[2025] NSWCATAP 283
General information, not legal advice.
NCAT Appeal Panel
2025-11-07
R C Titterton OAM, Senior MemberM Tyson, Senior Member
Original judgment source is linked above.
(1) rectification costs, $9,680.00 (Item 1);
(2) seal rectification, $550.00 (Item 2);
(3) a window gap seal, $1,980.00 (Item 3); and
(4) concrete marks, $1,155.00 (Item 4).
1. The rectification cost is outside of the agreement of the work, My Company Shouldnt liable for it. Chuling Su provided evidences that appears to lack authenticity and includes fraudulent invoices.
2. Chuling Su had an owner builder permit, this cost is invoiced by her own company, this cost shouldn't accept by the court. The submitted invoice constitutes a sham invoice, deliberately misrepresenting the transaction to circumvent fair market principles. This violates Australian commercial law requirements for authenticity, arm's-length dealings, and good faith. And the work value maximum $70 (1 hours for work, $50/hr and materials only cost $20).
3. This is a daily work, I only worked for 2 days and I received $1,000. The rest of work are not liable to me.
4. the work is completed. Engineer does not show this is an defect, Chuling Su received the engineer certificate already. therefore, this cost is not liable to me.
5. Chuling SU should pay me back the Daily labour work. it is outside of the contract and the total is $1,843.75
(grammatical and other errors as in original)
29 Parties to internal appeal
The parties to an internal appeal are -
(a) the appellant, and
(b) any person or body (other than the appellant) who was a party to the proceedings before the Tribunal at first instance, and
(c) if the Attorney General or another Minister intervenes in the proceedings under section 44 of the Act - the Attorney General or Minister, and
(d) any other person who is made a party to the proceedings by the Tribunal under section 44 of the Act, and
(e) any other person required to be joined or treated as a party to the proceedings by a Division Schedule for a Division of the Tribunal, enabling legislation or the procedural rules.
(1) whether there has been a failure to provide proper reasons;
(2) whether the Tribunal identified the wrong issue or asked the wrong question;
(3) whether a wrong principle of law had been applied;
(4) whether there was a failure to afford procedural fairness;
(5) whether the Tribunal failed to take into account relevant (that is, mandatory) considerations;
(6) whether the Tribunal took into account an irrelevant consideration;
(7) whether there was no evidence to support a finding of fact;
(8) whether the decision was so unreasonable that no reasonable decision-maker would make it.
To the above list [referring to the list in Prendergast extracted above] might be added the following (some of which are nuanced aspects of the categories in Prendergast):
(1) Whether the Tribunal drew inferences that were not available from the facts as found (an extension of item 7 [of Prendergast]) ...
(2) Whether the construction of a statute or contract arrived at by the Tribunal at first instance was wrong in some identified way: ...
(3) Whether the Tribunal's decision was vitiated by bias, or a reasonable apprehension of bias, relates to and intersects with the fair hearing rule, and may encompass or be related to the procedural fairness question: ...
(4) Whether the Tribunal failed to respond to substantial, clearly articulated arguments based on established facts which may constitute a failure to accord natural justice, that is, procedural unfairness. Alternatively, it may also constitute a constructive failure to exercise jurisdiction: ...
(5) Whether the facts as found necessarily satisfied the statute or necessarily did not: ...
33 Plainly, the categories are not closed.
(1) the decision of the Tribunal under appeal was not fair and equitable; or
(2) the decision of the Tribunal under appeal was against the weight of evidence; or
(3) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
Ordinarily it is appropriate to grant leave to appeal only in matters that involve:
(a) Issues of principle;
(b) questions of public importance or matters of administration or policy which might have general application; or
(c) an injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
(d) a factual error that was unreasonably arrived at and clearly mistaken; or
(e) the Tribunal having gone about the fact finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed.
(1) at [26], the Tribunal stated that Seido noted that the concrete upturn wall had embedded timber, which had been inadequately installed, and would not be waterproof and could potentially cause the concrete to crack. Seido offered four possible solutions, and the respondent elected to implement the fourth, which was to waterproof and render the wall;
(2) at [28], the Tribunal stated that, with regard to this defect, the appellant acknowledged that this was a defect requiring rectification, but that the appellant submitted it had never agreed to do rendering as part of the Original Scope of Works. (We note that the appellant repeated that submission at the appeal hearing);
(3) at [30], the Tribunal stated that the Seido Report noted that a pvc pipe installed by the appellant was unsealed, which could enable water to penetrate the concrete slab and wall. Seido offered four possible solutions, and the respondent elected to implement the third, which was to seal off the penetration. The respondent engaged the services of her own interior decorating company for this service at a cost of $550.00;
(4) at [33], the Tribunal states that the respondent stated that concrete marks made by the appellant's sub-contractor had stained her front retaining wall, and that she had obtained a quote for $1,155 to rectify these marks;
(5) at [35], the Tribunal states that the Seido Report noted a gap between the window frame and the steel lintel above caused water ingress concerns. Seido offered two possible solutions, and the respondent obtained a quotation of $1,980 to rectify this issue;
(6) at [36], in possible contradiction to the Tribunal's statement at [5] that further works and variations were agreed and implemented between the parties "along the way", but these were not the "direct subject" of the proceedings, the Tribunal states that "the [appellant] noted that the window installation was not part of the Original Scope of Works but did acknowledge that this was part of a variation added subsequently". The Tribunal then notes that this work was paid for by the respondent, with the appellant not explaining its failure to rectify the gap.
With regard to the arrangements between the parties, I find that the [appellant] did contract with the [respondent] to provide the Original Scope of Works for a fixed price, no hidden costs or additional labour or material charges. The [respondent] continues to owe $3,250 to the [appellant] under that contract, and that amount should therefore be applied to the rectification costs awarded herein.
With regard to the [respondent's] claim for rectification costs of $9,680 paid to Duo Rendering Pty Ltd, to rectify some of the defects, I find that these defects relate to the residential building works undertaken by the [appellant], and have been acknowledged by the [appellant]. The [appellant] elected not to rectify the defects, and therefore liability for the cost of rectification is attributable to the Respondent accordingly.
With regard to the [respondent's] claim for rectification costs of $550 paid to W & M Construction Project Pty Ltd to rectify the seal, I find that this defect relates to the residential building works undertaken by the [appellant], and has been acknowledged by the [appellant]. The [appellant] elected not to rectify the defects, and therefore liability for the cost of rectification is attributable to the [appellant] accordingly].
With regard to the [respondent's] claim for rectification costs of $10,010 quoted by Built & Co Pty Ltd, to rectify some of the defects, I find that the window gap seal ($1,980) and the removal of concrete marks ($1,155) are defects which are attributable to the [appellant], which he [sic - it] either refused to rectify or rectified inadequately, and therefore liability for the cost of rectification is attributable to the [appellant] accordingly.
CONCRETE UPTURN WALL
Timbers have been spotted embedded into concrete turnup wall after formwork has been removed as per the following photo shows. It is believed that timbers used as formwork support have been inadequately installed and result they became impossible to remove when concrete was poured around it.
[photos and diagram]
Concerns:
1. Timber could span and rot when contact with moisture particularly as H2 treated pine and over time it could cause the surrounding concrete to crack
2. Similar to basement or other underground external wall, this concrete upturn wall has been designed as retaining wall which the external face will be in contract with natural ground at all time. Proper waterproofing is required to stop moisture/water to penetrate into interior space however it is impossible to apply waterproofing due to the embedded timber.
Suggestion:
1. Completely remove the embedded timber off from concrete wall.
2. Roughen and etch the concrete surface around the opening after timber has been properly removed
3. Apply concrete repair mortar such SikaQuick-2500AU Repair mortar to seal up all penetration. Install steel anchor as per instruction where applicable.
4. Apply waterproofing to external face of upturn wall and apply render or other interior finish to the internal face.
... there are certain minimum characteristics that a Tribunal's reasons must possess. These are really supplied, in relation to the Tribunal, by s 62(3) of the [Civil and Administrative Tribunal Act 2013 (NSW)] which ... requires there to be set out in reasons (when requested by a party):
(a) the findings on material questions of fact, referring to the evidence or other material on which those findings were based,
(b) the Tribunal's understanding of the applicable law, and
(c) the reasoning processes that lead the Tribunal to the conclusions it made.
(emphasis added)
it was certainly a legal error by failure to give adequate, intelligible or logical reasons ... It was also a constructive failure to exercise jurisdiction insofar as it involved a failure to grapple with a substantial and clearly articulated aspect of the appellant's case ... That type of error can also be expressed in terms of procedural fairness (as raised by ground 5(b)): Dranichnikov v Minister for Immigration and Multicultural Affairs [2003] HCA 26; (2003) 77 ALJR 1088 at [24].
(1) Mr Jiadong Su is removed as a respondent.
(2) The appeal is allowed.
(3) The order of the Consumer and Commercial Division of the Civil and Administrative Tribunal of 5 June 2025 in matter 2025/00040649 is set aside.
(4) The matter is remitted to the Consumer and Commercial Division of the Civil and Administrative Tribunal for redetermination by a differently constituted Tribunal.
(5) If the appellant seeks its costs of the appeal, it is to file and serve any submissions (and if necessary, evidence) as to costs on or before 21 November 2025, 14 days from publication.
(6) The respondent may respond on or before 5 December 2025, 28 days from publication.
(7) The appellant may reply on or before 12 December 2025, 35 days from publication.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
10 November 2025 - Amended references in cover sheet and paragraph 27.
13 November 2025 - Paragraph 74 amended from "sores position then" to "a worse position than"
13 November 2025 - Paragraph 74 amended from "then" to "than"
Ace Homes & Construction Pty Ltd
Su [2025] NSWCATAP 283;
(2003) 77 ALJR 1088