Follow the AIRBUS Service Bulletin named in the AD: The AD mandates corrective actions “in accordance with AIRBUS Service Bulletin (SB) A330‑26‑3043.2.” To comply with the AD’s technical requirement, maintenance personnel must obtain and follow that SB for the precise inspection method, any disassembly, acceptance criteria for lug orientation, and corrective procedures if incorrect orientation is found. The SB will also specify report formats and required technical data for any corrective work; the AD ties compliance to that SB.
Perform the general visual inspection on both engines within 900 flight hours: The AD requires a one‑time general visual inspection of the fire‑extinguishing bottle nut assembly of both engines. This inspection must be completed within 900 flight hours after the AD’s effective date (18 December 2008), unless the inspection has already been accomplished. Where the inspection was previously performed, operators should retain documentary proof to demonstrate they met the AD before the effective date.
Report the inspection results to AIRBUS within 30 days: Regardless of outcome, the AD requires the results be reported to AIRBUS within 30 days of the inspection’s accomplishment date. Operators should follow the reporting procedure set out in the AIRBUS SB or in OEM guidance to ensure the report reaches the correct Airbus inbox and to retain proof of submission. Include serial numbers, part numbers (P/N A2621005000200), inspection dates, findings and any corrective actions taken.
If incorrect lug orientation is found, apply corrective action per the SB: The AD directs that any required corrective actions be applied in accordance with AIRBUS SB A330‑26‑3043.2. That will likely include reorientation or replacement of the assembly nut and verification of connection integrity. Do not improvise technical fixes outside the SB’s instructions unless authorised by the regulator or OEM through an approved deviation process.
Document and retain evidence of compliance: While the AD does not specify internal record‑keeping durations, operators should record the inspection and any corrective action in the aircraft’s maintenance log and retain supporting documentation (inspection report, parts replaced, work orders, photos if helpful). Keep copies of the report submitted to AIRBUS and any acknowledgements. These records serve as evidence of compliance during audits or any follow‑up by CASA.
Check parts traceability beyond listed serial numbers: Given the manufacturing origin of the defect, compliance for listed serial numbers does not preclude the same part being fitted elsewhere. Operators should review parts manifestation and maintenance history to confirm whether P/N A2621005000200 is present on other airframes. If that is the case, consider voluntarily performing the inspection on other airframes or seek advice from Airbus/CASA on whether additional action is required.
Coordinate with maintenance scheduling to meet flight‑hour deadline: Integrate the inspection into planned maintenance to ensure completion within the 900‑flight‑hour window. For high‑utilisation aircraft, this may require immediate scheduling in the next available maintenance opportunity. If operators rely on third‑party maintenance providers, confirm scope and timing in work orders.
Confirm reporting details and communication channels with AIRBUS: The AD obliges reporting to AIRBUS. Operators should confirm the exact reporting address or portal referenced by the SB or by Airbus communications, include required technical details (P/N, serial numbers, inspection date, findings, corrective action), and keep a record of what was sent.
Prepare for corrective parts procurement: If corrective action requires replacement nuts, arrange procurement of approved parts in accordance with the SB and standard parts procurement rules. Verify part numbers and traceability to avoid circular compliance issues.
Retain readiness for regulator queries: Even though the AD does not specify penalties, CASA issued the AD; CASA may enquire about compliance as part of oversight activities. Be prepared to present inspection and reporting evidence to CASA on request.