This Plan sets the land‑use rules that apply to the mapped land in Gloucester: zoning, permitted/prohibited uses, consent thresholds, exempt and complying development, subdivision and lot‑size rules, heritage, flood and environmental controls, and site‑specific permissions in the Schedules. It repeals earlier local plans (cl 1.8) and applies to the Land Application Map (cl 1.3).
The Council is the consent authority (cl 1.6). Landowners and developers pay for assessments, consents and compliance; the Council has discretion to grant exceptions to standards (cl 4.6) and must keep records of those assessments.
This instrument is the local environmental plan (LEP) that sets the statutory land use framework for the Gloucester local government area. Mechanically it:
Declares its name and commencement (cl 1.1; cl 1.1AA) and identifies the land it applies to by reference to maps available on the NSW Planning Portal (cl 1.3; cl 1.7).
Repeals prior local environmental plans that applied only to the same land (cl 1.8) and saves pending development applications lodged before commencement (cl 1.8A).
Establishes the consent authority as the Council, subject to the Environmental Planning and Assessment Act 1979 (cl 1.6).
Sets the zoning regime (Part 2, cl 2.1-2.3), including a Land Use Table that specifies, for each zone, objectives, development that may be carried out without consent, development that requires consent, and prohibited development (cl 2.3).
Prescribes principal development standards (Part 4) such as minimum lot sizes (cl 4.1 and 4.1AA), flexibility for rural subdivision (cl 4.2), rules about erection of dwellings in rural/conservation zones (cl 4.2A), strata subdivision limits (cl 4.2B), height limits (cl 4.3), floor space ratios (cl 4.4), methods for calculating site area and floor space ratio and mechanisms to prevent “double dipping” (cl 4.5), and the rules for exceptions to development standards (cl 4.6).
Defines exempt and complying development processes and tests (Part 3, cl 3.1-3.3 and Schedules 2-3) and excludes environmentally sensitive areas from being eligible for exempt or complying development (cl 3.3).
Contains a wide set of local provisions addressing heritage (cl 5.10 and Schedule 5), flood planning (cl 5.21), aquaculture (cl 5.19 and Schedule 6), intensive livestock agriculture (cl 5.18), restrictions on canal estate development (cl 2.9), temporary uses and events (cl 2.8; cl 6.5), conversion of fire alarm monitoring (cl 5.8), and protections for licensed premises playing music (cl 5.20).
Current sections
Direct links to the current provisions in Gloucester Local Environmental Plan 2010.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2—relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Agricultural produce industries; Agriculture; Airports; Airstrips; Animal boarding or training establishments; Aquaculture; Backpackers’ accommodation; Bed and breakfast accommodation; Boat launching ramps; Camping grounds; Caravan parks; Cellar door premises; Cemeteries; Community facilities; Dual occupancies; Dwelling houses; Eco-tourist facilities; Educational establishments; Emergency services facilities; Extractive industries; Farm buildings; Farm stay accommodation; Flood mitigation works; Function centres; Home businesses; Home industries; Intensive livestock agriculture; Intensive plant agriculture; Kiosks; Open cut mining; Recreation areas; Recreation facilities (outdoor); Restaurants or cafes; Roadside stalls; Rural industries; Veterinary hospitals; Waste or resource transfer stations
4
Prohibited
4 Prohibited
4 Prohibited
Any development not specified in item 2 or 3
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note.
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Note.
If land, other than land specified in the Table to subclause (2), is required to be acquired under the owner-initiated acquisition provisions, the Minister for Planning is required to take action to enable the designation of the acquiring authority under this clause. Pending the designation of the acquiring authority for that land, the acquiring authority is to be the authority determined by order of the Minister for Planning (see section 21 of the Land Acquisition (Just Terms Compensation) Act 1991).
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
(1) Must not cover mechanical ventilation inlet or outlet vents.
(2) Advertising panels (building identification signs or business identification signs) must comply with the following—
(a) maximum area—1m2,
(b) only 1 per property,
(c) must be secure and stable.
(3) An A-frame sign on private land used in conjunction with an existing premises for which consent has been granted on land that is in Zone E1 or MU1, must comply with the following—
(a) only 1 per property,
(b) must not involve any live or recorded entertainment including music, broadcast programs, flashing lights or the like,
(c) area must immediately adjoin the premises and not obstruct access to the premises or to any adjacent premises,
(d) maximum display area (on each side)—500mm2,
(e) must be secure and stable,
(f) must not involve construction work,
(g) must be temporary and must be removed at the close of business.
(4) Fascia sign must comply with the following—
(a) must be attached to an existing fascia and fixed flush with the fascia,
(b) must not extend above or below the fascia or return end of the awning,
(c) must not be illuminated,
(d) only 1 per property.
(5) Flush wall sign must comply with the following—
(a) maximum area—1m2,
(b) must be securely fixed to an existing wall,
(c) maximum height—2.5m above ground level (existing),
(d) must not be illuminated,
(e) only 1 per property in Zone RU5 Village,
(f) maximum of 2 per property in all other zones,
(g) must contain only a reference to identify the subject premises or a description of the subject premises, activities or professional affiliations of the occupation conducted in the building to which the sign is attached.
(6) Pole or pylon sign must comply with the following—
(a) maximum height—6m,
(b) maximum area of advertising panel (per side)—2.5m2,
(c) only 1 per property,
(d) may only be in Zone E4 or E5,
(e) must be built in accordance with engineer’s certification for the structure and footings.
(7) Real estate sign must comply with the following—
(a) maximum area (per side)—
(i) single dwelling house—2.5m2, or
(ii) multi dwelling development of less than 10 dwelling houses—5m2, or
(iii) multi dwelling development of 10 or more dwelling houses—10m2, or
(iv) commercial building—5m2, or
(v) rural property—10m2, or
(vi) subdivision of less than 20 lots—10m2, or
(vii) subdivision of 20 lots or more—15m2,
(b) must not be erected until development approval for the building or subdivision has been granted,
(c) maximum return—200mm,
(d) must contain only a notice that the building or site to which it is fixed is for sale or for let,
(e) maximum of 1 sign for each property or subdivision stage,
(f) must not be illuminated,
(g) must be removed within 14 days of the sale or letting of the property or in the case of subdivisions, when 90% of lots are sold, or within 5 years, whichever occurs first,
(h) maximum height—3m,
(i) only 1 directional sign with a maximum area of 1m2 is allowed in Zone RU1 Primary Production to direct people to the site or for auction or inspection purposes,
(j) must not interfere with sight distances for vehicles approaching intersections.
(8) Temporary sign (including a sign announcing an authorised local event for religious, educational, cultural, political, social or recreational purposes) must comply with the following—
(a) maximum height—3m,
(b) sign must not be higher than building on which it is mounted,
(c) maximum area—3m2,
(d) must not be illuminated,
(e) any sponsor’s names or logos must be less prominent than the message,
(f) must not be displayed earlier than 28 days before an event,
(g) must not be displayed later than 14 days after an event.
(9) Top hamper sign (including a sign attached to the transom of a doorway or display window of a building) must comply with the following—
(a) must be fixed flush to the wall,
(b) must be securely fixed,
(c) must not extend below the head of the doorway or window to which it is attached,
(d) must not extend more than 200mm beyond any building alignment,
(e) must not be illuminated.
(10) Under awning sign must comply with the following—
(a) may only be located in Zone E1 or MU1,
(b) must not be less than 2.6m from the ground or footpath to the underside of the sign,
(c) maximum length—2.5m,
(d) only 1 per property,
(e) must be securely fixed to awning,
(f) must not project beyond the awning,
(g) must be erected horizontal to the ground,
(h) must be located more than 3m from another under awning sign.
(11) Window sign (including a sign displayed on a shop window) must comply with the following—
(a) may only be located in Zone E1, E4, E5 or MU1,
(b) must not cover more than 75% of shop window,
(c) must not be illuminated,
(d) must be located on ground level facade,
(e) only 1 per shop window.
sch.2-sec-oc.2
Change use of buildings from industry to light industry
sch.2-sec-oc.2 Change use of buildings from industry to light industry
Change use of buildings from industry to light industry
(1) Previous use must have been a lawful use.
(2) New use must not cause the contravention of any existing condition of the most recent development consent that applies to the premises relating to approved area and hours of operation.
(3) New use must be a permissible use in the zone.
(4) New use must not exceed 500m2 in total floor area.
(5) Building must have rear service access or access to off-street loading facilities.
(6) Curtilage of the building must not be used for storage or display purposes.
(7) New use must be consistent with any condition of development consent of the existing use relating to the following—
(a) the maintenance of landscaping,
(b) the parking of vehicles,
(c) the provision of space for the loading or unloading of goods or vehicles.
(8) New use must not result in any premises being used for potentially hazardous industry or offensive industries.
Maps: Am 2011 (397), cl 4; 2013 (381), cl 4; 2019 (375), cl 4. Entries discontinued from July 2021 when responsibility for map updates moved to Department of Planning, Industry and Environment.
sch.3-sec
Industrial buildings (other than light industrial buildings)—minor additions and ancillary structures
sch.3-sec Industrial buildings (other than light industrial buildings)—minor additions and ancillary structures
Industrial buildings (other than light industrial buildings)—minor additions and ancillary structures
(1) The total floor area of the building on the site involved must not be more than 2,000m2.
(2) Additional floor area created must not exceed 50m2 and must not be used for manufacturing, industrial or like activity.
(3) Additional external areas must not be occupied for the purpose of storage or manufacturing or any like activity.
(4) Must not involve a change of building use.
(5) Must comply with any existing development consent conditions.
(6) Setbacks must comply with the following—
(a) each part of the structure must have a front setback of not less than 10m,
(b) each part of the structure must have side and rear setbacks of not less than 3m.
(7) Building height and materials must comply with the following—
(a) the height of any walls must not be more than 7.5m, not including a parapet,
(b) parapets may extend a maximum of 1.2m above the intersection of the wall and the roof,
(c) roof pitch must not be more than 20,
(d) the site must not be cut or filled greater than 500mm,
(e) cladding and materials used in construction must be new, must have low reflective properties and must be factory pre-coloured,
(f) security fencing must not be greater than 3m in height.
(8) Drainage must comply with the following—
(a) all roof and surface water must be drained to the street and discharged to the consent authority’s nearest stormwater drainage system in accordance with an engineer’s design,
(b) the drainage system must be designed for a 10-year return period, with excess flows designed to flow overland to the street.
(9) Garbage and storage areas must be on site and behind the building line of the property.
(10) A landscaping strip of at least 3m (if reticulated sewer is provided) or 6m (if there is no sewer) to each street frontage must be planted and maintained with canopy trees and shrubs with a maximum width of 7m for the driveway.
(11) Must not change existing arrangements for access, parking spaces, loading and waste disposal.
(12) Stormwater must be disposed of by way of—
(a) a registered stormwater easement, or
(b) an inter-allotment stormwater pit located within the property boundary, or
(c) land within a wetland of international significance declared under the Ramsar Convention on Wetlands.
Note.
Nothing in this clause affects any requirement under an Act relating to land specified in this clause to obtain a licence or other authority under that Act for development of the land.
8
Flood liability
8 Flood liability
8 Flood liability
Must be designed or constructed on land so that it will not be inundated by the discharge of a 1:100 ARI (average recurrent interval) flood event.
9
Species selection
9 Species selection
9 Species selection
Species of fish or marine vegetation cultivated or kept must be consistent with the relevant aquaculture industry development plan (within the meaning of clause 5.19).
10
Pond design
10 Pond design
10 Pond design
(1) Must not require the construction of new ponds, water storages, dams or buildings.
(2) Must not be located on permanent watercourses, creeks, billabongs or isolated outreaches of creeks or rivers.
(3) Must be capable of preventing the escape of stock into natural waterbodies or wetlands.
11
Culture water
11 Culture water
11 Culture water
Must use freshwater.
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Gloucester Local Environmental Plan 2010.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for land in Gloucester in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to manage the resources of Gloucester,
(b) to protect rural lands, natural resources and assets of heritage significance,
(c) to manage development to benefit the community,
(d) to embrace and promote the principles of ecologically sustainable development, conservation of biological diversity and sustainable water management, and to recognise the cumulative impacts of climate change,
(e) to protect, enhance and provide for biological diversity, including native threatened species, populations and ecological communities, by long term management and by identifying and protecting habitat corridors and links throughout Gloucester,
(f) to encourage a mix of housing to meet the needs of the community,
Provides mechanisms for classification/reclassification of public land (cl 5.2 and Schedule 4), identifies the relevant State acquisition authority for certain reserved land (cl 5.1), and contains local controls tied to mapped instruments (Lot Size Map, Height of Buildings Map, Floor Space Ratio Map, Land Zoning Map, ANEF map for airport noise, Industrial Release Area Map).
Includes a suspension mechanism for private covenants, agreements and similar instruments where necessary to enable development under this Plan, subject to explicit exceptions (cl 1.9A).
The Plan expressly recognises the hierarchy and interaction with State environmental planning policies by making itself subject to SEPPs that prevail (cl 1.9(1)) and by cross-referencing a number of other Acts and State instruments in its operation (see, for example, cl 1.9A, cl 3.1, cl 5.10 and numerous notes and definitions).
Who pays, who decides and what changes in behaviour: the consent authority (the Council) decides on most development applications, developers and landowners pay the compliance and approval costs (including any required studies), State agencies may be designated acquiring authorities or must be consulted for certain matters (cl 5.1; cl 5.10). Landholders face constraints on permissible land uses by zone and by mapped numeric limits (lot size, height, FSR), and some private instruments that would otherwise prevent development may be displaced under clause 1.9A, subject to exceptions.
Main concepts
The Plan is organised around a set of interlocking regulatory concepts that determine what can be built where and how applications are assessed.
Zoning and Land Use Table. Zones are the primary spatial determinant (cl 2.1-2.3). The Land Use Table provides, for each zone, objectives and lists of uses permitted without consent, permitted with consent and prohibited uses (cl 2.3; Land Use Table). The Plan also permits additional uses on particular parcels via Schedule 1 (cl 2.5; Schedule 1).
Maps as operative instruments. The Plan repeatedly delegates numerical and spatial limits to maps: the Land Zoning Map, Lot Size Map, Height of Buildings Map, Floor Space Ratio Map and other maps (cl 1.3; cl 1.7; cl 4.1; cl 4.3; cl 4.4). Practically, instructions to check the maps are repeated; the maps themselves (not reproduced in the text) fix the majority of quantitative controls.
Development consent, exempt and complying development. The Plan divides development into those that require development consent, exempt development (Schedule 2 under cl 3.1), and complying development which may be certified under Schedule 3 (cl 3.2). Exempt/compliant pathways remain subject to building code requirements (cl 3.1(3)(a); cl 3.2(3)(b)) and are excluded from environmentally sensitive areas (cl 3.3).
Principal development standards and flexibility. Lot sizes, height limits and FSRs are set by maps and numerical rules (cl 4.1; cl 4.3; cl 4.4). Clause 4.6 provides a statutory pathway for exceptions to standards where sufficient planning grounds exist, while limiting that pathway in particular circumstances such as certain rural and conservation zones (cl 4.6(2)-(6)). The Plan also contains narrowly framed mechanisms that permit boundary adjustments (cl 4.1A), limited rural subdivision for primary production (cl 4.2), and replacement dwellings (cl 4.2A(4)(a)).
Environmental and heritage protection overlays. The Plan contains multiple protections and procedural requirements for heritage items and Aboriginal places (cl 5.10; Schedule 5) and for flood-prone land (cl 5.21). Exempt/compliant development is specifically barred from environmentally sensitive areas (cl 3.3).
Sector-specific regimes. The Plan contains detailed requirements for aquaculture (cl 5.19 and Schedule 6), intensive livestock agriculture (cl 5.18), eco-tourist facilities (cl 5.13), and a music/noise provision for licensed premises (cl 5.20). These provisions specify both substantive criteria (e.g., species selection, pond design, screening) and locational/operational limits (e.g., buffer distances in cl 5.18(4)).
Rights and limits concerning private instruments. Clause 1.9A permits non-application of private covenants and similar instruments to the extent necessary to enable development under the Plan, but it expressly excludes covenants imposed by the Council and a set of conservation and Crown instruments (cl 1.9A(1)-(2)). The clause also preserves rights of public authorities under registered instruments (cl 1.9A(3)).
Interaction with state rules and other approvals. The Plan is subject to SEPPs that prevail where expressed (cl 1.9(1)). The Plan repeatedly notes that exempt/compliant development remains subject to approvals and licences under other Acts (e.g., Local Government Act, Heritage Act, Fisheries Management Act) (see cl 3.1 notes, Schedule 2 note, cl 5.19 notes, cl 5.12).
Those concepts structure incentives: they allocate decision-making to Council for most matters (cl 1.6), create administrative shortcuts for small/low-impact work, impose requirements for studies and consultation for matters of heritage, flood risk and intensive uses, and provide narrowly framed flexibility mechanisms that require the consent authority to be satisfied on specified tests (for example, cl 4.6(3)).
Who it affects
The Plan’s direct and foreseeable stakeholder set can be read from the permissions, prohibitions and procedural requirements.
Landowners and developers. The Plan defines which land uses are lawfully permitted in which zones (Part 2, Land Use Table). Landowners contemplating subdivision, erection of dwellings, industrial or commercial development must check the Lot Size Map, Height of Buildings Map and Floor Space Ratio Map and seek development consent where the use is listed as “permitted with consent” or is not in the “permitted without consent” list (cl 2.3; cl 4.1; cl 4.3; cl 4.4).
The Council (consent authority). The Council is the decision-maker for most applications (cl 1.6). The Plan prescribes mandatory matters the consent authority must have regard to (e.g., cl 2.3(2), cl 5.10(4), cl 5.21(2)-(3)) and circumstances that trigger other consultations or conditions (e.g., cl 5.10(7)-(9)).
State agencies and Ministers. The Plan identifies acquiring authorities for certain reserved land for the purposes of owner-initiated acquisition (cl 5.1(2)). For the Industrial Release Area a Director-General certification is required as a condition precedent to subdivision in certain circumstances (cl 6.3(3)). Various State Acts are integrated into the Plan (see cl 1.9A, cl 5.12, cl 5.10), meaning agencies administering those Acts will be stakeholders where their statutory functions are engaged.
Crown land holders and public authorities. Clause 1.9A(3) preserves public authorities’ rights and interests under registered instruments, and cl 5.12 confirms that the Plan does not restrict the Crown’s use of existing Crown buildings under State SEPPs. Schedule 4 gives the Plan the mechanics for classification/reclassification of public land (cl 5.2).
Primary producers and agribusiness. The Plan contains a number of provisions affecting agriculture and related uses: RU1, RU3, RU5 and other rural zones (cl 2.1; Part 2 Land Use Table), controls for farm stay and farm gate premises (cl 5.24-5.25), and detailed rules for intensive livestock agriculture (cl 5.18). The Plan’s aims include promoting agriculture (cl 1.2(g)).
Aquaculture and oyster industry participants. Clause 5.19 and Schedule 6 set site and operational requirements for pond-based, tank-based and oyster aquaculture and permit certain oyster aquaculture activities without consent in priority oyster aquaculture areas (cl 5.19(6)).
Heritage owners and Aboriginal communities. The Plan lists heritage items and a heritage conservation area (Schedule 5) and makes special procedural and substantive requirements for development affecting heritage items, archaeological sites and Aboriginal places (cl 5.10(2)-(9)) including mandated notification and consideration windows (28 days) for the Heritage Council and local Aboriginal communities (cl 5.10(7)-(8)).
Operators of licensed premises and entertainment venues. Clause 5.20 limits the grounds the consent authority may use to refuse development applications for licensed premises on matters related to playing music and related entertainment features, while still permitting refusal where noise cannot be managed to an acceptable level (cl 5.20(1)-(2)).
Event organisers and users of public reserves and roads. The Plan allows events on public reserves and public roads without development consent for up to 52 days in any 12-month period, subject to other statutory approvals (cl 6.5(2)-(4)).
Mortgagees and covenant holders. Clause 1.9A changes the practical operation of restrictive covenants in some circumstances by suspending their application to enable development under the Plan, subject to enumerated exceptions and preservation of public authority registered interests (cl 1.9A(1)-(3)).
In short, the Plan affects any person or entity proposing to use land in Gloucester, public authorities with land interests, sectoral operators (agriculture, aquaculture, hospitality, industry) and community groups with heritage or environmental interests. The Plan allocates costs to applicants for compliance studies, to Council for administration and compliance work, and to State agencies where the Plan specifies certification or consultation.
Key duties and rights
The Plan creates explicit statutory duties for decision-makers and practical rights for applicants and landowners. Relevant duties and rights include the following.
Duties on the consent authority (Council)
Determine development applications in accordance with the Plan, having regard to zone objectives and the Land Use Table (cl 2.3(2); cl 1.6).
Ensure that temporary uses comply with the conditions in cl 2.8, including the 52-day cap and restoration obligations (cl 2.8(2)-(3)).
Require heritage assessment reports or heritage management documents for development affecting heritage items or heritage conservation areas where appropriate (cl 5.10(4)-(6)).
Notify and consider submissions from the Heritage Council and local Aboriginal communities in specified circumstances (cl 5.10(7)-(9)).
Not grant subdivision consent that would separate principal and secondary dwellings where that would result in lots smaller than the Lot Size Map minimum for that land (cl 2.6(2)).
Apply the flood planning tests before granting consent to development in the flood planning area and consider climate change impacts and evacuation capacity (cl 5.21(2)-(3)).
In the Industrial Release Area, refuse subdivision that creates lots smaller than the pre-LEP minimum unless the Director-General has certified satisfactory road provision arrangements (cl 6.3(3)).
Statutory rights for applicants and landowners
Right to rely on exempt development provisions in Schedule 2 where the development meets the Schedule and Part 3 requirements (cl 3.1(2)-(5); Schedule 2 note).
Right to obtain a complying development certificate for development listed in Schedule 3 and meeting the specified standards and conditions (cl 3.2(2)-(4); Schedule 3).
Right to seek consent for development that is permitted with consent in the Land Use Table (cl 2.3).
Where a proposed development contravenes a development standard, an applicant may seek consent under the exceptions clause (cl 4.6), but the application must demonstrate reasons and planning grounds and the consent authority must record its assessment (cl 4.6(3)-(4); note re EP&A Regulation).
Right to apply for boundary adjustment subdivision where clause 4.1A conditions are satisfied (cl 4.1A(3)).
Right to have certain existing development applications determined under the former instrument when an application was lodged before commencement (savings, cl 1.8A).
Procedural duties on applicants
Provide BASIX-related commitments, where relevant, and be aware that development standards arising from BASIX commitments cannot be contravened under the exceptions clause (cl 4.6(8)(b) note).
Where proposing contravention of a development standard, provide the required document under the Environmental Planning and Assessment Regulation explaining grounds for the contravention (cl 4.6(3) note).
Other duties and limits
Clause 1.9A imposes a duty to accept that some private covenants will not operate to prevent development authorised under the Plan, except covenants imposed by Council and enumerated conservation/Crown instruments (cl 1.9A(1)-(2)).
Exempt development cannot be carried out on land listed on the State Heritage Register or subject to an interim heritage order (cl 3.1(3)(d)).
Rights preserved by the Plan
The rights and interests of public authorities under registered instruments are preserved (cl 1.9A(3)).
The Plan retains State SEPP precedence where applicable (cl 1.9(1)).
These duties create compliance obligations on applicants to prepare studies (heritage, flood, environmental assessments, odour/noise assessments for intensive uses), and create administrative obligations on the Council to record assessments and to consult statutory agencies where the Plan requires it.
Penalties and enforcement
The instrument itself is an environmental planning instrument and contains no standalone schedule of pecuniary penalties. Enforcement in practice flows from the statutory framework within which the Plan operates and from the conditions it sets.
Mechanisms available and signalled in the Plan
Conditions on development consent: The Plan makes provisions for mandatory consent requirements (for example, demolition cl 2.7; subdivision cl 2.6; heritage cl 5.10) and permits the imposition of conditions (for example, covenants to prevent “double dipping” of floor space in cl 4.5(9)). Non-compliance with consent conditions ordinarily attracts enforcement under the Environmental Planning and Assessment Act and associated regulations (the Plan is subject to that Act, see cl 1.6 and multiple notes referring to the Act).
Administrative certification gates: Certain developments are subject to statutory certification or notification requirements (for example, Director-General certification for the Industrial Release Area under cl 6.3(3); consultation and notice requirements for heritage matters under cl 5.10(7)-(9)). Failure to obtain required certifications or to satisfy notice obligations will render a development application incomplete or non-compliant and expose the proponent to refusal or enforcement action.
Interaction with other statutory regimes: The Plan repeatedly notes that other approvals may be required under other Acts (Schedule 2 note; cl 6.5 note; cl 5.19 note). Offences, sanctions and enforcement regimes in those Acts (for example, the Heritage Act 1977, Local Government Act 1993, Fisheries Management Act, Rural Fires Act, Land Acquisition (Just Terms Compensation) Act) will be engaged where their functions are infringed. The Plan does not itself set those penalties but preserves those other statutory routes.
Record-keeping and review requirements: Clause 4.6(4) requires the consent authority to keep a record of its assessment where an exception to a development standard is relied on. This record-keeping can be relevant to subsequent enforcement or merits review.
What the Plan does not specify
The Plan contains no express monetary fines or criminal offences within its text. It does not set out the enforcement penalties that apply under the Environmental Planning and Assessment Act or other statutes; those consequences are determined by the parent Acts and regulations, which the Plan repeatedly references but does not reproduce.
Practical enforcement considerations for practitioners
Enforcement will typically involve Council’s statutory compliance branch and relevant State agencies depending on the subject matter (heritage, environmental protection, fisheries, Aboriginal heritage). Practitioners should assume that non-compliance with development consent conditions, operating outside a permitted use, or undertaking exempt/compliant development in an excluded environment (cl 3.3) may attract action under the Environmental Planning and Assessment Act and other applicable Acts referenced in the Plan.
The Plan’s own consultation and certification gates (e.g., cl 5.10(7)-(9) and cl 6.3(3)) can be used defensively: failure to obtain required advice, certification or to consider prescribed matters may be grounds for refusal and can expose applicants to enforcement risk if works proceed.
In short, enforcement and penalties are provided by the broader statutory framework into which this Plan fits. The Plan prescribes duties, consultation and certification steps which, if not followed, expose proponents to the usual enforcement mechanisms in environmental and development law.
How it interacts with other laws
The Plan is designed to operate within and alongside a suite of State Acts and State environmental planning policies (SEPPs). The text explicitly cross-references and defers to other laws in multiple ways.
Priority and precedence
The Plan is subject to any SEPP that expressly prevails over it (cl 1.9(1)); the Plan also lists potentially relevant State environmental planning policies and chapters in the Land Use Table notes (Land Use Table notes and cl 5.12). Practitioners must check applicable SEPPs in addition to the LEP.
Cross-referenced statutory regimes and required compliance
Environmental Planning and Assessment Act 1979: The Plan operates as an environmental planning instrument under that Act. Many procedural effects are framed in the language of the Act (cl 1.6 note; cl 1.8A note). The exceptions to development standards clause refers to the regulations under the Act which require an applicant to supply documents justifying contraventions (cl 4.6(3) note).
Local Government Act 1993: The Plan uses the Local Government Act for the classification of public land and for on-site effluent approval requirements for complying development on unsewered land (cl 5.2; cl 3.2(3)(c) note).
Crown Land Management Act 2016 and related Crown instruments: Clause 1.9A explicitly excludes from its suspension-of-covenants effect “any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016” (cl 1.9A(2)(b)). The Plan also references Crown grants and reservation mechanics in cl 5.2(5).
Heritage Act 1977: The Plan treats State-heritage listed items as excluded from exempt development and requires notice to the Heritage Council in certain circumstances (cl 3.1(3)(d); cl 5.10(7), (9)), preserving the statutory role of the Heritage Council.
Fisheries Management Act 1994 and Fisheries Management (Aquaculture) Regulation 2017: Aquaculture rules reference aquaculture industry development plans under the Fisheries Management Act (cl 5.19, Schedule 6) and use terms defined in the Fisheries Management Regulation (Schedule 6(6)).
Rural Fires Act 1997: The Plan allows bush fire hazard reduction work authorised under that Act to be carried out without development consent (cl 5.11).
Land Acquisition (Just Terms Compensation) Act 1991: Clause 5.1 uses that Act to identify relevant State acquisition authorities for particular reserved land and notes the operation of owner-initiated acquisition provisions.
BASIX and building standards: Clause 4.6(8)(b) prohibits use of the exceptions clause to contravene development standards that arise in connection with BASIX commitments, reflecting an interaction with State energy and water efficiency requirements.
Operational interfaces
Maps and data updates: The Plan requires maps to be kept and made available in accordance with Minister-approved arrangements (cl 1.7) and notes that responsibility for map updates changed in July 2021 (Schedule 3 note). Practitioners must therefore consult the Planning Portal and relevant Departmental documents for current maps and GIS data.
Overlapping approvals: The Plan flags that exempt development under this LEP is not exempt from licences or approvals required under other Acts (Schedule 2 note; cl 6.5 note). In practice, this means development may need approval under multiple regimes (e.g., Road Act for roadworks, Local Government Act for foreshore works or effluent systems, Fisheries Act for discharge to water).
Conservation and property law effects: Clause 1.9A alters the effect of private covenants in limited instances but preserves specified conservation instruments (cl 1.9A(2)). That interaction can change the private property legal landscape where the Plan authorises development that a private covenant otherwise prohibited.
Limits on the Plan’s reach
Clause 1.9A was approved by the Governor under s 3.16 of the Act before being made, emphasising a constitutional/statutory check on suspending private instruments (cl 1.9A(4)). The Plan cannot override the rights of public authorities under registered instruments (cl 1.9A(3)).
For practitioners this means: (a) always check applicable SEPPs and the parent Acts referenced in the Plan; (b) secure any licences or permits under other regimes in addition to development consent; (c) be aware that some private rights may be declaratively displaced by the Plan in narrow circumstances, but public authority rights and specified conservation instruments are preserved.
Amendment history
The Plan text as provided contains embedded amendment annotations. The instrument has been amended multiple times since its initial making; the text records a selection of amendment events attached to particular clauses. Key amendment points in the provided text include:
Clause 1.8A (savings dealing with pending development approvals) was amended in 2019: cl 1.8A: Am 2019 (621), Sch 5[1].
Clause 1.9A (suspension of covenants, agreements and instruments) has been amended at least twice: Ins 2011 (363), Sch 8[1]; subsequent amendments in 2019 (621), Sch 5[2]-[4].
The land use zones list at cl 2.1 was amended in 2022: cl 2.1: Am 2022 (832), Sch 1.6[1].
The Land Use Table has a sequence of amendments spanning 2011-2023: Land Use tbl: Am 2011 (363), Sch 8[2]-[15]; other amending years noted include 2013, 2017, 2019, 2022, 2023 (see listed citations in the Land Use Table heading).
Part 3 and Schedules: Schedule 2 and Schedule 3 carry amendment notations including 2011 and 2022 changes (sch 2: Am 2011 (363), Sch 8[24]; 2022 (832), Sch 1.6[8]-[11]; sch 3: Am 2011 (363), Sch 8[25]).
Clauses on subdivision and lot sizing: clause 4.1AA (minimum subdivision lot size for community title schemes) was inserted 2011 and amended 2022: cl 4.1AA Ins 2011 (363), Sch 8[16]; 2022 (832), Sch 1.6[3].
Clause 4.1A (boundary adjustments between lots in Zones RU1 and C3) was inserted in 2017 and amended 2022: cl 4.1A Ins 2017 (133), Sch 1[2]; 2022 (832), Sch 1.6[3][4].
Clause 4.2A (erection of dwelling houses on land in certain rural and conservation zones) was amended in 2022: cl 4.2A: Am 2022 (832), Sch 1.6[3][5][6].
Clause 4.2B (strata subdivisions in certain rural or conservation zones) shows amendments in 2011, 2022 and 2024: cl 4.2B: Am 2011 (363), Sch 8[17][18]; 2022 (832), Sch 1.6[3][5]; 2024 (42), Sch 1.19.
Clause 4.6 (exceptions to development standards) contains repeals and notes referencing the Environmental Planning and Assessment Regulation 2021 (cl 4.6(3) note). Clause 4.6 itself appears with amendments across the instrument history (the 2021 Regulation note is in the clause).
Clause 5.3 (development near zone boundaries) was amended in 2022: cl 5.3: Am 2022 (832), Sch 1.6[7].
Clause 5.4 (controls relating to miscellaneous permissible uses) has amendments in 2011 and 2018 (cl 5.4: Am 2011 (363), Sch 8[19][20]; 2018 (406), Sch 1.51[1][2]).
Clause 5.5 (secondary dwellings on land in a rural zone) was substituted in 2021: cl 5.5 Subst 2021 (714), Sch 11.15.
Part 6 local provisions: clause 6.1 was repealed in 2021 (cl 6.1: Rep 2021 (225), Sch 1). Clause 6.2 (airport noise) shows amendments in 2011 and 2017 (cl 6.2: Am 2011 (397), Sch 1[3]; 2017 (493), Sch 1.2[2]). Clause 6.3 (Industrial Release Area) was amended in 2019 and 2023 (cl 6.3: Am 2019 (621), Sch 1.3; 2023 (554), Sch 2.11). Clause 6.4 (earthworks) was inserted in 2011 (cl 6.4: Ins 2011 (363), Sch 8[23]). Clause 6.5 (events permitted without consent) was inserted in 2017 (cl 6.5: Ins 2017 (611), cl 4). Clause 6.7 (restrictions in RU1 and C3) shows insertions in 2017 and amendment in 2022 (cl 6.7: Ins 2017 (133), Sch 1[4]; 2022 (832), Sch 1.6[3][4]).
The amendment annotations in the instrument reveal regular targeted updates to implement State policy changes (for example, changes related to strata and community land, BASIX and flood guidance references), to refine local operational matters (industrial release area, aquaculture), and to keep schedules (maps, land use lists) current. Practitioners should always consult the consolidated instrument on the NSW legislation and Planning Portal for the complete, up-to-date amendment record and the current operative maps cited in the Plan.
Litigation history
The Plan text provided contains no judicial decisions, reported litigation or express references to case law. It lists no appeals or judicial interpretations and does not include any cases as authorities. The instrument does, however, embed procedural requirements and records (for example, cl 4.6(4) requires the consent authority to keep a record of its assessment when granting an exception to a development standard), which can be relevant in subsequent merits review or judicial review proceedings under the Environmental Planning and Assessment Act and associated judicial review jurisprudence, but those remedies and cases are not described in the Plan text itself.
What is absent in the instrument:
No statements summarising past legal challenges or appellate decisions relevant to the LEP.
No tribunal or court orders recorded in the Plan.
No references to litigation outcomes that have shaped interpretation of particular clauses.
Practically, for a practitioner wanting to assess the current legal risk around a proposal under the Plan, the absence of litigation references in the instrument means two things: (1) you must search external sources (Land and Environment Court decisions, administrative tribunal records) for case law on analogous LEP provisions or on statutory themes such as exceptions to standards, heritage controls, or flood planning; and (2) you must rely on the parent Acts and regulations (Environmental Planning and Assessment Act, applicable SEPPs, local statutes) to understand appeal and review mechanisms. The Plan itself provides the statutory framework, but not a litigation ledger.
Gotchas
The Plan contains several provisions and interactions that commonly trip up practitioners if not noticed. Below are specific “watch-outs,” tied to clauses and schedules.
Maps carry the controlling numeric limits, not the text. Height limits, floor space ratios and minimum lot sizes are set by the Height of Buildings Map, Floor Space Ratio Map and Lot Size Map, respectively (cl 4.3; cl 4.4; cl 4.1). The maps are not included in the text. Practitioners must check the Planning Portal maps before advising on permitted development envelopes.
Savings for pre-existing applications. If a DA was lodged before the Plan commenced and not finally determined, it must be determined as if this Plan had not commenced (cl 1.8A). That can mean different applicable controls for an in-train application versus a new application.
Suspension of covenants is limited and not universal. Clause 1.9A can displace private covenants to the extent necessary to enable development under the Plan, but it expressly excludes covenants imposed by the Council and a range of conservation/Crown instruments (cl 1.9A(2)(a)-(g)). It also preserves public authority rights under registered instruments (cl 1.9A(3)). Don’t assume a private covenant will be nullified; check the exceptions.
Exempt and complying development exclusions. Exempt or complying development must not be carried out in environmentally sensitive areas (cl 3.3). Exempt development is also barred on State heritage items or where an interim heritage order applies (cl 3.1(3)(d)). The Schedule 2 note reminds that other Acts/licences may still be required even if the LEP treats the work as exempt.
The exceptions clause has limits and record requirements. Clause 4.6 allows contravention of development standards where sufficient planning grounds exist, but: (a) it excludes contravention of certain development standards (cl 4.6(8)); (b) it disallows subdivision outcomes that create multiple undersized lots in specified zones (cl 4.6(6)); and (c) the consent authority must keep a record of its assessment (cl 4.6(4)). The Environmental Planning and Assessment Regulation requires applicants to provide a supporting document for contraventions (cl 4.6(3) note). These steps are mandatory.
Boundary adjustments may create undersized lots only in narrow circumstances. Clause 4.1A allows boundary adjustments between adjoining lots in RU1 and C3 where resulting lots are under minimum size, only if they do not create extra dwellings, do not increase conflict or reduce agricultural viability (cl 4.1A(3)(a)-(d)). Tests are fact-specific and require the consent authority to be satisfied.
Secondary dwellings and subdivision interplay. Subdivision consent must not be granted if it would result in principal and secondary dwellings being on separate lots unless the lots meet minimum sizes (cl 2.6(2)). The definition of secondary dwelling is in the Dictionary (cl 2.6 note). Secondary dwelling size controls vary by zone (cl 5.4(9); cl 5.5 for rural zones).
Heritage triggers require pre-consent notifications. For archaeological sites (other than State-heritage listed land) the Heritage Council must be notified and its response considered within 28 days (cl 5.10(7)). For Aboriginal places of heritage significance, the consent authority must investigate and notify local Aboriginal communities and consider responses within 28 days (cl 5.10(8)). Demolition of nominated State heritage items requires notice to the Heritage Council (cl 5.10(9)). Missing these steps can invalidate or delay consent.
Flood and climate change considerations are explicit and evolving. Clause 5.21 requires the consent authority to satisfy itself about compatibility with flood function, effect on flood behaviour and evacuation capacity, and to consider projected changes as a result of climate change (cl 5.21(2)-(3)). The clause references the “Considering Flooding in Land Use Planning Guideline” (2021) and the Flood Risk Management Manual (2023) (cl 5.21(4)-(5)), so up-to-date modelling and guideline compliance are likely required.
Music protections for licensed premises are limited, not absolute. Clause 5.20 prevents refusal on certain grounds related to music and entertainment features, but allows refusal where the consent authority is not satisfied that noise can be managed to an acceptable level (cl 5.20(2)). Applicants for licensed premises should still prepare and submit noise management strategies.
Aquaculture and wastewater constraints. Clause 5.19 and Schedule 6 set operational and locational limits, including the prohibition on freshwater discharge to natural waterbodies for intensive pond/tank aquaculture (except open flow-through systems) and screening outlets to prevent escapes (cl 5.19(4); Schedule 6(4)-(5)). Extensive pond-based aquaculture must not be inundated by a 1:100 ARI flood event (Schedule 6(8)). These are technical, non-negotiable requirements.
Events and temporary uses are capped. Temporary uses on any zone are capped at 52 days per year (cl 2.8(2)) and events on public reserves or roads are capped at 52 days per year without development consent (cl 6.5(2)). Sales offices for new housing estate areas are exempt from the day cap (cl 2.8(4)-(5)). Other approvals under separate Acts remain necessary (cl 6.5 note).
Industrial release area and roads certification. Subdivision in the Industrial Release Area cannot create lots smaller than pre-Plan minimums unless the Director-General has certified satisfactory road provision arrangements (cl 6.3(3)). This certification is a practical gating mechanism in subdivision approvals.
“Double-dipping” prevention for FSR. Clause 4.5 permits a consent condition requiring a covenant to prevent the creation of floor area on a restricted lot where equivalent floor area would otherwise be created on another lot by virtue of being included in a consolidated site (cl 4.5(9)-(10)). This is an important drafting tool for complex multi-lot developments.
Practitioners should run a compliance matrix against the Plan’s mapped controls, heritage lists in Schedule 5, the Schedules for exempt/compliant development, and the specified consultation/certification gates to avoid these gotchas.
How to comply
The Plan establishes a set of practical compliance steps and thresholds. The following checklist is derived from the operative clauses and Schedules and is intended for lawyers, planners, consultants and applicants preparing a proposal under the LEP.
Check the operative maps and zone provisions first
Confirm the land’s zoning on the Land Zoning Map and check the Lot Size Map, Height of Buildings Map and Floor Space Ratio Map on the NSW Planning Portal (cl 1.3; cl 1.7; cl 4.1; cl 4.3; cl 4.4).
Read the Land Use Table entries for the zone to see if your intended use is permitted without consent, permitted with consent or prohibited (cl 2.3; Land Use Table).
Determine pathway: exempt, complying or development consent
If the proposal could be exempt or complying, check Schedule 2 (exempt development) and Schedule 3 (complying development) against the tests in cl 3.1 and cl 3.2. Ensure compliance with the Building Code of Australia requirements and any other statutory approvals required under other Acts (cl 3.1(3)(a); cl 3.2(3)(b); Schedule 2 note).
Remember that exempt/compliant development is excluded from environmentally sensitive areas (cl 3.3). Check whether the land is on an excluded list (coastal waters, Ramsar sites, high biodiversity significance, etc.).
If development consent is required, prepare the application to satisfy mandatory tests
For subdivision, satisfy Lot Size Map minimums (cl 4.1) or rely on permitted exceptions (cl 4.1AA, 4.1A, 4.2) if relevant. For boundary adjustments in RU1/C3 use cl 4.1A tests.
For dwelling erection in RU1/C2/C3, apply cl 4.2A tests and confirm status as existing holding or lot size exceptions.
For height and FSR compliance, calculate site area and floor space in accordance with cl 4.5 and consider whether covenants to avoid double-dipping should be proposed as a consent condition (cl 4.5(9)-(10)).
If you propose to rely on the exceptions clause to contravene a development standard, prepare the required document and the environmental planning grounds as required under cl 4.6(3) and the Environmental Planning and Assessment Regulation (cl 4.6 note). Expect the consent authority to keep a record of its assessment (cl 4.6(4)).
Prepare and include specialist studies where the Plan requires them
Heritage: If the site is a heritage item or in a heritage conservation area (Schedule 5), prepare a heritage management document and consult with the Heritage Council as required (cl 5.10(4)-(6), (7), (9)). For Aboriginal places, include an adequate investigation and notify local Aboriginal communities and take account of responses within 28 days (cl 5.10(8)).
Flood risk: For development in the flood planning area, demonstrate compatibility with flood function and behaviour, safe evacuation, and climate change impacts in line with the Considering Flooding Guideline (cl 5.21(2)-(5)). Use the Flood Risk Management Manual guidance where relevant.
Intensive livestock and aquaculture: For intensive livestock agriculture consult cl 5.18 and use industry codes and DPI guidelines (cl 5.18(3)(g)-(h)). For pond/tank/oyster aquaculture use cl 5.19 and Schedule 6: species selection, pond design, discharge rules, screening (cl 5.19; Schedule 6(2)-(5)).
Manage ancillary approvals under other Acts and policies
Identify and obtain any necessary approvals under the Local Government Act (on-site effluent systems cl 3.2(3)(c)), the Roads Act, Crown land licences, Fisheries licences, the Heritage Act and any required environmental licences (Schedule 2 note; cl 6.5 note; cl 5.19 note).
Check SEPPs that may prevail (cl 1.9(1)). BASIX commitments cannot be overridden by cl 4.6 (cl 4.6(8)(b)).
Address private instruments and covenants early
If private covenants might obstruct an LEP-authorised development, review cl 1.9A carefully. It can suspend covenants to enable Plan-consistent development subject to exceptions (cl 1.9A(1)-(3)). If in doubt, obtain legal advice and consider negotiation or seeking express Council agreement where Council covenants are involved (cl 1.9A(2)(a) excludes Council-imposed covenants from suspension).
Draft consent conditions and safeguards
Use covenants where permitted to prevent “double-dipping” on FSR rights where multi-lot sites are involved (cl 4.5(9)-(10)).
For licensed premises and entertainment venues prepare noise management plans demonstrating that music/noise can be managed to an acceptable level because cl 5.20 removes many grounds for refusal related to music but permits refusal where noise cannot be managed (cl 5.20(1)-(2)).
Use the Plan’s event and temporary use provisions strategically
For short-term events on public land or roads, rely on cl 6.5 up to 52 days per annum, but ensure compliance with other statutory approvals (cl 6.5(2)-(4)). For temporary uses on private land the 52-day cap in cl 2.8 applies, and sales offices are an exception (cl 2.8(4)-(5)).
Watch procedural gates and consultation obligations
Heritage, Aboriginal heritage, and the Heritage Council/Aboriginal community notification windows (28 days) are non-trivial and can delay determination if not managed (cl 5.10(7)-(8)). Industrial Release Area subdivisions require Director-General certification where specified (cl 6.3(3)). Include these timeframes in project planning.
Keep records and anticipate evidentiary needs
For exceptions to development standards, the consent authority must keep a record (cl 4.6(4)). For complex applications prepare written submissions addressing the Plan’s mandatory tests and retain copies of all correspondence and certification.
Concluding practical note: the LEP is map-driven and cross-references numerous State instruments, so a compliance workflow that begins with map checks and proceeds through a statutory checklist (zoning, permitted use, mapped numeric limits, heritage/flood triggers, SEPP interactions, other-Act approvals) will reduce the risk of surprise refusals or delays. Where the Plan allows flexibility (boundary adjustments, exceptions to standards) do not assume these are routine; they require the consent authority to be satisfied on enumerated tests and in some instances to record their reasoning in writing (cl 4.1A; cl 4.6(3)-(4)).
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(1AA) (Repealed)
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note.
The maps adopted by this Plan are to be made available on the NSW Planning Portal. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the website of the Department of Planning and Environment.
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
Note.
The following local environmental plans are repealed under this provision—
Gloucester Local Environmental Plan 2000
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
1 Savings provision relating to pending development approvals
1 Savings provision relating to pending development approvals
1.8A Savings provision relating to pending development approvals
If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note.
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
cl 1.8A: Am 2019 (621), Sch 5[1].
1 Application of SEPPs
1 Application of SEPPs
1.9 Application of SEPPs
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
1 Suspension of covenants, agreements and instruments
1 Suspension of covenants, agreements and instruments
1.9A Suspension of covenants, agreements and instruments
(1) For the purpose of enabling development on land in any zone to be carried out in accordance with this Plan or with a consent granted under the Act, any agreement, covenant or other similar instrument that restricts the carrying out of that development does not apply to the extent necessary to serve that purpose.
(2) This clause does not apply—
(a) to a covenant imposed by the Council or that the Council requires to be imposed, or
(b) to any relevant instrument within the meaning of section 13.4 of the Crown Land Management Act 2016, or
(c) to any conservation agreement within the meaning of the National Parks and Wildlife Act 1974, or
(d) to any Trust agreement within the meaning of the Nature Conservation Trust Act 2001, or
(e) to any property vegetation plan within the meaning of the Native Vegetation Act 2003, or
(f) to any biobanking agreement within the meaning of Part 7A of the Threatened Species Conservation Act 1995, or
(g) to any planning agreement within the meaning of Subdivision 2 of Division 7.1 of the Act.
(3) This clause does not affect the rights or interests of any public authority under any registered instrument.
(4) Under section 3.16 of the Act, the Governor, before the making of this clause, approved of subclauses (1)–(3).
The land use zones under this Plan are as follows—
Rural Zones
RU1 Primary Production
RU3 Forestry
RU5 Village
Residential Zones
R2 Low Density Residential
R3 Medium Density Residential
R5 Large Lot Residential
Employment Zones
E1 Local Centre
E4 General Industrial
E5 Heavy Industrial
Mixed Use Zones
MU1 Mixed Use
Special Purpose Zones
SP1 Special Activities
SP2 Infrastructure
Recreation Zones
RE1 Public Recreation
RE2 Private Recreation
Conservation Zones
C1 National Parks and Nature Reserves
C2 Environmental Conservation
C3 Environmental Management
cl 2.1: Am 2022 (832), Sch 1.6[1].
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes.
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) In deciding whether to grant development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Notes.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note.
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2
1
If a subdivision is specified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
2
2
Part 6 of State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 provides that the strata subdivision of a building in certain circumstances is complying development.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note.
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), the temporary use of a dwelling as a sales office for a new release area or a new housing estate may exceed the maximum number of days specified in that subclause.
(5) Subclause (3) (d) does not apply to the temporary use of a dwelling as a sales office mentioned in subclause (4).
2 Canal estate development prohibited
2 Canal estate development prohibited
2.9 Canal estate development prohibited
(1) Canal estate development is prohibited on land