#### 28B Circumstances in which authority to install ground anchor must be provided
28B Circumstances in which authority to install ground anchor must be provided
> > (1) For the purposes of the Act, section 107(2)(d), a building practitioner must give the Secretary a ground anchor installation right document if the practitioner proposes to carry out building work involving an encroaching ground anchor.
>
> > (2) If the ground anchor is a temporary encroaching ground anchor the building practitioner must also give the Secretary a document detailing—
> >
> > > (a) the process for destressing the temporary encroaching ground anchor, and
> >
> > > (b) the time the destressing will occur.
>
> > (3) If the ground anchor is a removable encroaching ground anchor the building practitioner must also give the Secretary a document detailing—
> >
> > > (a) the process for the removal of the removable reinforcement tendon, and
> >
> > > (b) the time the removal will occur.
>
> > (4) The documents must be given—
> >
> > > (a) before the building work commences, and
> >
> > > (b) in the approved way.
>
> Maximum penalty for subclauses (1)–(3)—
>
> > (a) for a body corporate—200 penalty units, or
>
> > (b) otherwise—100 penalty units.
>
> **cl 28B:** Ins 2022 (62), Sch 1\[3\].