurious variation claims." 305 In relation to the representation about an existing third party accredited quality system he gave evidence that it was important in the assessment process. 306 It is necessary to consider the extent of reliance by Mr Witherdin on the representations and then consider what flows from that in the terms of his report to Council and the Council's acceptance of the tender. 307 In respect of quality assurance situation it is plain that Mr McNabb sought and obtained some examples of quality systems that had been employed by the plaintiff on previous projects. In a letter of 2 August 2001 Mr McNabb asked for evidence of the nominated third party accredited quality system as well as typical plans used for other jobs. The response from Mr Beckhaus was to reply, indicating that he would drop off some plans from the current contract and a previous quality plan from their contract at Warren in 1998. He indicated that a job specific quality plan would be developed for the particular project. He made absolutely no mention of and did not provide evidence of the nominated third party accredited quality system. 308 Clearly the existence of the third party accredited quality system was still a fact which was relied upon in the assessment of the tenders. In discussing the Beckhaus Civil tender Mr Witherdin said the following when referring to their quality control: "Quality - third party accredited quality system, was previously RTA qualified. Would have a qualified engineer on site. Submitted previous quality procedures for other jobs." 309 Clearly Mr Witherdin accepted the statement of the existence of the third party accredited quality system and that became part of his recommendation for the acceptance of the tender. 310 Mr Witherdin was cross-examined concerning his reliance on representations concerning quality systems and a consideration of that indicates that he still relied upon the existence of a third party quality assurance system. The fact that other scores of various tenderers were close to that of Beckhaus does not detract from the fact of his reliance which, as I say, is also clear from the terms of his report. 311 I have referred to the evidence given by Mr Witherdin as to the importance which he placed on the financial capacity. Nothing detracted from his view on that and I accept his evidence in this regard that he would not recommend a contractor in such a financial position so far as a low value of the net assets was concerned. 312 Of course it was not Mr Witherdin who made the decision to accept the tender. That decision was made by the Brewarrina Council. The matter was considered at a meeting of the Council on 25 September 2001. There were eleven members present and it was resolved that the Beckhaus tender be accepted, "As recommended by the consultants PPK Environment and Infrastructure and agreed to by DLWC and DPWS after a thorough review". There is no evidence to suggest that either the review or recommendation was put before the Council. No evidence was given as to reliance by members of the Council. There was evidence from Mr Walters who put the matter forward to the Council that if PPK had not recommended Beckhaus he would not have recommended them to the Council. He himself did not read the full PPK report but merely noted their ultimate recommendation. In Henville v Walker (2001) 206 CLR 459 it was held that where a contravention of s 52(1) was one of two concurrent causes of a loss that was enough to enable damages to be recovered under s 82. McHugh J at paragraphs 106 to 109 referred to the matter in these terms: " [106] If the defendant's breach has 'materially contributed' to the loss or damage suffered, it will be regarded as a cause of the loss or damage, despite other factors or conditions having played an even more significant role in producing the loss or damage. As long as the breach materially contributed to the damage, a causal connection will ordinarily exist even though the breach without more would not have brought about the damage. In exceptional cases, where an abnormal event intervenes between the breach and damage, it may be right as a matter of common sense to hold that the breach was not a cause of damage. But such cases are exceptional. [107] Of particular importance to the present case is the long-standing recognition of the possibility that two or more causes may jointly influence a person to undertake a course of conduct . In separate judgments in Gould v Vaggelas, Wilson and Brennan JJ emphasised that a representation need not be the sole inducement in sustaining the loss. If 'it plays some part even if only a minor part', in contributing to the course of action taken -- in that case the formation of a contract -- a causal connection will exist. [108] This principle has been applied in cases where a complicating factor is the intervention of some act or decision of the plaintiff or a third party that allegedly constitutes a more immediate cause of the loss or damage. Thus, in Medlin v State Government Insurance Commission Deane, Dawson, Toohey and Gaudron JJ said: 'The ultimate question must, however, always be whether, notwithstanding the intervention of the subsequent decision , the defendant's wrongful act or omission is, as between the plaintiff and the defendant and as a matter of commonsense and experience, properly to be seen as having caused the relevant loss or damage. Indeed, in some cases, it may be potentially misleading to pose the question of causation in terms of whether an intervening act or decision has interrupted or broken a chain of causation which would otherwise have existed. An example of such a case is where the negligent act or omission was itself a direct or indirect contributing cause of the intervening act or decision.' (Emphasis added.) [109] Similarly, in respect of claims under s 82, courts have accepted that loss or damage is causally connected to a contravention of the Act if a misrepresentation was one of the causes of the loss or damage sustained by the claimant. As the Full Federal Court pointed out in Como Investments Pty Ltd (In liq) v Yenald Nominees Pty Ltd: 'The law does not consider cause and effect in mathematical or in philosophical terms. The law looks at what influences the actions of the parties. Acknowledging that people are often swayed by several considerations, influencing them to varying extents, the law attributes causality to a single one of those considerations, provided it had some substantial rather than negligible effect.'" 313 True it is that no-one from the Council who actually made the decision to award the tender was called to give evidence but it is plain from the minute that there were two matters put forward in favour of the acceptance of that tender. One was the recommendation by PPK and the other was that the investigations be carried out separately. It would seem to me that the recommendation by PPK was a material matter on which the decision was based. As I have found that recommendation was brought about in part as a result of the misleading conduct, causation is established. 314 So far as damages are concerned in these circumstances where the question was whether the Beckhaus Civil tender should be accepted in contrast to that of the next lowest tenderer who was Sudholz it should be noted that the difference between the two tenders was approximately $1 million. In these circumstances the damages which the Council may recover on its cross-claim would be no greater than the cost of rectification less the unpaid portion of the contract sum including provisional costs items and also less the difference between the contract sum and the amount which would have been paid to Sudholz as the next most likely tenderer. 315 Having regard to my decision on the cross-claim it is clear that the damages will not anywhere near approach a sufficient sum to demonstrate that the Council has in fact suffered damage. 316 As has been noted in submissions, the tender by Sudholz was about $1 million higher than that of Beckhaus but having regard to the terms of its tender and the provisional quantities, it would be likely to be at least another $200,000.00 more than those claimed by the plaintiff. There is nothing in the circumstances of this case which would lead one to consider some other order under s 87 rather than damages under s 82. Conclusion 317 I have found that in respect of the cross-claim the Council is entitled to damages for two small matters and naturally enough the evidence before me did not address those specific costs. The damages claim was based on estimates on several different bases predicated on substantial success by the Council on its cross-claim. In these circumstances it is probably appropriate that the parties either agree to these additional small amounts of damages or, if necessary, appropriate evidence can be taken. 318 I direct the parties to bring in short minutes to give effect to the reasons I have expressed in this judgment. If there are any matters requiring further consideration, such as interest and variation 21, the parties can let me have submissions and we can deal with the matters on the next occasion. **********
Last Modified: 12/10/2004 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Beckhaus
Brewarrina
(2001) 52 NSWLR 705
(2001) 206 CLR 459
(1999) 197 CLR 414