54DContent of cost recovery declaration
Start here
Get a plain-English read of 54D
Turn the raw legal text into a practical explanation grounded in Electricity Infrastructure Investment Regulation 2021.
54D Content of cost recovery declaration
54D Content of cost recovery declaration
(1) A cost recovery declaration must—
(a) specify the network infrastructure of the eligible network operator to which the declaration applies, and
(b) specify whether, for the purposes of the National Electricity Rules, the network infrastructure forms part of—
(i) the transmission system, or
(ii) the distribution system, and
(c) classify, for the purposes of the National Electricity Rules—
(i) services provided by the eligible network operator in relation to the transmission system as transmission services, and
(ii) services provided by the eligible network operator in relation to the distribution system as distribution services, and
(d) further classify, for the purposes of the National Electricity Rules—
(i) the services classified as transmission services as—
(A) prescribed common transmission services, or
(B) prescribed TUOS services, and
(ii) the services classified as distribution services as direct control services that are standard control services, and
(e) specify a commencement date for the declaration, which must be a date that is—
(i) at the start of a regulatory control period for the eligible network operator, and
(ii) at least 2 years after the date on which the declaration is published in the Gazette.
(2) In this clause—
regulatory control period has the same meaning as in the National Electricity Rules.
cl 54D: Ins 2022 (786), Sch 1[2].