Future Made in Australia (Guarantee of Origin) Rules 2025
37Other facility application—Act, pars 75(2)(b), (3)(h), (j) and (4)
Start here
Get a plain-English read of 37
Turn the raw legal text into a practical explanation grounded in Future Made in Australia (Guarantee of Origin) Rules 2025.
37 Other facility application—Act, pars 75(2)(b), (3)(h), (j) and (4)
(1) An application must include:
(a) the general application information mentioned in subsection (2); and
(b) for an application to register a facility that is an energy storage system—the general energy storage system information mentioned in subsection (3); and
(c) for an application to register an energy storage system that has a direct supply relationship with an electricity generation system—the information mentioned in subsection (4); and
(d) for an application to register a facility that is a hydro system—the general hydro system information mentioned in subsection (5); and
(e) for an application to register an energy storage system that is a pumped hydro system—the information mentioned in subsection (6); and
(f) for an application to register a small generation unit—the information mentioned in subsection (7).
General application information
(2) For paragraph (1)(a), the following information is required:
(b) the nameplate capacity of the facility;
(c) evidence that the facility meets the requirements (if any) prescribed by a measurement standard that apply to the facility;
(d) an electrical single line diagram for the facility;
(e) estimated life expectancy of the facility;
(f) for each component of the facility:
(i) evidence in relation to the matters mentioned in paragraph 79(2)(e) of the Act; and
(ii) if the component forms part of a registered renewable electricity facility or an accredited power station—details of the component, including:
(A) how the component is used by the renewable electricity facility and the facility that is the subject of the application; and
(B) whether the component consumes electricity;
(g) details of the electricity network connection for the facility;
(h) if the facility is subject to a related scheme—details of the scheme;
(i) whether the facility is located on land that is subject to an Aboriginal or Torres Strait Islander land rights law;
(j) if the facility is located on land that is subject to an Aboriginal or Torres Strait Islander land rights law:
(k) evidence in support of the application.
Note: See section 79 of the Act, for matters of which the Regulator must be satisfied before registering a facility.
General energy storage system information
(3) For paragraph (1)(b), the following information is required:
(a) the type of energy storage system;