28C Provision of evidence about temporary ground anchor destressing
28C Provision of evidence about temporary ground anchor destressing
For the purposes of the Act, section 107(2)(d), a building practitioner for building work involving a temporary encroaching ground anchor must provide evidence to the Secretary that the ground anchor has been destressed—
(a) for development that does not require an occupation certificate—before the development is completed, or
(b) otherwise—before applying for the final occupation certificate for the development.
Maximum penalty—
(a) for a body corporate—200 penalty units, or
(b) otherwise—100 penalty units.