Abt Railway Development Act 1999
19Excavations
Start here
Get a plain-English read of 19
Turn the raw legal text into a practical explanation grounded in Abt Railway Development Act 1999.
19 Excavations
(1) Any person who proposes to undertake any excavation of land within 5 metres of any railway track that is part of the railway must notify the Ministerial Corporation within 48 hours before doing the excavation.
Penalty: Fine not exceeding 50 penalty units.
(2) The Ministerial Corporation may give any directions it considers necessary in relation to the excavation.
(3) A person must comply with any directions of the Ministerial Corporation in relation to the excavation of land.
Penalty: Fine not exceeding 50 penalty units.