sch.3-sec.109 When particular scheme pipelines become non-scheme pipelines
This clause applies to a pipeline that, before the commencement day, was a voluntary access arrangement pipeline and— is deemed to be a scheme pipeline under clause 105; or becomes a scheme pipeline under clause 108. On the earlier of the following events happening, the pipeline becomes a non-scheme pipeline— if there is an applicable access arrangement that applies to the pipeline services provided by means of that pipeline—when that arrangement expires; when a scheme pipeline revocation determination takes effect in relation to the pipeline. sch 3 s 109 ins 2022 No. 21 (SA) s 90 (2) (sch.3-sec.109-ssec.1) This clause applies to a pipeline that, before the commencement day, was a voluntary access arrangement pipeline and— is deemed to be a scheme pipeline under clause 105; or becomes a scheme pipeline under clause 108. (sch.3-sec.109-ssec.2) On the earlier of the following events happening, the pipeline becomes a non-scheme pipeline— if there is an applicable access arrangement that applies to the pipeline services provided by means of that pipeline—when that arrangement expires; when a scheme pipeline revocation determination takes effect in relation to the pipeline.
- (a) is deemed to be a scheme pipeline under clause 105; or
- (b) becomes a scheme pipeline under clause 108.
- (a) if there is an applicable access arrangement that applies to the pipeline services provided by means of that pipeline—when that arrangement expires;
- (b) when a scheme pipeline revocation determination takes effect in relation to the pipeline.