Compliance requires a systematic approach. The following steps assume the operator wishes to continue using the heater. If the operator prefers to disable, see the alternative route.
Step 1: Determine applicability. Check whether the aircraft has a Kelly Aerospace B-Series combustion heater (models B1500, B2030, B2500, B3040, B3500, B4050, or B4500) and one of the listed fuel regulator shutoff valve part numbers (14D11, A14D11, B14D11, C14D11, 23D04, A23D04, B23D04, C23D04, P23D04). If the heater is present but the valve part number is unknown, determine it from the aircraft maintenance records or by physical inspection. If the aircraft model is not in the AD’s table, check whether the heater was installed via an STC or field approval; if so, the AD applies.
Step 2: Calculate the initial compliance deadline. Determine the total aircraft time in service (TIS) as at 7 July 2005. If a satisfactory inspection was performed within the preceding 75 hours TIS, the initial inspection is due within 25 hours TIS after 7 July. If not, the initial inspection is due within 25 hours TIS after 7 July. Record the deadline in hours TIS (which may be a future calendar date depending on utilisation). Note that if the aircraft is not flown for long periods, the 12-month calendar limit will apply to subsequent inspections but not to the initial one (which is solely hour-limited).
Step 3: Obtain the required technical data. The primary reference is KAPS Service Bulletin No. A-107A dated 06 September 2002 (or a later FAA approved revision). Also obtain Piper Vendor Service Publication VSP-150 dated 31 January 2003 (or later revision) if the aircraft is a Piper PA-31-350. The AD also mentions “the applicable maintenance manuals” for the replacement procedure. Ensure you have the current versions.
Step 4: Perform the inspection. Use either a visual inspection for fuel stains or a pressure test, as described in the Service Bulletin. The source does not specify which method is mandatory; both are permitted. Choose based on available equipment and best engineering judgment. A pressure test may be more reliable but requires special equipment. The choice affects cost and time.
Step 5: Document the result. If no leak or stain is found, make an entry in the aircraft log book with the date of inspection. The entry should reference the AD number (AD/AIRCON/13 Amdt 3) and the Service Bulletin used. If a leak or stain is found, proceed to Step 6; do not fly the aircraft until the valve is replaced.
Step 6: Replace leaking valve. Obtain a new valve of the correct part number with a manufacturer’s date code of 02/02 or later. For Piper PA-31-350, use P/N P23D04-7.5. Install per the Service Bulletin and the applicable maintenance manual. After replacement, ensure the old valve is properly disposed of and cannot be reused. Make a log book entry recording the replacement.
Step 7: Schedule future inspections. Set a reminder for the next inspection at 100 hours TIS or 12 months after the date of the last inspection, whichever is sooner. The repetitive interval applies from each inspection. The AD does not allow stretching the interval even if no problems have been found.
Alternative route: Disable the heater. If the operator chooses to disable, perform the following steps before the next required inspection (i.e., before the deadline calculated in Step 2): (i) Cap the fuel supply line upstream of the fuel regulator and shutoff valve. (ii) Disconnect the electrical power and ensure connections are secured to reduce spark risk. (iii) Inspect and test to confirm the heater system is disabled. (iv) Ensure no other aircraft system is affected. (v) Ensure there are no fuel leaks. (vi) Fabricate a placard reading “System Inoperative” and install it at the heater control valve within the pilot’s clear view. Also ensure that the disablement is permissible under any MEL or CAR 37 provisions. Record the disablement in the aircraft log book, referencing the AD. Then, if in the future the operator wishes to use the heater again, they must perform the full inspection and replacement routine of requirements 1 through 4, including possibly replacing the old valve with a post-02/02 part.