The proposed penalty
57 By s 44AAG(2)(a) of the CC Act, the Court may impose a civil penalty on a person who is declared to be in breach of a civil penalty provision of a uniform energy law or a State/Territory energy law.
58 Section 2AA(1)(c) of the NEL specifies that a civil penalty provision is a provision of the NER prescribed by the National Electricity (South Australia) Regulations (the Regulations) to be a civil penalty provision. Regulation 6(1) of the Regulations provides that, for the purposes of s 2AA(1)(c), a provision of the NER listed in Schedule 1 of the Regulations is a civil penalty provision. Schedule 1 lists NER 4.4.3 as a civil penalty provision.
59 By s 2 of the NEL, the maximum penalty applicable throughout the whole of the relevant period for a contravention of NER 4.4.3 was an amount not exceeding $100,000 in addition to an amount not exceeding $10,000 for each day that the contravention continued. This means that the maximum penalty which may be imposed for Pacific Hydro's continuing contravention of NER 4.4.3 in the period from 6 August 2013 to 3 October 2016 is $11,650,000 (being $100,000 plus $10,000 for each of the 1,155 days during which the contravention continued).
60 The parties have agreed that a civil penalty of $1,100,000 is appropriate for Pacific Hydro's contravention.
61 The Court may act on the parties' agreement in determining an appropriate civil penalty: Commonwealth of Australia v Director, Fair Work Building Industry Inspectorate [2015] HCA 46; (2015) 258 CLR 482 (Cth v FWBII). In that case, the plurality said:
[46] [T]here is an important public policy involved in promoting predictability of outcome in civil penalty proceedings and … the practice of receiving and, if appropriate, accepting agreed penalty submissions increases the predictability of outcome for regulators and wrongdoers…
62 Later, the plurality said:
[58] … Subject to the court being sufficiently persuaded of the accuracy of the parties' agreement as to facts and consequences, and that the penalty which the parties propose is an appropriate remedy in the circumstances thus revealed, it is consistent with principle and … highly desirable in practice for the court to accept the parties' proposal and therefore impose the proposed penalty. To do so is no different in principle or practice from approving an infant's compromise, a custody or property compromise, a group proceeding settlement or a scheme of arrangement.
(Emphasis in the original and citation omitted)
63 However, as was noted by the Full Court (Wigney, Beach and O'Bryan JJ) in Volkswagen Aktiengesellschaft v Australian Competition and Consumer Commission [2021] FCAFC 49 at [126], the public interest in predictability of outcomes cannot override the statutory directive for the Court to impose a penalty which it considers to be appropriate.
64 A number of matters of principle bearing upon the fixation of an appropriate civil penalty are settled. The principal (and perhaps only) object of the imposition of a civil penalty is to achieve deterrence, both general and specific: Cth v FWBII at [55]. Thus it has been said that a civil penalty should put a price on contraventions which is sufficiently high to deter repetition by the contravenor and by others who may be tempted to contravene the Act in a similar way: Trade Practices Commission v CSR Ltd [1990] FCA 762; [1991] ATPR 41-076 at 52,152 in a passage approved in Cth v FWBII at [55]. A civil penalty should not be so high as to be oppressive, but should be such as to deter participants in the relevant industry "from the cynical calculation involved in weighing up the risk of penalty against the profits to be made from contraventions": Singtel Optus Pty Ltd v Australian Competition and Consumer Commissioner [2012] FCAFC 20: (2012) 287 ALR 249 at [63].
65 Section 64 of the NEL requires the Court when fixing a civil penalty to have regard to all relevant matters, including:
(a) the nature and extent of the breach; and
(b) the nature and extent of any loss or damage suffered as a result of the breach; and
(c) the circumstances in which the breach took place; and
(d) whether the person has engaged in any similar conduct and been found to be in breach of a provision of [the NEL], the Rules or the Regulations in respect of that conduct; and
(e) whether the service provider had in place a compliance program approved by the AER or required under the Rules, and if so, whether the service provider has been complying with that program.
66 As is apparent, the listed matters are not an exhaustive statement of the matters which may be relevant. Matters which may, depending on the circumstances of the given case, be relevant include those discussed by French J in CSR at 52,152-3. In addition to those to which s 64 directs attention, these include the size and resources of the contravenor; the degree of power of the contravenor; the deliberateness of the conduct; the length of time over which the conduct occurred; the degree of involvement of senior management; the culture of the organisation as to compliance or contravention; any cooperation; and any evidence of contrition - see Construction, Forestry, Maritime, Mining and Energy Union v Australian Building and Construction Commissioner (The Non-Indemnification Personal Payment Case) [2018] FCAFC 97; (2018) 264 FCR 155 at [20].
67 It is also established that the Court is to determine an appropriate penalty by a process of instinctive synthesis after taking into account all relevant factors, similar to the manner discussed in Markarian v The Queen [2005] HCA 25; (2005) 228 CLR 357 at [37], [39] - see Pattinson v Australian Building and Construction Commissioner [2020] FCAFC 177; (2020) 299 IR 404 at [90], [112].
68 The nature and circumstances of Pacific Hydro's contravention have been set out above and need not be repeated.
69 As previously noted, Suzlon (an international wind turbine supplier) had designed, supplied and installed the Clements Gap Wind Farm. Pacific Hydro was not aware until after 28 September 2016 that Repeat LVRT Protection Systems had been applied on the wind turbines and, accordingly, that non-approved settings had been applied. The circumstance that its contravention was not intentional or reckless is an important matter of context bearing upon the fixation of penalty.
70 The blackout on 28 September 2016 caused a review of the situation. On 3 October 2016, Pacific Hydro informed AEMO that:
(a) Suzlon had indicated that it was possible to raise the settings on the Repeat LVRT Protection Systems so that the Systems would be triggered only if the LVRT Capability was activated more than three times within a 120 second period; and
(b) it had requested Suzlon to modify the settings so that the Repeat LVRT Protection Systems on the generating units would be triggered if the LVRT Capability was activated between 15 and 20 times in a 120 second period.
71 On or about 4 October 2016, Suzlon did raise the Repeat LVRT Protection System settings on each of the Clements Gap Wind Farm generating units so that the Systems would activate only if the LVRT Capability was activated 15, 17 or 20 times (the settings varied across the generating units) within a 120 second period.
72 I infer that this was done with the approval of AEMO. It can therefore be concluded that Pacific Hydro's contravention was not only not deliberate, but it took prompt action to rectify the position once it became aware of the situation.
73 Pacific Hydro's contravention must be characterised as serious. When negotiating its performance standards, Pacific Hydro did not identify to either ElectraNet or AEMO that the LVRT Capability on the turbines was subject to the settings in the Repeat LVRT Protection Systems, or that the turbines would shut down in the event that the voltage of any of the three phases at the generating units' terminals fell below 80% of nominal voltage three times within a 120 second period. Moreover, for the period of just on three years and two months which ensued after 6 August 2013, Pacific Hydro did not notify either ElectraNet or AEMO of this circumstance. Further, during the Relevant Period, Pacific Hydro did not make any assessment of the wind turbines which may have led to the presence of the Repeat LVRT Protection Systems installed by Suzlon being identified.
74 The seriousness of Pacific Hydro's contravention in applying non-approved settings is underlined by its potential consequences. As noted earlier in these reasons, AEMO's ability to achieve and maintain security in the power system depended, amongst other things, on Generators such as Pacific Hydro providing, both at the time of the connection and subsequently, accurate and complete information concerning their ability to operate in accordance with the agreed performance standards. The rigorous regime summarised earlier and in particular cl S5.2.2, is directed, amongst other things, to the achievement and maintenance of power system security, this being an important public purpose. Pacific Hydro's use of non-approved settings in the present case compromised AEMO's ability to discharge its responsibility because it meant that it was making important decisions concerning the secure operating limits of the power system on the basis of incomplete information. As the events of 28 September 2016 indicate, a compromise of the security of the power system can have extensive and serious consequences.
75 It is, however, appropriate to note the absence of some aggravating features as well as matters which mitigate the seriousness of the contravention. Apart from the fact that Pacific Hydro's contravention was not deliberate, it has not previously been found by a court to be in breach of a provision in the NEL or in the NER; it had during the Relevant Period sought to ensure that it complied with its obligations under the NEL by implementing its own compliance program, as required by NER 4.15(b); and it did not obtain any financial benefit by reason of its contravention. The AER does not allege that the involvement of Pacific Hydro's senior management made the contravention more serious.
76 Pacific Hydro is part of a substantial corporate group. It is a wholly owned subsidiary of Pacific Hydro Pty Ltd (PHPL) which is, and was during the Relevant Period, the holding company for the Pacific Hydro corporate group's operations in Australia. PHPL was also the relevant reporting entity for revenue and profit during the Relevant Period. PHPL reported total revenue and profit after tax for the period 2013 to 2016 as follows:
Period $ Total Revenue $ Profit/loss after tax
12 months ending 30 June 2014 205.576 million 12.011 million
6 months ending 31 December 2014 104.236 million 56.897 million
12 months ending 31 December 2015 247.457 million 19.910 million
12 months ending 31 December 2016 256.548 million 34.525 million