sec.112 AEMO to develop load shedding procedures for each participating jurisdiction
AEMO must, in accordance with the Rules, develop, maintain, and if necessary, update procedures in relation to the manner in which loads or classes of loads (including sensitive loads) will be shed or restored— in this jurisdiction in accordance with the jurisdictional load shedding guidelines; and as between participating jurisdictions. AEMO (if not the jurisdictional system security coordinator) must give to the jurisdictional system security coordinator a copy of the AEMO load shedding procedures, and any updated procedures, applicable to this jurisdiction. The procedures must be consistent with the relevant jurisdictional load shedding guidelines. s 112 amd 2009 No. 31 (SA) s 39 (sec.112-ssec.1) AEMO must, in accordance with the Rules, develop, maintain, and if necessary, update procedures in relation to the manner in which loads or classes of loads (including sensitive loads) will be shed or restored— in this jurisdiction in accordance with the jurisdictional load shedding guidelines; and as between participating jurisdictions. (sec.112-ssec.2) AEMO (if not the jurisdictional system security coordinator) must give to the jurisdictional system security coordinator a copy of the AEMO load shedding procedures, and any updated procedures, applicable to this jurisdiction. (sec.112-ssec.3) The procedures must be consistent with the relevant jurisdictional load shedding guidelines.
- (a) in this jurisdiction in accordance with the jurisdictional load shedding guidelines; and
- (b) as between participating jurisdictions.