Residential Building Work Contracts and Dispute Resolution Act 2016
13Contracts must be in writing
Start here
Get a plain-English read of 13
Turn the raw legal text into a practical explanation grounded in Residential Building Work Contracts and Dispute Resolution Act 2016.
13 Contracts must be in writing
A building contractor who enters into a residential building work contract must ensure the contract –
(a) is in written form when it is entered into; or
(b) is put into written form –
(i) as soon as practicable (but in any case within 5 business days) after it is entered into; and
(ii) before residential building work begins to be performed under the contract.
Penalty: In the case of –
(a) a body corporate, a fine not exceeding 800 penalty units; or
(b) an individual, a fine not exceeding 300 penalty units.