Hydro-Electric Corporation Regulations 2024
4Major power facility installed capacity
Start here
Get a plain-English read of 4
Turn the raw legal text into a practical explanation grounded in Hydro-Electric Corporation Regulations 2024.
4 Major power facility installed capacity
For the purposes of the definition of major power facility in section 8(4) of the Act –
(a) 40 megawatts is the limit fixed by regulation for the new generating plant located at the power station listed as item 23 of Schedule 1 to the Act and commonly known as Tarraleah; and
(b) 40 megawatts is the limit fixed by regulation for new generating plant that generates electricity by pumping water from Lake Cethana through a pipe or tunnel to an upper reservoir, in a process also known as pumped hydro energy storage; and
(c) 300 megawatts is the limit fixed by regulation for all other forms of new generating plant.
Displayed and numbered in accordance with the Rules Publication Act 1953.
Notified in the Gazette on 17 July 2024
These regulations are administered in the Department of State Growth.