Step 1: Identify affected engines and airframes. Confirm whether the engines fitted to the airframes in your fleet are the listed models: LTS101‑650B1, LTS101‑750B1, LTS101‑650C and LTS101‑750C (Applicability). Confirm whether the airframe ADs referenced in Note 2 (AD/JBK 117/9, AD/GBK 117/7 and AD/BELL 222/19) apply to your aircraft type, since Requirement 2 must be done "concurrent with" those ADs as applicable.
Step 2: Determine the binding Service Bulletins and revision levels. The AD requires the installations "in accordance with" the Honeywell SBs specified, and fixes the revisions to those "as in force on the commencement date of this AD." The SBs and revisions named in the AD are:
Operators must obtain the exact SB revision documents that were in force on 20 August 2021 and ensure work instructions and parts conform to those revisions.
Step 3: Plan sequencing and scheduling to meet timing constraints. Requirement 1 must be completed before further flight after the AD’s commencement date. Requirement 2 must be completed before further flight and "concurrent with" the identified airframe wiring ADs as applicable. That requires coordinating engine overhaul or shop visits with airframe maintenance windows and ensuring the airframe wiring AD work is carried out in the same maintenance event when the overspeed controller is installed.
Step 4: Procure parts and qualified maintenance resources. Source the improved turbine retention system components, improved rotor assembly, and the improved electronic overspeed controller per the SBs. Ensure maintenance is performed by appropriately authorised and certificated personnel or organisations competent to carry out SB work to the specified revisions. Verify that any electrical wiring work required under the airframe ADs will be done to the standards called for in those ADs.
Step 5: Execute installations per the SBs. Implement the SB‑prescribed procedures for mechanical and electrical installation. Because the AD fixes SB revisions, do not substitute procedures from later SB revisions without a separate authorisation. Ensure that the engine retention and rotor assembly installation and the overspeed controller are installed exactly as required by the named SB revision.
Step 6: Coordinate airframe wiring installations. For models where AD/JBK 117/9, AD/GBK 117/7 or AD/BELL 222/19 are applicable, ensure the wiring changes required for the overspeed controller are made during the same maintenance event, as required by Requirement 2.
Step 7: Establish and retain compliance evidence. The AD does not specify documentation formats; nevertheless, maintain contemporaneous maintenance records showing work performed, SB revision references, parts serial numbers, certifying signatures and dates. Retain these records to demonstrate that installations were completed "before further flight" after 20 August 2021.
Step 8: Verify conformity and return to service. Before authorising further flight, confirm that the work matches the SB revision instructions and that the electrical integration with the airframe complies with the referenced airframe ADs. Confirm the appropriate certifying engineer or maintenance organisation has completed all required signoffs consistent with normal airworthiness practice.
Step 9: Monitor for further ADs or amendments. The AD’s locking to particular SB revisions means later revisions will not be covered by this AD unless CASA issues an amendment or supplementary AD. Monitor CASA communications for any subsequent ADs or amendments to AD/LTS/13, or for explicit acceptance of later SB revisions.
Step 10: Be prepared to demonstrate concurrency where required. Because Requirement 2 requires the overspeed controller installation to be concurrent with certain airframe ADs, maintain scheduling records and cross‑referenced maintenance entries that show the airframe wiring AD work and overspeed controller installation occurred in the same maintenance event.
Practical checklist summary (from the AD text)
- Confirm engine model is one of the four listed models (Applicability).
- Obtain the exact Honeywell SBs and the specified revision that were "in force on the commencement date" (Requirement 1 and Requirement 2).
- Schedule installations so they are completed before further flight after 20 August 2021 (Compliance).
- Coordinate and perform airframe wiring AD work concurrently with the overspeed controller installation where those airframe ADs apply (Note 2).
- Retain full maintenance records and certification entries demonstrating compliance before further flight.
The AD supplies no alternative compliance route within its text. Any need to rely upon later SB revisions, non‑Honeywell parts, or different technical approaches will require separate authorisation from CASA, which is not provided by this AD text.