Future Made in Australia (Guarantee of Origin) Rules 2025
43Creation and variation of record—Act, par 84(1)(b)
Start here
Get a plain-English read of 43
Turn the raw legal text into a practical explanation grounded in Future Made in Australia (Guarantee of Origin) Rules 2025.
43 Creation and variation of record—Act, par 84(1)(b)
(1) The record must also include the following prescribed information:
(a) each energy source of the facility;
(b) the nameplate capacity of the facility;
(c) for a facility that is an energy storage system:
(i) the type of energy storage system; and
(ii) if the system has a direct supply relationship with an electricity generation system—the information mentioned in subsection (2);
(d) for a facility that is a hydro system:
(i) water flows for the system; and
(ii) if the system shares water flows with an interconnected system—details of the interconnected system; and
(iii) the difference in elevation, in metres, between the water intake level for the system and the turbine outlet; and
(iv) the reservoir size in gigalitres;
(e) each electricity input for the facility;
(f) if the owner or operator of a component recorded under paragraph 84(1)(a) of the Act is not the eligible registered person:
(i) the component; and
(ii) the owner and operator of the component.
(2) For subparagraph (1)(c)(ii), the following information must be included for the electricity generation system:
(a) the name and location of the system;
(b) if the system is a registered renewable electricity facility—the facility identification code;
(c) if the system is an accredited power station—the unique identification code allocated to the facility under section 16 of the REE Act;
(d) each eligible renewable energy source used by the system.