Identify affected aeroplanes. Confirm whether the aeroplane is an F28 Mark 0070 (Fokker 70) or F28 Mark 0100 (Fokker 100), as those are the models to which the AD applies (Applicability). If the aeroplane is outside those marks, the AD text does not apply.
Obtain the mandated technical document. Acquire Fokker Service Bulletin SBF100-22-050 dated 25 April 2006 and identify Section 3, "Accomplishment Instructions" (Requirement). If a later revision exists, confirm that the later revision has EASA approval, because the AD allows compliance using a later EASA-approved revision (Requirement).
Plan the modification within the compliance window. The AD is effective 31 August 2006 and requires compliance within 36 months (Compliance). Schedule the ADU installation and associated wiring changes to be completed no later than 31 August 2009. Build maintenance slots and parts procurement timelines around this fixed deadline.
Perform the installation per Section 3. Execute the ADU installation and associated wiring changes strictly in accordance with Section 3 of the referenced service bulletin (Requirement). The AD designates that Section 3 as the required means of compliance; adherence to its accomplishment instructions is the route to satisfying the AD.
Document the work. Record the completion of the modification in the aeroplane’s maintenance records, referencing the AD number (AD/F100/81), the service bulletin used (including revision and EASA approval if applicable), the work order, parts installed and the certifying maintenance release. The AD requires the modification but does not describe the recordkeeping format; maintain customary continuing airworthiness records that demonstrate compliance.
Verify the ADU functional change. After installation, confirm that the ADU functions as described in the service bulletin and AD background: operation of the control-wheel stabiliser trim switches should disconnect the autopilot (Background). Functional checks and ground tests required by Section 3 should be completed and logged.
Coordinate with the regulator for uncertainties. If there is any ambiguity in the accomplishment instructions, if a later service bulletin revision exists without clear EASA approval, or if you propose an alternative modification that you believe provides an equivalent level of safety, contact CASA for clarification and for guidance on approval. The AD text itself does not set out an alternative compliance process; therefore, operators should seek regulatory confirmation in writing when deviating from the prescribed accomplishment instructions.
Consider operational awareness and crew familiarisation. The system behaviour change will affect how stabiliser trim switch inputs interact with the autopilot. While the AD does not mandate training updates, operators should evaluate whether crew briefings, operating procedures or training syllabi require changes to reflect the ADU behaviour and to reduce the risk of confusion during high-workload events described in the Background.
Check related foreign authority actions. Review CAA-NL AD NL-2006-010 and EASA Approval 2006-0195 referenced in the AD Note (Requirement Note). Where the aeroplane operates internationally or is registered in a state other than Australia, confirm whether corresponding actions by the state of registry or EASA require parallel or additional compliance steps.
Ensure parts provenance and EASA approvals. Source ADU hardware and wiring in a way that conforms to the service bulletin parts list and any EASA approval requirements. If relying on a later revision of the service bulletin, ensure that the revision has the necessary EASA approval before using it to comply, as mandated in the AD (Requirement).
Schedule inspections and continuing airworthiness integration. After modification, integrate the ADU installation into the aircraft’s continuing airworthiness records, inspection intervals and any maintenance programmes affected by the wiring changes or ADU installation. Document compliance in a manner that will be straightforward to present to regulators or third parties.
Maintain traceability. Keep a clear audit trail: AD reference number, service bulletin revision and approval, dates of modification, certifying personnel, and test or functional check documentation. Although the AD does not specify the record format, traceability will be necessary to demonstrate compliance with the Directive’s mandatory modification.
If in doubt, engage the regulator early. The AD prescribes the corrective action and a deadline but does not enumerate relief mechanisms. If an operator foresees difficulties meeting the deadline, obtaining parts, or following the specific accomplishment instructions, approach CASA promptly for guidance and to obtain any necessary written approvals or instructions.
Signed and dated compliance evidence. When the work is complete, ensure that the modification certificate or release to service cites AD/F100/81 and references the service bulletin and revision used for compliance. This creates the documentary proof that the aeroplane complies with the AD as issued.