Compliance with AD/B767/228 requires a structured program of engineering, maintenance, and record-keeping. The following steps are based solely on the text of the Directive and its referenced service bulletin.
Step 1: Identify applicability. Determine whether each aircraft in the fleet is a Boeing 767-200 or 767-300 series aeroplane as identified in Boeing SB 767-30A0038, Revision 2. Obtain that service bulletin now. Verify the variable number (VN) from the aircraft records. If the VN is VN471, VN472, or VS704 through VS707, note the specific grandfathering limitations.
Step 2: Determine the original certification date. Locate the date of issue of the original certificate of airworthiness (if the aircraft was first certificated in Australia) or the original export certificate of airworthiness (if imported). This date is needed to calculate all compliance deadlines. If the records are missing, contact the manufacturer or CASA for assistance. Record this date in the aircraft log.
Step 3: Calculate the initial inspection deadline. For Requirement 1.a (FOD and contamination): take the later of 18 months after the original certification date and 90 days after 15 March 2007. For Requirement 1.b (heat damage, exposed foam, damaged tape): same later-of calculation. The deadlines may be the same if the certification date is recent. If the certification date is many years ago, the 90-day fallback will apply. Note that these are the deadlines for the first inspection; the inspection itself must be performed by that date, not planned for after.
Step 4: Perform the initial inspection. Have a qualified maintenance organisation perform a general visual inspection of both the forward and aft cargo compartments, in accordance with the Accomplishment Instructions of SB 767-30A0038, Revision 2. The inspection must cover both categories (FOD/contamination and tape condition). Document the date and findings. If any discrepancy is found, go to Step 5. If no discrepancy, note that repetitive inspections are required until the terminating action is done.
Step 5: Corrective action if discrepancies found. For any discrepancy identified in Step 4, do not return the aircraft to service until corrective action is completed in accordance with the same service bulletin. Note that the corrective action may include cleaning, removal of FOD, repairing tape, or other steps. The requirement says “applicable corrective action”, so follow the SB. Record all actions.
Step 6: Plan the terminating action (Requirement 3). Determine which of the two options will be used:
- Option (a): Replace all heater tapes on the potable water supply and grey water drain lines in the forward and aft cargo compartments (as applicable) with Adel Wiggins ribbon heaters.
- Option (b): Deactivate and remove any defective heater tape(s) from the same lines and wrap the drain lines with foam insulation.
Option (b) is only available for defective tape; if the existing tape is not defective, only Option (a) is permitted. The operator may need to judge whether existing tape is defective beyond the criteria used in the inspection. If in doubt, consult the manufacturer.
Step 7: Calculate the terminating action deadline. Use the formula from the AD:
- If, as of the effective date, the heater tape had not been replaced under ASB 767-30A0037 (May 2002) or SB 767-30A0037 Revision 1, then the deadline is the later of 42 months from the original certification date and 24 months after 15 March 2007.
- If the tape had been replaced under those earlier bulletins, the deadline is the later of 42 months after that replacement and 24 months after the effective date.
This requires accurate records of any prior replacement. The operator must also verify that the prior replacement was done in accordance with the stated bulletins, not other versions.
Step 8: Perform the terminating action. Carry out the chosen option in accordance with the service bulletin. Document the date and the work performed. Note that completing the terminating action ends the requirement for repetitive inspections under Requirements 1.a and 1.b. Mark the records accordingly.
Step 9: For aircraft with prior actions, verify grandfathering. If the aircraft has VN471, VN472, or VS704 through VS707, check that the prior inspection or corrective action was performed in the forward cargo compartment only (for these VNs) using the correct earlier bulletin version. If so, that portion of the AD is satisfied. If the prior action was on a different VN, it may be credited for both compartments. Ensure records are clear to avoid rework.
Step 10: Ongoing compliance after terminating action. If the terminating action is done, no further inspections under this AD are required. If the terminating action is deferred to a later date, continue the repetitive inspections at the prescribed hour intervals. Note that if the aircraft is sold or transferred, the new operator must be informed of the compliance status and whether the terminating action has been completed.
Step 11: Accepting later FAA-approved revisions. If, after the effective date, Boeing issues a later revision of SB 767-30A0038 and that revision is approved by the FAA as an AMOC to FAA AD 2007-02-18, the operator may use that revision for inspection or modification work. The operator must verify the FAA approval (checking FAA website or the bulletin itself). No separate CASA AMOC is needed. However, using a later revision does not change the deadlines in the AD; it only changes the method of compliance. The deadlines must still be met.
Step 12: Record keeping and audit readiness. Maintain all records of inspection dates, findings, corrective actions, and the terminating action. Retain a copy of the service bulletin used. Be prepared to show CASA that the aircraft is in compliance on request. Non-compliance can lead to grounding, so a proactive approach is essential.