39A Site remediation for certain land
39A Site remediation for certain land
(1) This clause applies to the land to which item 51 of Schedule 8 applies.
(2) Site area remediation works are to be carried out on the land in accordance with the requirements of the Environmental Planning and Assessment Act 1979, State Environmental Planning Policy (Resilience and Hazards) 2021, Chapter 4 and the Contaminated Land Management Act 1997 at no cost to the council.
(3) All consents, permissions or other approvals required under the Environmental Planning and Assessment Act 1979, State Environmental Planning Policy (Resilience and Hazards) 2021, Chapter 4 and the Contaminated Land Management Act 1997 for the carrying out of the remediation works must be obtained.
(4) Prior to the commencement of the remediation works, a remediation action plan, a works program and a validation monitoring program in respect of the works must be submitted to the council.