[2024] VCAT 1218
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2024-12-19
Original judgment source is linked above.
Review the failure by Head, Transport for Victoria to confirm within a reasonable time that the requirements of Condition 30 of Planning Permit DC/309/2022 (and, in particular, condition 30(b)) have been completed to its satisfaction).
An amended Transport Impact Assessment prepared by Traffix Group (dated July 2024) was provided to Head, Transport for Victoria ('TfV') on 5 August 2024. This followed months of discussions between Traffix Group and TfV to confirm the methodology and assumptions to be adopted in the assessment. TfV has failed to make a decision within a reasonable time, which, pursuant to regulation 54 of the Planning and Environment Regulations 2015, is 30 days.
(a) Prior to commencement of the buildings and/or works unless otherwise agreed in writing by Head, Transport for Victoria the following must be completed to the satisfaction of and at no cost to Head Transport for Victoria:
....
(b) An Amended Transport Impact Assessment report must be submitted to and approved by the Head, Transport for Victoria and the responsible authority. The Transport Impact Assessment must include the following: ....
In the alternative, should the Tribunal not be satisfied that TfV's letter of 7 October 2024 amounted to a decision, the Applicant respectfully requests that the Tribunal exercises its discretion under section 126 of the Victorian Civil and Administrative Act 1998 to extend the time for commencement of the proceeding.
Had TfV not advised the Applicant on 5 September 2024 (Day 31) that it was 'generally...happy' with the Traffic Impact Assessment, the Applicant would have made an application for review within 28 days of the deemed refusal. If the Tribunal requires us to elaborate on this point by reference to the factors identified in Hunter Valley Developments Pty Ltd v Minister for Home Affairs and Environment (1984) FCR 344), we would be pleased to do so.
(a) to consider the applicant's request to amend the application from an application made under section 149(1)(d) of the PE Act to an application made under section 149(1)(a) of the PE Act
(b) to consider whether the application was made within or outside of any time limit;
(c) if the application is determined to have been made outside of any time limit, to consider whether to extend the time to commence the proceeding under section 126 of the Victorian Civil and Administrative Tribunal Act 1998 (Vic) ('VCAT Act'); and
(d) to consider the future conduct of the proceeding. This may include a consideration of dates, duration, compulsory conference and/or venue.
Was the communication of the Head, Transport for Victoria, dated 7 October 2024, a decision for the purpose of section 149(1) of the Planning and Environment Act 1987 (Vic)?
It appears to me that Parliament's intention is the same - that only a decision that is final or operative and determinative be subjected to merits review by the Tribunal.
Was the application made within or outside of any time limit?
An application for review of a decision referred to in subsection (1)(a), (b) or (c) must be made within 28 days after the day on which the decision is made.
Extension of the time to commence the proceeding under section 126 of the VCAT Act
45.1 whether the applicant can show an acceptable explanation for the delay;
45.2 whether it is fair and equitable in the circumstances to extend time;
45.3 whether the applicant's actions continued to make the decision maker aware that they contest the finality of the decision, as distinct from allowing the decision maker to believe that the matter was finally concluded;
45.4 whether the respondent has been prejudiced by the delay;
45.5 whether the delay may result in the unsettling of other people or of established practices;
45.6 the merits of the substantive application; and
45.7 consideration of fairness as between the applicant and other persons otherwise in a like position.
Did the decision maker believe the matter was finally concluded?
Whether the delay may result in the unsettling of other people or of established practices
The request to amend the application from an application made under section 149(1)(d) of the PE Act to an application made under section 149(1)(a) of the PE Act - granted
149 (1) A specified person may apply to the Tribunal for the review of -
(a) a decision of a specified body in relation to a matter if a planning scheme specifies or a permit contains a condition that the matter must be done to the satisfaction, or must not be done without the consent or approval, of the specified body...
...
(d) if there is no prescribed time for a decision of a kind referred to in paragraph (a), (b) or (c), a failure of a person or body to make that decision within a reasonable time after the matter is referred to it.
[1] The submissions and evidence of the parties, any supporting exhibits given at the hearing, and the statements of grounds filed; have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[2] In an email addressed to the Registrar of the Tribunal dated 28 October 2024.
[4] Citing the Federal Court of Australia's judgment in Hunter Valley Developments Pty Ltd v Minister for Home Affairs and Environment [1984] FCA 176; [1984] 3 FCR 344.
723 Calder Highway Maiden Gully Pty Ltd
Head, Transport for Victoria