Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2019
11Modified system not to be commissioned unless properly installed
Start here
Get a plain-English read of 11
Turn the raw legal text into a practical explanation grounded in Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2019.
11 Modified system not to be commissioned unless properly installed
11 Modified system not to be commissioned unless properly installed
The person responsible for a modified storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
(a) the modification has been implemented by a duly qualified person, and
(b) the person by whom the modification has been implemented has provided the person responsible for the system with—
(i) a list of the industry standards that have been followed in connection with the implementation of the modification, and
(ii) a copy of the implementation specifications for the modification, and
(iii) current “as-built” drawings for the system.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).