[2023] VCAT 729
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-06-29
Original judgment source is linked above.
Question of law: Characterisation of land use; Extractive Industry; Meaning of rehabilitation; Clause 73.03 of the Monash Planning Scheme; Ordinary meaning; Read in context of planning scheme definition; Definition of use; Section 3 of the Planning and Environment Act 1987 (Vic); Real and substantial purpose; No use of land.
William Curt Thompson, Oksana Murashova Thompson & Others
Valente v Monash CC [2023] VCAT 729
Is the land use proposed by planning permit applications TPA/53179 and TPA/53477 properly characterised as Extractive industry as defined in clause 73.03 of the Monash Planning Scheme?
The activities proposed in the planning applications TPA/53179 and TPA/53477 are not characterised as use of the land for extractive industry as defined in clause 73.03 of the Monash Planning Scheme. Further, the activities proposed in the planning applications TPA 53179 and TPA 53477 do not comprise use of the land under the Monash Planning Scheme.
Alexandra Guild of counsel, instructed by Hall & Wilcox
For William Curt Thompson, Oksana Murashova Thompson & Others
Use and development of the land for preloading of earth and construction of buildings and works (temporary landfill gas venting trench) and alteration of access to a Transport Zone
Applications under section 82 of the Planning and Environment Act 1987 - to review the decision to grant a permit.
Use and development ... for preloading of earth and construction of buildings and works (temporary landfill gas venting trench) and alteration of access to a Transport Zone 2
The use and development of land for preloading of earth including buildings and works (drainage swales), the removal of native vegetation and alteration of access to a road in the Transport Zone 2.
Is the land use proposed by planning permit applications TPA/53179 and TPA/53477 properly characterised as Extractive industry as defined in clause 73.03 of the Monash Planning Scheme?
The activities proposed in the planning applications TPA 53179 and TPA 53477 are not characterised as use of the land for extractive industry because the activities do not comprise use of the land.
The return of disturbed land to a safe, stable, and sustainable condition capable of supporting the agreed end use. It broadly involves landform design, construction and shaping; materials characterisation, handling and placement; surface water management and revegetation
(a) is not likely to cause injury or illness; and > > (b) structurally, geotechnically and hydrogeologically sound; and > > (c) non-polluting; and > > (d) aligns with the principles of sustainable development.
use in relation to land includes use or proposed use for the purpose for which the land has been or is being or may be developed
Finding of Tribunal - need for caution (in characterising an activity) with utilising an innominate use ahead of a suitable defined land use term
[T]he duty of a court is to give the words of a statutory provision the meaning that the legislature is taken to have intended them to have. Ordinarily, that meaning (the legal meaning) will correspond with the grammatical meaning of the provision. But not always. The context of the words, the consequences of a literal or grammatical construction, the purpose of the statute or the canons of construction may require the words of a legislative provision to be read in a way that does not correspond with the literal or grammatical meaning.
The starting point for the ascertainment of the meaning of a statutory provision is the text of the statute whilst, at the same time, regard is had to its context and purpose. Context should be regarded at this first stage and not at some later stage and it should be regarded in its widest sense. This is not to deny the importance of the natural and ordinary meaning of a word, namely how it is ordinarily understood in discourse, to the process of construction. Considerations of context and purpose simply recognise that, understood in its statutory, historical or other context, some other meaning of a word may be suggested, and so too, if its ordinary meaning is not consistent with the statutory purpose, that meaning must be rejected.
[T]he modern approach to statutory interpretation (a) insists that the context be considered in the first instance, not merely at some later stage when ambiguity might be thought to arise, and (b) uses 'context' in its widest sense to include such things as the existing state of the law and the mischief which, by legitimate means such as those just mentioned, one may discern the statute was intended to remedy. Instances of general words in a statute being so constrained by their context are numerous.
Where permits are ambiguous, it certainly is correct that one can look at a permit application in order to discern what is meant by the permit; and, in this situation, one could also legitimately look at material before an appeals tribunal. Indeed in the Becton case, I held that one could look at a previous planning scheme provision where that was effectively the antecedent of the permit in issue.
...
The true rule is that evidence of surrounding circumstances is admissible to assist in the interpretation of the contract if the language is ambiguous or susceptible of more than one meaning. But it is not admissible to contradict the language of the contract when it has a plain meaning. Generally speaking facts existing when the contract was made will not be receivable as part of the surrounding circumstances as an aid to construction, unless they were known to both parties, although, as we have seen, if the facts are notorious knowledge of them will be presumed.
(footnotes omitted)
The activities proposed in the planning applications are not characterised as use of the land for extractive industry because the activities do not comprise use of the land.
development includes -
(a) the construction or exterior alteration or exterior decoration of a building; and
(b) the demolition or removal of a building or works; and
(c) the construction or carrying out of works; and
(d) the subdivision or consolidation of land, including buildings or airspace; and
(e) the placing or relocation of a building or works on land; and
(f) the construction or putting up for display of signs or hoardings;
development agency - see section 46GA;
...
works includes any change to the natural or existing condition or topography of land including the removal, destruction or lopping of trees and the removal of vegetation or topsoil;
Land forming, laser grading, levee banks, raised access roads and tracks, building pads, storage embankments, channel banks and drain banks and associated structures.
In deciding whether a proposed use falls within a specified land use it is necessary for the decision maker to determine the real and substantial purpose of the activity. This determination is 'not to be approached through a meticulous examination of the details of processes or activities, or through a precise cataloguing of individual items of goods dealt in, but by asking what, according to ordinary terminology, is the appropriate designation of the purpose being served by the use of the premises at the material date.'[23] In Cascone v Whittlesea Shire Council,[24] Ashley J summarised the relevant principles:
(1) In characterising the proposed use of premises it is always necessary to ascertain the purpose of the proposed use.
(2) Whilst intended use of premises, in the sense of activities, processes or transactions to be undertaken, will be useful in casting light upon the purpose of the proposed use, it is wrong to determine the relevant purpose simply by identifying activities, processes or transactions and then fitting them to some one or more uses as defined in a scheme.
(3) It is wrong to approach the ascertainment of purpose of proposed use on the footing that it must fit within one (or more) of the uses defined in a scheme; at least that is so where there is provision for innominate uses in the scheme.
(4) The ascertainment of purpose of a proposed use may yield the result that the purpose revealed very largely falls within a defined use. The extent to which it does not may be so trifling that it should be ignored. In that event the purpose as revealed should be taken to fall within the defined use.
(5) The ascertainment of purpose of a proposed use may yield the result that more than one separate and distinct purpose is revealed. In that event the question initially arises whether one is dominant. The further question that may arise is whether the lesser purpose or purposes are ancillary to the dominant purpose. If the answer to both questions is 'yes', and the dominant purpose is available as of right or is permitted, the lesser purpose or purposes are legitimised. Then, in planning terms, there is but one purpose. But if the answer to the first question is 'no', each revealed purpose must be available as of right or permitted, else there will be a breach of the scheme. The mere fact that one purpose is authorised will not prevent other revealed purposes from being prohibited.
(6) In resolving the problems of characterisation raised in the preceding pars (1) to (5) the preferable view, in my opinion, is that the adjectival phrase 'real and substantial' qualifying 'use' will always be nominally present. But it is unlikely to be of practical importance in many cases. It will always serve to emphasise that there is a distinction between 'purpose of use' and 'use' in the sense of activities, processes or transactions. It should not be used to cloud the potential for more than one purpose being revealed. It should not be thought to provide a basis for treating a combination of activities, processes or transactions as necessarily attracting the appellation of 'innominate use'. It is likely to be of practical importance in cases falling within pars (4) and (5) above.[25]
restoration to former health
restoration of rights, privileges or reputation
... that the meaning of rehabilitation in the context of extractive industry generally and in the context of the cl 73.03 definition is to be understood in the context of industry usage and the regulatory regime for extractive industries: rehabilitation means what ERR says it means. Either extractive industries rehabilitation is intended to have a 'technical' meaning informed by industry usage and the extractive industries regulatory regime, or that the 'ordinary meaning' of extractive industries rehabilitation is informed by industry usage and the regulatory regime.
This contention is borne out by consideration of the history of the definition of Extractive Industries...
Rather, the MRSD Act:
(a) requires the preparation of rehabilitation plans;
(b) requires implementation of rehabilitation plans;
(c) prescribes the content of rehabilitation plans; and
(d) requires a bond to secure rehabilitation.
Objective discernment of statutory purpose is integral to contextual construction. The requirement of s 15AA of the Acts Interpretation Act 1901 (Cth) that "the interpretation that would best achieve the purpose or object of [an] Act (whether or not that purpose or object is expressly stated...) is to be preferred to each other interpretation" is in that respect a particular statutory reflection of a general systemic principle. For:
"it is one of the surest indexes of a mature and developed jurisprudence not to make a fortress out of the dictionary; but to remember that statutes always have some purpose or object to accomplish, whose sympathetic and imaginative discovery is the surest guide to their meaning."
In the interpretation of a provision of an Act or subordinate instrument-
a construction that would promote the purpose or object underlying the Act or subordinate instrument (whether or not that purpose or object is expressly stated in the Act or subordinate instrument) shall be preferred to a construction that would not promote that purpose or object; and
Dictionary definitions may assist in identifying the range of possible meanings a word may bear in various contexts, but will not assist in ascertaining the precise meaning the word bears in a particular context.
The activities proposed in the planning applications TPA 53179 and TPA 53477 are not characterised as use of the land for extractive industry as defined in clause 73.03 of the Monash Planning Scheme. Further, the activities proposed in the planning applications TPA 53179 and TPA 53477 do not comprise use of the land under the Monash Planning Scheme.

(5) An environmental action notice applies notwithstanding anything to the contrary in -
(a) the Planning and Environment Act 1987 or any regulations, planning scheme or permit made, approved or granted under that Act;
[1] The submissions of the parties, any supporting exhibits given at the hearing, and the statements of grounds filed; have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[4] The date for compliance was extended at the commencement of the hearing.
[5] See report to council on 31 January 2023 at pages 13-15 in relation to the preloading of earth for drainage swales.
[6] See report to council on 31 January 2023 at page 18.
[10] See Thompson submission at [16].
[11] See Thompson submission at [18].
[13] See Thompson submission at [24].
[14] See Thompson submission at [28].
[21] See council submission at [65 and 65].
[22] [2022] VSC 588 at [23].
[23] Shire of Perth v O'Keefe [1964] HCA 37; (1964) 110 CLR 529, 535 (Kitto J); [1964] HCA 37.
[25] Ibid 190, quoted in Stanley Rural Community Inc v Stanley Pastoral Pty Ltd (2017) 54 VR 676, 694-5 [79] (the Court); [2017] VSCA 385.
[26] See respondent's submissions at [73-74].
[29] See page ix - Executive Summary of Audit.
[30] See page xii - Executive Summary of Audit.
Valente
Monash CC [2023] VCAT 729
(2014) 250 CLR 664
(2016) 91 NSWLR 439
(1964) 110 CLR 529
(2017) 54 VR 676