Future Made in Australia (Guarantee of Origin) Rules 2025
38Accredited power station registration—Act, s 78(3)(a) and (4)
Start here
Get a plain-English read of 38
Turn the raw legal text into a practical explanation grounded in Future Made in Australia (Guarantee of Origin) Rules 2025.
38 Accredited power station registration—Act, s 78(3)(a) and (4)
(1) The Regulator must have regard to the following prescribed matters:
(a) whether a suitability event has occurred in relation to:
(i) the applicant; and
(ii) if the applicant is not the nominated person for the accredited power station—the nominated person;
(b) if information provided as part of the application is consistent with the following information under the REE Act:
(i) information that relates to the applicant who is the nominated person for the accredited power station;
(ii) information that relates to the facility that is an accredited power station;
(c) if the accredited power station has a direct supply relationship with an energy storage system that is the subject of an application under section 75 (Application to register other facilities) of the Act:
(i) whether the direct supply relationship meets any requirement prescribed under section 35 (Direct supply relationship—Act, par 71(b)); and
(ii) whether the information provided in relation to the energy storage system is accurate;
(d) if the accredited power station includes an energy storage system as a component of the power station—whether the nameplate capacity of the energy storage system is of a size that would reduce the credibility of claims about the generation of electricity by the accredited power station, including if:
(i) the sum of the nameplate capacity of the accredited power station and the nameplate storage power of the energy storage system is more than 5 megawatts; or
(ii) the nameplate storage power of the energy storage system is more than 1 megawatt.
Example: The Regulator may impose a condition requiring that a component is used for measuring electricity consumption for another component, and further that the measurements are reported at a frequency stated in the condition.