sec.37 Grounds for amending, suspending or cancelling boat harbour approvals
Each of the following is a ground for amending, suspending or cancelling a boat harbour approval— the approval was obtained because of false or misleading information; the approval was given in error; the holder of the approval has failed to comply with a condition of the approval; the holder of the approval is not, or is no longer, a suitable person to hold the approval; the holder of the approval has failed to pay a fee payable under the Act in relation to the approval by the date or within the period during which the fee must be paid; there has been a material change of circumstances since the approval was granted and, had the changed circumstances existed when the approval was granted, the approval would not have been granted.
- (a) the approval was obtained because of false or misleading information;
- (b) the approval was given in error;
- (c) the holder of the approval has failed to comply with a condition of the approval;
- (d) the holder of the approval is not, or is no longer, a suitable person to hold the approval;
- (e) the holder of the approval has failed to pay a fee payable under the Act in relation to the approval by the date or within the period during which the fee must be paid;
- (f) there has been a material change of circumstances since the approval was granted and, had the changed circumstances existed when the approval was granted, the approval would not have been granted.