160 Freeway Corporation to give notice
(1) Before commencing Project construction work on licensed land, the Freeway Corporation must give notice of the proposed Project construction work in accordance with this section.
(2) The notice must—
(a) be published in the Government Gazette; and
(b) be given in writing to each Utility that the Freeway Corporation is aware owns or operates Utility infrastructure in the Extended Project area.
(3) The notice must require Utilities with Utility infrastructure in the Extended Project area to notify the Freeway Corporation in writing within 30 business days after the publication or giving of the notice (whichever is the later)—
(a) setting out the nature and location of the Utility infrastructure; and
(b) stating whether or not the Utility believes that the Utility infrastructure will be affected by the Project construction work.
(4) The Freeway Corporation is not required to give a notice to a Utility under subsection (2)(b) in relation to particular Utility infrastructure if an approved Utility agreement exists with that Utility in relation to that Utility infrastructure.