485 Based on the calculation set out above, Mr Makin concluded that $29,200.00, exclusive of GST, of the total cost of Preliminaries was time-related and therefore relevant to a calculation of delay costs. He then assumed an 11-day working fortnight (which I found above to be appropriate). The contract period was for 30 weeks. Mr Makin divided $29,200.00 by 30 and further divided the result by 5.5 to arrive at a daily rate for time-related preliminaries of $176.97, exclusive of GST.
486 Mr Makin next referred to Attachment 6 of the Contract, which was headed "Rates for Supervision" and which contained the following daily rates, exclusive of GST:
Project manager $675.00
Leading hand $450.00
487 Based on the addition of these two rates, for supervision he allowed a daily time-related cost of $1,125.00, exclusive of GST.
488 From the above, Mr Makin concluded that the total time-related costs for the project were $1,301.97 per day, exclusive of GST.
489 Mr Makin then applied this rate to a delay period of 228 days (the period assessed by Mr Ash) to arrive at a total delay cost of $296,849.16, exclusive of GST.
Illawarra's Submission
490 Illawarra's submission was:
"116 Illawarra accepts that temporary site sub-boards, fax and telephone lines, toilet and site facilities, telephone and fax rental, and insurances are time-related but submits that miscellaneous plant hire, temporary lighting, telephone and fax charges, mobile telephone charges, first aid kit, temporary protection and hoarding materials are not time-related and ought not to be included. Illawarra also submits that there is no evidence that Walton supplied fax or telephone lines, toilets or other site facilities.
117 The contract allowance for the items which Illawarra accepts are time-related and were provided (excluding telephone and fax rental, for which no break-down is provided) is $13,600. This translates to a daily rate for Preliminaries of $82.42. Illawarra submits that this rate for Preliminaries should be used in lieu of the rate calculated by Mr Makin.
118 Illawarra agrees that the rates for the project manager and leading hand obtained from the schedule of rates are appropriate where the project manager and leading hand were engaged in additional work but submits that they are not appropriate for periods, if any, during which these resources were idle. Where any delay caused the project manager or leading hand to be idle, Walton is only entitled to the costs it incurred in relation to those resources. Walton has not produced any costs records. Therefore, unless the Referee is satisfied that these resources were engaged in additional work, the Referee must allow nil for these resources. Illawarra submits, in particular, that the Referee cannot be satisfied as to the extent to which the project manager was engaged in additional work as a result of any or all of the alleged periods of delay.
119 It is common ground that the project manager worked on other jobs during the course of the subject works and was not engaged on the project full-time. No time sheets and very little other evidence of how the project manager was engaged at the material times have been adduced. Illawarra accepts that Mr Jerez was engaged on the project during the period of the alleged construction certificate delay but says that, during this time, he was progressing the contract works. He was not required to do any extra work during this period. He was not idle. His project management task was not increased. In these circumstances, no additional costs were incurred and none are payable as a result of the construction certificate delay. Illawarra concedes that other delay events, like the office works, asbestos and power delays, increased the project management task, as additional subcontracts, co-ordination and supervision may have been required, but says that there is simply no evidence of the quantum of extra work involved. It does not follow that because the Date for Practical Completion is extended by x days, that Mr Jerez's work expanded by the same number of days. Illawarra submits that without any way of quantifying the quantum of extra project work necessitated by any delays, Walton's claim for additional project management costs must fail.
120 Illawarra accepts that a leading hand was employed full-time for much of the project but says that there is no evidence that a leading hand was engaged during the period of the construction certificate delay, no evidence a leading hand carried out any work during the period of the asbestos delay and no evidence that the work of the leading hand expanded by the same number of days as the period for which the Date for Practical Completion was extended. Thus although Illawarra accepts that a leading hand was employed during this period and that Walton is entitled to the scheduled rate for any extra work carried out by the leading and is also entitled to the full cost of the leading hand for periods during which he was idle or under-employed, there is no basis on which the Referee can establish the number of days to which the scheduled rate can be applied and no known cost which the Referee can apply to the balance. For these reasons, Walton's claim for delay costs associated with the leading hand must also fail.
121 The evidence discloses that Mr Jerez ceased to be on site from, at the latest, December 2006 when he was engaged on another project (Coal Services project) and, indeed, Jerez's salary was no longer recorded as an expense of the Illawarra project from and including December 2006. (See Craig Walton affidavit dated 5 November 2008 paragraphs 46 and 47 and John Loke affidavit dated 5 November 2008 paragraph 10.) It is reasonable to assume that if Jerez was not being charged against the Illawarra Hotel project, then he was being charged against some other project, most likely the Coal Services project. Accordingly, no allowance should be made for Jerez's salary for any delay days allowed after 1 December 2006.
122 At V56, Walton claims the alleged costs of extra propping in Stage 2. As set out below, a proportion of the supply costs are time-based and are alleged to have been caused by the Asbestos delay and the Structural Steel delay. Illawarra submits that, as Walton should not have commenced propping before obtaining a hazardous materials report, any extra supply costs alleged to stem from the Asbestos delay were actually caused by Walton's default. Illawarra also submits that there is no evidence to support any finding that the Structural Steel delay extended the time for which the propping was required."
Walton's Submission in Reply
491 In reply, Walton submitted:
"36 The contract provided for "rates per day" of $675 for a project manager and $450 for a leading hand. These rates quantify Walton's entitlement to payment for project and site management. Those rates apply for each day that the works were delayed prior to Practical Completion.
37 In reply to Illawarra's submission at paragraph 119, the critical point is that management of the works occurred as required; it is not to the point whether or not that management took 8 hours each day. The daily rate does not change depending on how much work Mr Jerez had to do, it is a fixed sum which is payable under the contract regardless of how much work Mr Jerez had to do on any particular day of delay.
38 On top of the management rates is the preliminaries rate determined by Mr Makin which does not seem to be challenged."
Illawarra's Further Submission
492 In oral submissions, Illawarra conceded that it had not cross-examined Mr Makin on his opinion relating to the applicable daily rate to be applied to delay costs. Counsel said, however, that:
"where Mr Makin makes certain assumption, notwithstanding that he was not the subject of cross-examination, where those assertions don't have an appropriate factual basis, then very little weight should be attached to them".
493 Counsel elaborated on this, saying that, under the contract, Walton was entitled to the costs it actually incurred and not a product of a rate and a number of days. Counsel said:
"We would want to know what was paid and what the on costs are ... We would suggest that you, Madam Referee, to be satisfied that additional costs were incurred, would want to see evidence of those costs and we say that none has been adduced."
The Contract
494 The relevant sections of the contract were:
"36 DELAY OR DISRUPTION COSTS
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any of the events referred to in Clause 35.5 (b) (i), the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused by any other event for which payment of extra costs for delay or disruption is provided for in the Annexure or elsewhere in the Contract, the Principal shall pay to the Contractor such extra costs as are necessarily incurred by the Contractor by reason of the delay.
Nothing in Clause 36 shall-
(a) oblige the Principal to pay extra costs for delay or disruption which have already been included in the value of a variation or any other payment under the Contract; or
(b) limit the Principal's liability for damages for breach of contract."