[2025] SACAT 93
General information, not legal advice.
SA Civil and Administrative Tribunal
2025-09-30
Member Lazarevich
Original judgment source is linked above.
Wetherby & Anor v Commissioner of Highways [2025] SACAT 93
The applicants sought review of a decision of the Commissioner for Highways to acquire a portion of their property pursuant to the Land Acquisition Act 1969 (LA Act). The applicants' land was acquired for the purpose of constructing a northbound overtaking lane on Main South Road to the north of Wirrina Cove.
The applicants submitted that the acquisition of their land was unnecessary because the Commissioner owns land on the other side of the road. They also argued that there are significant trees on their property which will be affected by the acquisition, as well as their livestock, water supply and native fauna on the property. They also submitted that there is historic stonework on their property which would be affected by the acquisition.
The respondent submitted that it was necessary to acquire a portion of the applicants' land for the purpose of carrying out the installation of the Northbound Overtaking Lane. The Commissioner determined the alignment of the lane through extensive technical, social, economic, deliverability and economic assessments.
Administrative Review - Land Acquisition Act 1969 - Review of a decision of the Commissioner of Highways to refuse a request to not proceed with the acquisition of the subject land
Administrative tribunals - Procedure - Statutory Powers - Confidentiality orders
South Australian Civil & Administrative Tribunal Act 2013 ss 34, 37, 60
South Australian Civil and Administrative Tribunal Rules 2014 r 28
Physiotherapy Board of Australia v Rivett [2023] SACAT 48
Re Pochi and Minister for Immigration and Ethnic Affairs [1979] AATA 64; (1979) 26 ALR 247
Salia Property Pty Ltd v Commissioner of Highways [2011] SASC 106
(1) A person who has an interest in the subject land may, within 30 days after notice of intention to acquire the land is given, require the Authority, by written notice -
(a) to give an explanation of the reasons for acquisition of the land; and
(b) to provide reasonable details of any statutory scheme in accordance with which the land is to be acquired.
...
12 - Right to object > > (1) A person who has an interest in the subject land may within 30 days after notice of intention to acquire the land is given or, if an explanation of the reasons for the acquisition is required, within 30 days after the explanation was provided, by written notice -
(a) request the Authority not to proceed with the acquisition of the subject land; or
(b) request an alteration in the boundaries of the subject land; or
(c) request that a particular part of the subject land be not acquired, or that further land be acquired.
(2) For the purposes of this section -
(a) the registered representative of claimants to, or holders of, native title in land is taken to have an interest in that land; and
(b) the relevant representative Aboriginal body is taken to have an interest in the land if -
(i) the land is native title land; and
(ii) there is no native title declaration for the land; and
(iii) -
(A) there are no registered representatives of claimants to native title in the land; or
(B) an Aboriginal group that claims to hold native title in the land and for which there is no registered representative has, in accordance with the regulations, authorised the representative Aboriginal body to act on its behalf.
(3) A request may be made under subsection (1) -
(aa) on the ground that acquisition of the land or a particular part of the land is not necessary for the purposes of carrying out the undertaking to which the acquisition relates; or
(a) on the ground that acquisition of the land or carrying out the purposes for which the acquisition is proposed would -
(i) seriously impair an area of scenic beauty; or
(ii) destroy, damage or interfere with an Aboriginal site within the meaning of the Aboriginal Heritage Act 1988; or
(iii) destroy or impair a site of architectural, historic or scientific interest; or
(iv) prejudice the conservation of flora or fauna that should be conserved in the public interest; or
(v) prejudice some other public interest; or
(b) on some other ground stated in the request.
(4) The Authority must consider any request made to it under this section and must, within 14 days after receipt of the request, serve notice in writing on the person by whom the request was made, indicating whether it accedes to, or refuses, the request.
12A - Right of review > > (1) A person who makes a request under section 12 in relation to a proposed acquisition which is refused by the Authority under that section may apply to the Tribunal under section 34 of the South Australian Civil and Administrative Tribunal Act 2013 for a review of the Authority's decision. > > (2) An application for review under subsection (1) must be made within 7 days of service on the person of the notice of the Authority's decision to refuse. > > (3) The Tribunal must complete its proceedings on a review within 21 days of the application being made under subsection (1). > > (4) The merits or otherwise of the undertaking to which the proposed acquisition relates cannot be called into question in a review under this section. > > (5) Section 71 of the South Australian Civil and Administrative Tribunal Act 2013 does not apply to or in relation to a decision of the Tribunal under this section. > > (6) In this section - > > "Tribunal" means the South Australian Civil and Administrative Tribunal established under the South Australian Civil and Administrative Tribunal Act 2013.
[45] ... Section 11 is a significant provision. It entitles a person with an interest in the land in question to acquire information that might help the person express a requirement that the authority reconsider its decision as a result of a request under s 12(1) of the Act. However, the entitlement to make that request does not depend upon the relevant person making a requirement under s 11 of the Act, although doing so will extend the time for making a request under s 12(1) of the Act. If the request under s 12 does not result in any change by the authority, the relevant person can then require the minister to review the decision, by application in writing under s 12 A. The entitlement to make that request does not depend upon the making of a requirement under s 11(1) of the Act. Accordingly, while the discharge of the authority's obligation under s 11 may assist a person who wishes to make a request under s 12(1), that is as far as it goes. The making of a requirement under s 11(1) of the Act is not a precondition to the exercise, by the relevant person, of the entitlements conferred by ss 12 and 12A. This conclusion is not undermined by the opening words of s 16(1): "Subject to this Act the Authority may". Those words should not be treated as making each provision of the Act an essential preliminary to the exercise of the power under s 16. These words do no more than reflect the fact that there are various provisions of the Act that bear, in one way or another, on the procedure by which the authority may put itself in a position to utilise s 16. > > [46] The judge also considered the purpose of the Act. The focus of the Act is on the acquisition of land on just terms: s 3. A person with an interest in the relevant land has no right to challenge the decision to acquire the land. Such a person can do no more than require the authority to reconsider its decision, and require the minister to review the decision. Information provided under s 11 does not provide a basis for a challenge to the decision to acquire land.
The acquisition, by agreement or compulsory process, of all the land identified in Attachment 3 and any interest in the land to accommodate the Main South Road Overtaking Lane Project, for the third overtaking lane at Wirrina Cove between Second Valley and Normanville (northbound).
32.1 The acquisition of the land is 'not necessary' because the Commissioner of Highways owns land on the other side of the road.
32.2 There are two significant trees on the opposite side of the road which will be affected by the development anyway, and on the applicants' side there are 11 trees that might be affected.
32.4 The proposed works will affect their water supply.
32.5 There is a culvert which directs water into the applicants' northern most dam which contains historic stonework.
34.1 It is necessary to acquire the land for roadworks that are necessary for the purposes of carrying out the installation of the Northbound Overtaking Lane, namely the extension of two existing culverts and their associated fill batters, and the extension of a small section of the existing cut batter.
34.2 The alignment of the Northbound Overtaking Lane was determined through extensive technical, social economic, deliverability and ecological assessments.
34.3 All reasonable endeavours were made to minimise the extent of land being required.
34.4 The location of photos that the applicants relied upon to say there was an area of scenic beauty depict features that are not situated within the land being sought to be acquired. The works would not cause serious impairment to the pictured site.
34.5 The existing culvert with the stone features is not on the applicants' property but on an existing road reserve. The Commissioner undertook a heritage assessment. The heritage assessment did not reveal any listed sites on the applicants' property or neighbouring properties.
34.6 The trees depicted in the applicants' photos would not be affected. An environmental assessment was done in relation to the effect on flora and fauna. Significant effort was done to minimise the impact on flora and fauna, with emphasis on avoiding vegetation with high biodiversity scores. Regrettably, there would be some impact on vegetation on the applicants' land, but the design avoids a significant number of planted trees on the western side of South Road and the greater public interest in preserving vegetation with the highest biodiversity value.
34.7 Safety considerations were taken into account. The design of the development takes into account the compliance with principles in the Austroads Guide to Road Design and the proposed alignment was the result of extensive consideration by expert road engineers. The public interest is served by the proposed acquisition.
34.8 All access points to the applicants' land remain unobstructed.
34.9 There will be no detrimental impact on the applicants' water supply. Ancillary works would be done in relation to an existing culvert which will see a resulting increase in waterflow to the northernmost dam.
34.10 The applicants will be compensated for the acquisition of the land.
34.11 The assertion of lack of maintenance on Main South Road and dissatisfaction with the extent of consultation are not a reason to disallow the objection.
34.12 There was extensive public consultation. The applicants' preferred location for an overtaking lane between Finnis Vale Drive and Paradise Drive was not a preferred location.
34.13 The request that the acquisition not proceed is refused.
35.2 An affidavit of Dr Kew (one of the applicants) dated 20 September 2025 which sets out the arguments referred to earlier in these reasons.
35.3 A Statement of Reasons of the Commissioner. This included:
35.3.1 A description of Main South Road as an important freight route connecting heavy vehicles, commuters, and tourists to destinations along the Fleurieu Peninsula.
35.3.2 Between Myponga and Cape Jervis the road is typically characterised by a narrow road corridor and curvilinear geometry landing. The nature and geometry of the road increases safety risk risks for road users and a lack of present overtaking opportunities is resulting in unreliable travelling times, causing drivers to make unsafe decisions.
35.3.3 A number of initiatives were identified for the purpose of improving road safety along Main South Road and to build capacity for future traffic growth. It was identified that a northbound overtaking lane between Normanville and Second Valley North of Paradise Drive, Wirrina Cove was required. There are no northbound overtaking lanes within this particular region of Main South Road. Furthermore, an overtaking lane at this location would provide an opportunity to safely overtake vehicles towing boats and caravans getting back to Adelaide from Wirrina Cove.
35.3.4 The Northbound Overtaking Lane is part of the Main South Road Overtaking Lane Project and will complement the other safety initiatives.
35.3.5 It is necessary to acquire a portion of the applicants' land for the purpose of constructing the Northbound Overtaking Lane.
35.3.6 The Northbound Overtaking Lane will be constructed primarily within the existing road reserve.
35.3.7 The works to be undertaken on the portion of the applicants' property to be acquired are in connection with the construction of that lane and are limited to the extension of existing drainage culverts and associated fill batter slopes and the extension of a small section of an existing cut batter slope.
35.3.8 The purpose of these works is to ensure that these stability and safety of the batter slopes is maintained. There are also existing culverts running across the road at natural water channels that drain water from the road which will be retained. The culverts will be extended to ensure water flows are not impacted around these fill areas. Accordingly, the partial acquisition of the property is required in order to modify existing batter slopes and drain culverts which are an integral part of the road infrastructure.
35.3.9 Approval was given by the Minister for Infrastructure and Transport to acquire a portion of the property on 1 October 2024. In accordance with s 10 of the LA Act the applicants were sent a Notice of Intention to Acquire Land (NOI). The NOI defined the interest in land to be acquired to be an unencumbered estate in fee simple in a portion of the land comprised in the certificate of title for the applicants' property. The NOI was served on the applicants on 14 March 2025.
35.3.10 On 28 March 2025 the applicants requested an explanation for the reason for the acquisition and details of the statutory scheme. The delegate for the Commissioner responded to this request on 30 July 2025.
35.3.11 By letter of 27 August 2025 the applicants objected to the proposed partial acquisition of the property.
35.3.12 The location and design of the Northbound Overtaking Lane was determined through extensive technical, socio-economic, and ecological assessments. The process to identify an appropriate site for an overtaking lane is a conflictual process involving advice from requisite subject matter experts. Multiple criteria are required to be taken into account. Furthermore, the Northbound Overtaking Lane must comply with the requirements of the Austroads Guide to Road Design that is an in-depth technical process that informs the recommendation made to the Commissioner.
35.3.13 Due consideration was given by the Commissioner to the applicants' request that the partial acquisition of their property not proceed. However, for the reason stated in the letter of 9 September 2025 the Commissioner determined to refuse that request and proceed with the acquisition.
35.4 The recommendation by the Commissioner to the Minister to approve the acquisition of land (approved 1 October 2024).
35.6 A composite of photographs prepared by the applicants showing a long section of road including where the applicants say a better place for the overtaking lane would be.
35.10 The applicants' objection letter of 27 August 2025 and the reviewable decision.
35.12 Full Planning Study Report (various revisions). The document is extensive. It includes material relating to the project background, data about traffic volumes, data about speed and crashes, information about flora and fauna, historic heritage and aboriginal heritage; an explanation of problems and solutions, plans, concept designs, discussion about a long list of options and the refinement into a short list, including the criteria adopted, information about approvals, information about environmental and heritage impact assessments, cost benefit analysis, details on curve widenings and options, stakeholder engagement information, and recommendations. The heritage and assessment report includes detailed information on species of fauna and flora, a view that the impact would be insignificant due to the limited extension of clearance, and the mitigation measures to be put in place.
35.13 A Native Vegetation Clearance Report. The document is lengthy. The option chosen was selected because there would be a smaller impact on vegetation relative to other options, and, additionally, it would avoid the clearance of a threatened flora species.
35.14 An affidavit of an employee of the Commissioner, Michael Rander.
Wetherby & Anor
Commissioner of Highways [2025] SACAT 93
(1979) 26 ALR 247