(f) Beckhaus did not respond to the letter of 3 May 2002.
(g) On 28 May 2002 the superintendent issued a payment certificate in respect of progress claim No 7; the amount certified was nil.
10 It was common ground between the parties that, as the payment certificate issued on 28 May 2002 was outside the period of 14 days referred to in the second paragraph of cl 42.1, it was invalid and had no legal effect.
11 In regard to the information that Beckhaus had in fact supplied to the Council, Macready AJ observed:
"Whether or not the information supplied to the superintendent was within the terms of the clause is a factual matter, which in the present case if it were relevant would raise a triable issue. Similarly the failure to supply the information in the monthly report along with the progress claim would raise a triable issue. The question is whether one can imply a condition precedent that suspends the obligation to assess".
12 The parties accepted that his Honour had accurately described what both agreed were triable issues. Further, it was common ground that the learned judge should, at the stage of summary judgment, determine the legal issues whether cl 42.1 contained a condition precedent as contended for by the Council and whether progress claim No 7 had been made in accordance with the requirement under the contract that payment claims were to be made "monthly".
13 Macready AJ dealt with the Council's argument based on the condition precedent as follows:
"The defendant's submission was in effect that the supply of the information was a condition precedent to the superintendent's obligation to consider and assess. It is to be noticed that at the end of the second paragraph of the clause the superintendent is to set out the amount that in his opinion is to be paid. He is to set out his calculations in writing of the amount and his reasons for the difference. That procedure certainly allows the superintendent to cater for the situation where insufficient information in his opinion or, indeed, no information has been supplied. If the contractor is foolish enough to not comply with the reasonable request of the superintendent he cannot be heard to complain if the superintendent treats his claim harshly. In these circumstances it is hard to see how the obligation on the superintendent that he 'shall issue' should be suspended. The reasoning behind the cases to which I have referred would not support such a construction. It would be necessary to imply a condition precedent to the effect contended for by the defendant. Such a condition would be inconsistent with an express term of the contract, namely, 'if no payment certificate has been issued, the principal shall pay the amount of the contractor's claim'. This express term has no qualifications to its operation."
14 I do not agree, with respect, that the condition precedent contended for by the Council would be inconsistent with the provision that "if no payment certificate has been issued, the principal shall pay the amount of the Contractor's claim". The obligation to pay the amount of the contractor's claim when no payment certificate has been issued is, by the third paragraph of cl 42.1, expressed to be "subject to the provisions of the contract". This express qualification (that is, that the obligation to pay be subject to the terms of the contract) means that no inconsistency arises.
15 Macready AJ observed that the procedure in cl 42.1 "allows the superintendent to cater for the situation where insufficient information in his opinion or, indeed, no information has been supplied". The solution proposed by his Honour was that the superintendent could treat "harshly" those claims inadequately supported by appropriate evidence or information. Mr Harrison SC, who appeared for Beckhaus, supported this reasoning. He contended that a superintendent who could not adequately assess a claim for payment because it was not supported by evidence or information should issue a certificate assessing the value of the claim at nil.
16 In some situations, the failure on the part of a contractor to support its claim for payment with evidence of the amount due and information reasonably required might make it difficult or even impossible for the superintendent to value the claim. I accept that in many instances the superintendent will be familiar with the work done and be able to assess its value of his or her own accord, without reference to evidence or information supplied by the contractor. But there may well be instances where this would be difficult or even impossible. In large construction projects, work is sometimes performed 24 hours per day over a large area of ground by a contractor who employs hundreds of workers, or more, and also employs sub-contractors, who in turn employ large numbers of workers themselves. In these circumstances, it may happen that work is completed and closed up before it has properly been inspected, measured and valued by the superintendent. This is but one example of circumstances under which a superintendent may need evidence and information from a contractor to be able reliably to assess and value a progress claim. Other and different circumstances may also occur which may result in the same need.
17 Beckhaus submitted that the ability of a superintendent to issue a nil payment certificate, where a contractor failed to provide evidence and information in support of its claim, afforded a practical way out of the dilemma in which, in those circumstances, the superintendent might experience. The Council, on the other hand, submitted that cl 42.1 provided for this situation by requiring the contractor to support its claim with evidence and the requisite information, failing which the superintendent's obligation to issue a payment certificate would be suspended.
18 In considering the merits of these opposing arguments, the question arises whether cl 42.1 imposes a contractual obligation on the contractor to supply evidence and information. Inherent in this question is the further question whether a claim for payment comprises the formal claim document as well as the evidence and information (or the claim document alone).
19 Beckhaus accepted that a claim for payment within the meaning of cl 42.1 would have to "include the value of work carried out by the Contractor in the performance of the contract to that time together with all amounts then due to the Contractor arising out of or in connection with the contract or for any alleged breach thereof" (as provided by the second sentence of the first paragraph of the clause). Beckhaus submitted, however, that the evidence of the amount due to the contractor and the information that the superintendent might reasonably require did not form part of the claim.
20 The ordinary meaning of the first paragraph of cl 42.1 supports Beckhaus' submission. The first sentence of the paragraph distinguishes between "claims for payment" and the evidence and information that is to support such claims. The second sentence of the paragraph sets out matters that are expressly included in claims for payment - and evidence and information are not mentioned in this context. In my opinion, the evidence and information do not form part of payment claims.
21 This conclusion, however, does not mean that the requirement to support the claim with evidence and provide information to the superintendent cannot condition the performance of the superintendent's obligation to issue a payment certificate.
22 The requirement to support the claim with evidence and information can constitute such a condition on either of two bases. First, it may be a non-promissory condition to which the superintendent's obligation to issue a payment certificate is subject (as to non-promissory conditions of this kind, see Perri v Coolangatta Investments Pty Limited (1982) 149 CLR 537 at 551 to 552 and 565). Second, it may constitute an obligation imposed on the contractor, performance of which conditions the superintendent's obligation to issue a payment certificate. On either basis, a failure by the contractor to support a payment claim with evidence and the required information would mean that the superintendent would not be obliged to issue a payment certificate.
23 It is not necessary for the purposes of these reasons to decide whether the requirement as to evidence and information is a non-promissory condition or an obligation imposed on the contractor. But the question does call for some examination.
24 One possible argument against the requirement being a contractual obligation the contractor is required to perform is that it is contained in a sentence requiring the contractor to deliver payment claims at specified times. It may be thought that it is unlikely that the parties would intend the contractor to be contractually obliged to make its claims at specified times - the question may be asked, if the contractor feels like delaying its claim, why should the principal under the contract be concerned about that? If the contractor is not obliged to make claims at specified times, it might be difficult to contend that the contractor is obliged to support its claims with evidence and information.
25 The answer to the question posed in the preceding paragraph is provided by Dorter and Sharkey, Building and Construction Contracts in Australia (2nd ed) at para 10.270:
"In practice, whether it be through oversight or for tactical reasons, sometimes the contractor does not make a claim when he or she should. Accordingly, there can arise situations where the overall interests of the contract and the project require recognition of the need, nonetheless, to make a progress claim, for example entitlements of nominated sub-contractors or other unpaid third parties. Accordingly, AS 4000 and AS 2124-1986 contain the sensible, flexible and wider discretion for the superintendent to issue a payment certificate even though the contractor has not made a claim for payment".
26 In other words, the principal may have good reason to require the contractor to make claims at specified times or at specified intervals. This seems to be the reason why the first paragraph of cl 42.1 provides that the contractor "shall" deliver claims to the superintendent at the times for payment "stated in the Annexure". The word "shall" is an indication that the parties intended to impose a contractual obligation on the contractor to deliver its payment claims at the times stipulated.
27 On the other hand, it is difficult to see how a breach of such an obligation could sound in damages, and ordinarily it would be impractical to seek specific performance of it.
28 One thing, however, is plain: the significance of the requirement that payment claims should be delivered at specified times is that failure by the contractor to comply therewith allows the superintendent to issue a payment certificate of his or her own accord (as provided by the third paragraph of the cl 42.1). In some circumstances, as Dorter and Sharkey point out, this right could be of importance to the principal.
29 Similar considerations apply to the requirement to supply evidence and information.
30 Mr Harrison submitted that the words requiring the contractor to supply evidence and information in support of claims for payment are merely facilitative and do not impose any obligation on the contractor. For my part, however, I can see no point in the clause incorporating the words in question without those words having some contractual effect. There is a strong presumption against words being otiose.
31 One does not have to go far to find an important contractual and practical purpose for the requirement that the contractor provide evidence of the amount due and information reasonably required by the contractor. I have referred to the real possibility that a superintendent might need evidence and information before being able to issue a reasonably accurate payment certificate. By cl 23 of the contract the principal is required to ensure that the superintendent "arrives at a reasonable measure or value of work, quantities or time". Without a contractor providing evidence of the amount claimed by it and information that the superintendent might reasonably require, the superintendent might well not be able to make a reasonable measurement or valuation of the work, quantities or time. It follows that superintendent's ability to issue a certificate in accordance with cl 23 might well depend on the contractor supporting its claim for payment by evidence and by providing information to the superintendent that he or she may reasonably require.
32 Moreover, the second paragraph of cl 42.1 requires the superintendent, in a payment certificate, to set out his or her calculations and the reasons for any difference between the amount certified and the amount claimed. The superintendent's ability to comply with this requirement, also, may well rest on whether the requisite evidence and information is provided.
33 The fact that the ability of the superintendent to comply with cl 23 and the second paragraph of cl 42.1 may depend on whether the contractor complies with the requirements set out in the first sentence of the first paragraph of cl 42.1 is a powerful indication that the latter requirements are intended to have contractual force. For present purposes, it is not to the point whether that force results in a contractual obligation to perform or a non-promissory condition. What is to the point, in my view, is that on either basis, the superintendent does not have to issue a payment certificate until the evidence and information is provided.
34 In this sense, the requirement that the contractor provide the necessary evidence and information is comparable to the purchaser's obligation to serve a notice to complete. This notice has to be served before the vendor can be required to complete the sale: Michael Realty Pty Limited v Carr [1977] 1 NSWLR 553 at 571. In the same way, the evidence and information have to be provided before the superintendent can be required to issue a payment certificate. They are both conditions precedent to performance.
35 The form of cl 42.1 supports this inference. For the sake of convenience, I shall repeat the relevant parts of the clause. They are:
"At the times for payment claims stated in the Annexure …., the Contractor shall deliver to the Superintendent claims for payment supported by evidence of the amount due to the Contractor and such information as the Superintendent may reasonably require.
…
Within fourteen days after receipt of the claim for payment, the Superintendent shall issue to the principal and to the Contractor a payment certificate stating the amount of the payment which, in the opinion of the Superintendent, is to be made by the principal to the Contractor or by the Contractor to the principal. The Superintendent shall set out in the certificate the calculations employed to arrive at the amount and, if the amount is more or less than the amount claimed by the Contractor, the reasons for the difference".
36 The requirement that payment claims be supported by evidence and information is closely followed by the provision that, within 14 days after receipt of a claim for payment, the superintendent shall issue a payment certificate. The juxtaposition between the requirement to supply evidence and information, on the one hand, and the obligation of the superintendent to issue a payment certificate, on the other suggests that there is a relationship and connection between the provision of evidence and information and the issue of a payment certificate. In my opinion, the relationship and connection is as stated above.
37 On the basis of the construction contended for by Beckhaus, the superintendent would be required to issue a payment certificate even in circumstances where he or she was entirely unable to assess the claim. This, in my view, is an incongruous result that could not have been intended. In this regard Dorter and Sharkey op cit say the following in regard to the second paragraph of cl 42.1:
"The drafter could have perhaps better have employed the relative 'such' (as he has in other clauses) … This may not be so if the intention were in fact to require the superintendent to issue a payment certificate on any claim for payment whatsoever but such an intention is very unlikely."