9 Fee
The project proponent is required to pay the Crown $123 750 by 31 July 2020 to cover the costs and expenses which may be incurred by the Crown, or the Commission, in connection with the assessment of the project or the planning approval process.
Displayed and numbered in accordance with the Rules Publication Act 1953.
Notified in the Gazette on 24 June 2020
This order is administered in the Department of Justice.